Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Spread the love

Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Today Jun 10
Mostly Cloudy then Slight Chance Showers And Thunderstorms
88° 60°

Mostly Cloudy then Slight Chance Showers And Thunderstorms

💨 10 to 20 mph 💧 20%

Leave a Comment





Latest News Stories

Arizona recommends measles vaccine during outbreak

Arizona recommends measles vaccine during outbreak

By Chris WoodwardThe Center Square Arizona is recommending vaccinations to combat the state's worst measles outbreak since the 1990s. The latest update this week showed the state has 111 cases...
Govt. shutdown leads to over 800 flights cancelled, number growing

Govt. shutdown leads to over 800 flights cancelled, number growing

By Thérèse BoudreauxThe Center Square As the government shutdown drags into its 38th day and forced flight reductions begin taking effect, the number of daily flight cancellations Americans are experiencing...
Illinois approves $1.5B transit package, funding for long-delayed projects

Illinois approves $1.5B transit package, funding for long-delayed projects

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Illinois lawmakers approved a $1.5 billion transit package, including long-delayed Moline-to-Chicago rail, hailed by Democrats as...
Supreme Court allows Trump to withhold partial SNAP payment

Supreme Court allows Trump to withhold partial SNAP payment

By Brett RowlandThe Center Square The Supreme Court said Friday that the Trump administration could withhold a partial payment for the federal food benefits program amid the longest-ever government shutdown....
Illinois quick hits: State EPA looks to fund EV charging stations; Tax Foundation says mayor's proposal would hinder employment;

Illinois quick hits: State EPA looks to fund EV charging stations; Tax Foundation says mayor’s proposal would hinder employment;

By Jim Talamonti | The Center SquareThe Center Square State EPA looks to fund EV charging stations The Illinois Environmental Protection Agency (EPA) has announced an Electric Vehicle (EV) Charging...
Congressional Perks: Committees, caucuses cost $50 million since 2019

Congressional Perks: Committees, caucuses cost $50 million since 2019

By Arthur KaneThe Center Square Since 2019, partisan and special interest caucuses and coalitions in the U.S. House spent at least $50 million for staff, food, travel and other expenses,...
Screenshot 2025-11-06 at 4.17.15 PM

Federal Lobbyists Brief Will County on Government Shutdown, Warn of SNAP and TSA Disruptions

Meeting Summary and Briefs: Will County Legislative Committee for November 4, 2025 Article Summary: Will County’s federal lobbyists reported that the ongoing government shutdown, now the longest in U.S. history, is...
New-Lenox-Village-Board.2

New Lenox Residents Plead for Help in Escalating Neighborhood Dispute

New Lenox Village Board Meeting | October 27, 2025 Article Summary: A New Lenox couple made an emotional plea to the Village Board, detailing a year-long dispute with a neighbor that...
Will County Logo Graphic

Commission Approves Mokena-Area Garage Variance Over Village’s Objection

Will County Planning and Zoning Commission Meeting | November 4, 2025 Article Summary: The Will County Planning and Zoning Commission approved a variance for a new garage in unincorporated Frankfort Township...
Screenshot 2025-11-05 at 4.02.49 PM

Will County Committee Advances Gougar Road Bridge Project with Over $540,000 in Agreements

Will County Public Works & Transportation Committee Meeting | November 2025 Article Summary: The Will County Board approved two key agreements for the Gougar Road bridge project in New Lenox,...
Joliet-Junior-college.-Graphic-Logo.4

JJC Receives Surprise $1.9 Million from IRS Employee Retention Credit

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryJoliet Junior College has received an unexpected $1.9 million windfall from the federal Employee Retention Credit (ERC), a...
Joliet-Junior-college.-Graphic-Logo.2

JJC Advances ERP Modernization with New Vendor and Two-Year Budget

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryJoliet Junior College is entering the next phase of its Enterprise Resource Planning (ERP) system overhaul, with the...
new-lenox-fire-district-stations.3

Station 62 Remodel Advances as Fire District Seeks to Waive Permit Fees

New Lenox Fire Protection District Meeting | September 2025 Article Summary: The planned remodel of New Lenox Fire Station 62 is moving into its next phase, with officials having completed...
Screenshot 2025-11-06 at 4.17.02 PM

Will County Committee Shapes 2026 Legislative Agendas on Housing, Energy, and Health

Meeting Summary and Briefs: Will County Legislative Committee for November 4, 2025 Article Summary: The Will County Legislative Committee advanced key priorities for its 2026 state and federal legislative agendas, focusing...
New-Lenox-School-122.3

New Lenox School District 122 Considers Community Solar Program Promising $55K in Annual Savings

New Lenox School District 122 Meeting | September 2025 Article Summary: New Lenox School District 122 is exploring a 20-year subscription to a community solar program that could save the...