New Lenox Awards $1.18 Million Contract for North Side Water Main Replacement
New Lenox Village Board Meeting | October 27, 2025
Article Summary: As part of a multi-phase plan to upgrade infrastructure on the village’s north side, the New Lenox Village Board awarded a contract for over $1.18 million to P.T. Ferro Construction Co. for the replacement of water mains on Cooper, Ash, and Wood Streets. The project is the first of three parts aimed at modernizing the area’s water system.
Water Main Project Key Points:
-
The board approved a bid of $1,187,327 from P.T. Ferro Construction Co., which was the lowest of 13 bidders and came in under budget.
-
The project targets the replacement of aging water mains on Cooper, Ash, and Wood Streets.
-
The contract award is contingent on the village’s expected loan approval from the Illinois Environmental Protection Agency (IEPA).
The New Lenox Village Board on Monday, October 27, 2025, took a major step in its plan to upgrade aging infrastructure by awarding a nearly $1.2 million contract for water main replacements on the north side of the village.
The board approved a bid of $1,187,327 from P.T. Ferro Construction Co. to replace water mains on Cooper, Ash, and Wood Streets. The bid was the lowest of 13 submitted and was under the village’s budget for the project. The contract is contingent upon final loan approval from the Illinois Environmental Protection Agency (IEPA).
This work represents the first phase of a three-part initiative to systematically replace water infrastructure in the area. Public Works staff expressed confidence in P.T. Ferro, which has successfully completed projects for the village in the past.
In a related move, the board also approved a proposal for Christopher Burke Engineering to handle the design of the second phase of the project. This next stage will focus on replacing water mains on G-Lane, Hawthorne Lane, and Fur Lane, with construction anticipated to begin in the spring of 2027.
Latest News Stories
Meeting Summary and Briefs: New Lenox Village Board for June 8, 2026
Meeting Summary and Briefs: Will County Board Executive Committee for June 11, 2026
Will County Mental Health Board Touts Crisis Program in Quarterly Report
Meeting Summary and Briefs: Will County Board Finance Committee for June 2, 2026
New Lenox Approves $92,954 Purchase for Railroad Quiet Zone Delineators
Will County Coroner Reports Nearly 8,000 Death Investigations in 2025
Will County Committee Advances Three New Assistant State’s Attorneys
Will County Committee Advances $75,000 for U of I Extension
Baldermann Credits Public Pressure for Stalling State Housing ‘Build Plan’
Will County Committee Pulls Single-Member District Referendum
Will County Land Bank Clears Committee With Two Amendments
Will County Committee Advances $179,000 Coroner Cot Purchase