Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Spread the love

Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Leave a Comment





Latest News Stories

New Lenox Village Board Graphic.1

Meeting Summary and Briefs: New Lenox Village Board for June 8, 2026

New Lenox Village Board Meeting | June 8, 2026 The New Lenox Village Board moved through a lengthy agenda on Monday, June 8, 2026, with Trustees Lindsay Scalise and Amy...
Will County Board Graphic.04

Meeting Summary and Briefs: Will County Board Executive Committee for June 11, 2026

Will County Board Executive Committee Meeting | June 11, 2026 The Will County Board Executive Committee met Thursday, June 11, 2026, in Joliet, advancing a slate of items to the...
Will County Board Graphic.02

Will County Mental Health Board Touts Crisis Program in Quarterly Report

Will County Board Executive Committee Meeting | June 11, 2026 Article Summary: The Will County Community Mental Health Board's quarterly report to the Executive Committee on Thursday, June 11, 2026,...
Will County Finance Logo

Meeting Summary and Briefs: Will County Board Finance Committee for June 2, 2026

Will County Board Finance Committee Meeting | June 2, 2026 The Will County Board Finance Committee took up a short slate of budget and appropriation items at its regular meeting...
New Lenox Village Board Graphic.1

New Lenox Approves $92,954 Purchase for Railroad Quiet Zone Delineators

New Lenox Village Board Meeting | June 8, 2026 Article Summary: The New Lenox Village Board on June 8 waived formal bidding and approved a purchase of about $92,954 for...
Will County Board Graphic.03

Will County Coroner Reports Nearly 8,000 Death Investigations in 2025

Will County Board Executive Committee Meeting | June 11, 2026 Article Summary: Will County Coroner Laurie Summers presented her 2025 annual report to the Executive Committee on Thursday, June 11,...
Will County Board Graphic.01

Will County Committee Advances Three New Assistant State’s Attorneys

Will County Board Executive Committee Meeting | June 11, 2026 Article Summary: The Will County Board Executive Committee on Thursday, June 11, 2026, recommended increasing the authorized number of assistant...
Will County Finance Logo

Will County Committee Advances $75,000 for U of I Extension

Will County Board Finance Committee Meeting | June 2, 2026 Article Summary: The Will County Board Finance Committee on Tuesday, June 2, 2026, voted to advance a resolution committing $75,000...
New Lenox Village Board Graphic.1

Baldermann Credits Public Pressure for Stalling State Housing ‘Build Plan’

New Lenox Village Board Meeting | June 8, 2026 Article Summary: Mayor Tim Baldermann used his June 8 report to the New Lenox Village Board to detail what he described...
Will County Board Graphic.03

Will County Committee Pulls Single-Member District Referendum

Will County Board Executive Committee Meeting | June 11, 2026 Article Summary: The Will County Board Executive Committee on Thursday, June 11, 2026, removed a proposed referendum on single-member county...
Will County Board Graphic.04

Will County Land Bank Clears Committee With Two Amendments

Will County Board Executive Committee Meeting | June 11, 2026 Article Summary: The Will County Board Executive Committee on Thursday, June 11, 2026, recommended creating a Will County Land Bank...
Will County Finance Logo

Will County Committee Advances $179,000 Coroner Cot Purchase

Will County Board Finance Committee Meeting | June 2, 2026 Article Summary: The Will County Board Finance Committee on Tuesday, June 2, 2026, voted to advance a request authorizing $179,000...
New Lenox Village Board Graphic.1

147-Room Hilton Hotel Approved Near New Lenox Crossroads Sports Complex

New Lenox Village Board Meeting | June 8, 2026 Article Summary: The New Lenox Village Board on June 8 approved a site plan and set surety for a 147-room Hilton...
New Lenox Village Board Graphic.1

New Lenox Advances Cedar Pointe Annexation and Rezoning on First Read

New Lenox Village Board Meeting | June 8, 2026 Article Summary: The New Lenox Village Board held a public hearing and first readings June 8 on ordinances that would annex,...
Will County Board Graphic.01

Will County Board Members Spar Over Wheatland Township Mental Health Grant

Will County Board Executive Committee Meeting | June 11, 2026 Article Summary: A $155,000 mental health grant to Wheatland Township drew sharp questioning at the Will County Board Executive Committee...