Executive Committee Advances $28.7 Million BNSF Bridge Project for Lorenzo Road
Will County Executive Committee Meeting | February 11, 2026
Article Summary: The Executive Committee approved an agreement with BNSF Railway to construct a grade separation bridge on Lorenzo Road in Wilmington. The railroad will contribute over $15 million toward the project and provide a one-time maintenance payment to the county.
Lorenzo Road Bridge Key Points:
-
Project: Construction of a grade separation bridge carrying Lorenzo Road (CH 80) over the BNSF Railroad tracks.
-
Location: 1.25 miles west of I-55 in County Board District 1.
-
Total Cost: The estimated total project cost is $28,717,523.80.
-
Railroad Contribution: BNSF will reimburse the county 100% of costs after the execution of ICC funds, up to a cap of $15,102,943.80.
-
Maintenance Fee: BNSF will pay Will County a one-time maintenance fee of $675,003.28 for the useful life of the overpass.
The Will County Board Executive Committee on Wednesday, February 11, 2026, approved Resolution 26-046, authorizing an agreement between the County and BNSF Railway for a major infrastructure project on Lorenzo Road.
The project involves constructing a bridge to separate the grade of Lorenzo Road (County Highway 80) from the BNSF rail line, located approximately 1.25 miles west of Interstate 55. The project aims to eliminate the at-grade crossing, improving safety and traffic flow in the heavy industrial corridor.
According to the agreement attached to the agenda, the total estimated cost of construction is $28,717,523.80. Under the terms of the deal, BNSF Railway will contribute significantly to the project. Once $12 million in Illinois Commerce Commission (ICC) funds are executed, BNSF will reimburse the county for remaining costs up to a cap of $15,102,943.80.
Additionally, the agreement stipulates that BNSF will provide a one-time lump sum payment of $675,003.28 to the county to cover future maintenance costs for the structure over its useful life. The county will be responsible for maintaining the roadway, bridge structure, and drainage.
The agreement requires the contractor to maintain strict safety clearances during construction, including 25 feet horizontally from the track centerline.
The measure was moved by Member Jacqueline Traynere and seconded by Member Denise Winfrey. It passed unanimously.
Latest News Stories
P&Z Commission: Peotone Area Variances Forwarded for Garage and Pole Barn
Peotone License Plate Camera Renewal Sparks Privacy Debate in Public Works Committee
Joliet Unity Movement Criticizes Board’s Handling of Cannabis Tax Revenue
Safety Upgrades Planned for Wilmington-Peotone Road; Gas Line Proposal Rejected
Tensions Flare as Board Members Clash Over Budget Process and Protocol
Will County Board Approves $2.7 Million Reserve Draw to Finalize 0% Tax Levy
Meeting Summary and Briefs: New Lenox Township for October 2025
Meeting Summary and Briefs: New Lenox Public Library District for October 2025
Meeting Summary and Briefs: Village of New Lenox for Nov. 24, 2025
Meeting Summary and Briefs: Lincoln-Way Community High School District 210 for November 20, 2025
Lincoln-Way Board Approves Tutoring Service for Hospitalized Students
New Lenox Becomes First Community to Adopt “Tribute to Valor” Resolution