will county Committee-Capital Improvement.Graphic

Will County Leaders Debate New Construction to Escape $1.2 Million in Leases

Spread the love

Capital Improvements & IT Committee Meeting | March 2026

Article Summary: The Will County Capital Improvements and IT Committee is aggressively exploring options to consolidate county offices and exit leased properties, sparking a debate over where to build a new government campus and how to fund it.

Capital Improvements 5-Year Plan Key Points:

  • Will County currently utilizes approximately 65,000 square feet of leased space, costing taxpayers roughly $1.2 million annually.

  • A Master Plan Update in the agenda packet projects the county will need 118,000 square feet for the County Office Building and 101,040 square feet for Judicial Agencies by 2050.

  • Committee members are divided on whether to build a new facility on the site of the recently demolished old courthouse or expand the current county office campus.

  • A debt capacity report indicates the county could potentially issue up to $142.6 million in new bonds without increasing the overall annual debt service level.

The Will County Capital Improvements and IT Committee on Tuesday, March 3, 2026, waded into a complex debate over the future of the county’s physical footprint, driven by a desire to consolidate scattered departments and eliminate expensive rental leases.

Committee Chair Mica Freeman initiated the discussion by outlining her vision to bring currently displaced departments—such as the Public Defender, State’s Attorney, and Regional Office of Education—under a single, county-owned roof.

According to County Board Member Daniel J. Butler, the county’s reliance on leased spaces is currently a significant financial drain.

“We use 65,000 square feet of rental space and we paid $1.2 million for rental,” Butler said, noting that these costs were part of the original argument for attempting to save and expand the old 140,000-square-foot county courthouse before the board ultimately voted to demolish it.

“Building a new courthouse building in that exact same location would be the height of folly. I mean, really, tearing down the building and building it right back,” Butler remarked, though he acknowledged the urgent need to address the spatial deficit.

Member Steve Balich argued that the most logical and cost-effective long-term solution is to construct a new, basic facility—potentially on the site of the old courthouse—to eliminate the rental overhead.

“You just build a two-story building, steel, it’s cheaper, and move everybody in there, move everybody into different places in the building, and we’ll save a ton of money in rental,” Balich said. “We don’t really need to have bonds because we’ll be able to take the rent money to pay for the cost of a building.”

However, Member Jacqueline Traynere strongly opposed any plan that might increase the tax burden, and pushed back against utilizing the old courthouse site due to historical construction hurdles.

“I’m not in favor of raising property taxes to pay for new buildings,” Traynere said. She advocated for constructing a smaller, expandable building on the current County Office Building campus instead. “We could put parking at the bottom of the building, but we can’t go down deep because that’s limestone. That was the problem we had with the jail. Building anywhere in that general vicinity costs us a lot of extra money.”

While the committee did not take a formal vote, the agenda packet included deep contextual data to inform their upcoming decisions. A Master Plan Update provided by Wight projects that by the year 2050, the County Office Building departments will require 118,000 Departmental Gross Square Feet (DGSF), up from their current 62,260 DGSF. Similarly, Judicial Agency Departments will see their needs grow from 88,841 DGSF to 101,040 DGSF.

To finance potential construction, the committee referenced a recent debt profile from Speer Financial, included in the packet. The report shows that as older bonds are paid off, Will County will experience a significant drop in outstanding debt payments after 2026 and 2030. By structuring a split-issuance of General Obligation Alternate Revenue Source bonds, the county could theoretically capture up to $142.6 million in project funds without raising its current $25 million annual debt service target.

Member Mark V. Revis suggested that once staff returns with concrete price-per-square-foot estimates, the board should convene a special meeting to ensure all members are aligned before moving forward.

“This is one of those items that is going to cross the threshold where everybody is going to want to have a firm understanding of it before they cast their vote,” Revis said.

Leave a Comment





Latest News Stories

Will County Board Land Use Committee Graphic.1

Committee Approves Frankfort Township Gaming Bar on Split Vote

Will County Land Use & Development Committee Meeting | November 6, 2025 Article Summary: Despite an objection from Frankfort Township, a proposed video gaming bar on West St. Francis Road is...
Will County Board Land Use Committee Graphic.3

Crete Township Senior Group Home Gets Unanimous Committee Support

Will County Land Use & Development Committee Meeting | November 6, 2025 Article Summary: A proposal to convert a single-family home in Crete Township into a shared living facility for up...
Will County Board Land Use Committee Graphic.4

Beecher-Area Rezoning and Variances Approved to Legalize Structure

Will County Land Use & Development Committee Meeting | November 6, 2025 Article Summary: The Will County Land Use and Development Committee approved a rezoning and two variances for a property...
Will County Board Land Use Committee Graphic.2

Committee Approves Wilton Township Land Division Despite Spot Zoning Concerns

Will County Land Use & Development Committee Meeting | November 6, 2025 Article Summary: The Will County Land Use and Development Committee approved a request to rezone a 1.75-acre parcel in...
Meeting-Briefs

Meeting Summary and Briefs: New Lenox Village Board for October 27, 2025

New Lenox Village Board Meeting | October 27, 2025 The New Lenox Village Board meeting on Monday, October 27, 2025, was highlighted by the preliminary approval of a new restaurant,...
Meeting Briefs

Meeting Summary and Briefs: Will County Capital Improvements & IT Committee for November 4, 2025

Will County Capital Improvements & IT Committee Meeting | November 4, 2025 The Will County Capital Improvements & IT Committee on Tuesday, November 4, 2025, reviewed a successful bond refinancing...
New-Lenox-Village-Board

New Lenox Announces 5.51% Increase in 2025 Property Tax Levy

New Lenox Village Board Meeting | November 10, 2025 Article Summary: The Village of New Lenox has proposed a 2025 property tax levy of just over $4 million, which represents...
Glock: Judge’s OK of Chicago’s anti-gun lawsuit questionable, at best

Glock: Judge’s OK of Chicago’s anti-gun lawsuit questionable, at best

By Jonathan Bilyk | Legal NewslineThe Center Square Firearms maker Glock is asking for permission to appeal a Cook County judge's ruling allowing the city of Chicago to continue its...
Illinois quick hits: DHS responds to migrant release order

Illinois quick hits: DHS responds to migrant release order

By Jim Talamonti | The Center SquareThe Center Square DHS responds to migrant release order The U.S. Department of Homeland security issued a statement after a federal judge in Chicago...
Dutch Bros. Coffee logo

New Gas N Wash and Dutch Bros. Coffee Projects Advance in New Lenox

New Lenox Village Board Meeting | November 10, 2025 Article Summary: The New Lenox Village Board approved plans for two major commercial developments, a Gas N Wash on Route 6...
The Patio Restaurant

New Lenox Approves Final Plans for The Patio Restaurant, Construction to Begin in December

New Lenox Village Board Meeting | November 10, 2025 Article Summary: The New Lenox Village Board gave final approval to "The Patio," a new restaurant planned for the southwest corner...
New-Lenox-Village-Board

New Lenox Awards $1.18 Million Contract for North Side Water Main Replacement

New Lenox Village Board Meeting | October 27, 2025 Article Summary: As part of a multi-phase plan to upgrade infrastructure on the village's north side, the New Lenox Village Board awarded...
Meeting Briefs

Meeting Summary and Briefs: Will County Public Works & Transportation Committee for November 2025

Will County Public Works & Transportation Committee Meeting | November 2025 The Will County Public Works & Transportation Committee on Tuesday approved a landmark agreement to consolidate the Central Will...
Screenshot 2025-11-06 at 3.37.39 PM

Will County Committee Members Debate Future Capital Priorities, Clash on Borrowing

Will County Capital Improvements & IT Committee Meeting | November 4, 2025 Article Summary: After learning Will County could borrow over $100 million for new projects, members of the Capital Improvements...
Meeting Briefs

Meeting Summary and Briefs: Will County Planning and Zoning Commission for November 4, 2025

Will County Planning and Zoning Commission Meeting | November 4, 2025 The Will County Planning and Zoning Commission on Tuesday, November 4, 2025, considered a series of homeowner requests for...