Executive Committee Advances $28.7 Million BNSF Bridge Project for Lorenzo Road
Will County Executive Committee Meeting | February 11, 2026
Article Summary: The Executive Committee approved an agreement with BNSF Railway to construct a grade separation bridge on Lorenzo Road in Wilmington. The railroad will contribute over $15 million toward the project and provide a one-time maintenance payment to the county.
Lorenzo Road Bridge Key Points:
-
Project: Construction of a grade separation bridge carrying Lorenzo Road (CH 80) over the BNSF Railroad tracks.
-
Location: 1.25 miles west of I-55 in County Board District 1.
-
Total Cost: The estimated total project cost is $28,717,523.80.
-
Railroad Contribution: BNSF will reimburse the county 100% of costs after the execution of ICC funds, up to a cap of $15,102,943.80.
-
Maintenance Fee: BNSF will pay Will County a one-time maintenance fee of $675,003.28 for the useful life of the overpass.
The Will County Board Executive Committee on Wednesday, February 11, 2026, approved Resolution 26-046, authorizing an agreement between the County and BNSF Railway for a major infrastructure project on Lorenzo Road.
The project involves constructing a bridge to separate the grade of Lorenzo Road (County Highway 80) from the BNSF rail line, located approximately 1.25 miles west of Interstate 55. The project aims to eliminate the at-grade crossing, improving safety and traffic flow in the heavy industrial corridor.
According to the agreement attached to the agenda, the total estimated cost of construction is $28,717,523.80. Under the terms of the deal, BNSF Railway will contribute significantly to the project. Once $12 million in Illinois Commerce Commission (ICC) funds are executed, BNSF will reimburse the county for remaining costs up to a cap of $15,102,943.80.
Additionally, the agreement stipulates that BNSF will provide a one-time lump sum payment of $675,003.28 to the county to cover future maintenance costs for the structure over its useful life. The county will be responsible for maintaining the roadway, bridge structure, and drainage.
The agreement requires the contractor to maintain strict safety clearances during construction, including 25 feet horizontally from the track centerline.
The measure was moved by Member Jacqueline Traynere and seconded by Member Denise Winfrey. It passed unanimously.
Latest News Stories
New Lenox Approves 24/7 Cybersecurity Monitoring
New Lenox Buried Under 12.3 Inches of Snow; Sub-Zero Cold Snap Approaching Friday
Frankfort Turns to County for Wildlife & Dangerous Animal Control
JJC Foundation Director Kristin Mulvey to Retire After 25 Years of Transformative Leadership
New Lenox Township Hires Full-Time Maintenance Position Amid Surging Food Pantry Demand
Lincoln-Way 210 Switches to Under Armour for Athletic Apparel
Baldermann Defends Investment Strategy, Blasts Social Media Critics
Crete “Group Care” Home Approved for Senior Living
Meeting Summary and Briefs: New Lenox School District 122 for October 21, 2025
New Lenox Library Reviews Strategic Plan Draft Following Robust Community Feedback
Meeting Summary and Briefs: New Lenox Community Park District for October 15, 2025
New Bar Approved in Frankfort Despite Board Opposition
JJC Board Approves Grundy County Land Purchase Amid Heated Debate