Will County Board Graphic.03

Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Spread the love

Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Leave a Comment





Latest News Stories

Will County Board Graphic.01

Meeting Summary and Briefs: Public Health & Safety Committee for March 5, 2026

Public Health & Safety Committee Meeting | March 5, 2026 The Will County Public Health and Safety Committee met on Thursday to address critical infrastructure and wellness updates across the...
Sheriff Scam Alert Graphic

Will County Officials Warn of Zoom Court Scam Targeting Defendants for Fraudulent Dismissal Fees

Article Summary: Will County officials have issued an alert regarding a fraudulent scheme where scammers infiltrate courtroom Zoom sessions to extort money from defendants. The perpetrators use private chat features...
Screenshot 2026-05-10 at 4.08.39 PM

New Lenox Board Approves Nearly $325,000 in Urgent Infrastructure and Sports Complex Upgrades

New Lenox Village Board of Trustees Meeting | March 9, 2026 Article Summary: The New Lenox Village Board authorized substantial capital expenditures to address failing roadway infrastructure and significantly enhance...
Will County Board Land Use Committee Graphic.3

Will Land Use Committee Evaluates Multi-Million Dollar Buyout for Flooded Harris Drive Homes

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: The Will County Land Use and Development Committee is exploring a multi-million-dollar buyout program for several homes...
Will County Board Graphic.04

Behavioral Health Division Drops Wait Times, Reports Zero Opioid Deaths in February

Public Health & Safety Committee Meeting | March 5, 2026 Article Summary: Will County’s Behavioral Health Division reported significant operational improvements, including a near-elimination of wait times for therapy and...
Will County Board Graphic.03

Harris Drive Residents Plead for County Intervention Amid Failing Septic Systems and Flooding

Public Health & Safety Committee Meeting | March 5, 2026 Article Summary: Residents of Harris Drive appealed to the Public Health and Safety Committee for help with severe seasonal flooding...
Police Crime

Will County Sheriff’s Office Investigates Fatal Hit-and-Run in Homer Glen

Article Summary: The Will County Sheriff’s Office is seeking the public's assistance in identifying a driver involved in a fatal hit-and-run crash in Homer Glen that left a pedestrian dead....
will county Committee-Public Health & Safety.Graphic

Federal Funding Freezes Threaten Will County Public Health Programs Amid Ongoing Lawsuits

Public Health & Safety Committee Meeting | March 5, 2026 Article Summary: Will County health officials are bracing for potential service disruptions as they monitor multiple federal lawsuits surrounding frozen...
Will County Board Federal Agenda

Board Splits Along Party Lines to Approve 2026 Federal Legislative Agenda

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board adopted its 2026 Federal Legislative Agenda in a 10-9 vote, establishing the county's priorities for lobbying efforts...
Screenshot 2026-05-10 at 3.41.28 PM

Meeting Summary and Briefs: New Lenox Village Board of Trustees for February 23, 2026

New Lenox Village Board of Trustees Meeting | February 23, 2026 The New Lenox Village Board of Trustees advanced several major infrastructure and development initiatives during its regular meeting on...
Will County Board Graphic.01

Meeting Summary and Briefs: Will County Landfill Committee for February 10, 2026

Will County Landfill Committee Meeting | February 10, 2026 The Will County Landfill Committee met on Tuesday to address legal preparations for the upcoming landfill expansion and operational needs at...
Will County Board Graphic.03

Meeting Summary and Briefs: Will County Board for February 19, 2026

Will County Board Meeting | February 19, 2026 Meeting SummaryThe Will County Board meeting on Thursday, February 19, 2026, was marked by significant zoning decisions, including the unanimous rejection of...
Will County Board Graphic.04

Board Approves Joliet Township Clean Fill Facility Despite Environmental Objections

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board approved a map amendment and special use permit for a Clean Construction and Demolition Debris (CCDD) facility...
solar panels photovoltaics in solar farm

Will County Board Unanimously Rejects Controversial Solar Farm in Troy Township

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board unanimously rejected a special use permit for a commercial solar energy facility near Shorewood following strong opposition...
Will County Board Graphic.03

Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Will County Landfill Committee Meeting | February 10, 2026 Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to...