Will County Landfill Committee Meeting | Jan. 13, 2026

Article Summary: The Landfill Committee voted to move forward with engineering estimates for a fourth compressor at the Prairie View Renewable Natural Gas (RNG) facility. The $1.8 million investment aims to reduce downtime and increase revenue, despite concerns about funding sources and timing.

RNG Plant Key Points:

  • Downtime Costs: Data shows that feed compressor failures account for nearly 36% of plant downtime, costing the county an estimated $600,000 annually in lost revenue.

  • Proposed Solution: Installing a fourth compressor would ensure three units are always operational, maximizing gas production and revenue. The estimated cost is $1.8 million with a 3-5 year return on investment.

  • Budget Concerns: The purchase was not included in the current fiscal year budget. Officials discussed using remaining funds from the previous year or splitting the cost across two budget cycles due to a 46-week lead time for the equipment.

Will County officials are taking steps to boost efficiency and revenue at the Prairie View Renewable Natural Gas (RNG) plant by pursuing the addition of a fourth feed compressor.

At the Landfill Committee meeting on Tuesday, January 13, 2026, Dave Hartke, Director of the Resource Recovery & Energy Division, presented data highlighting the financial impact of equipment failures. The facility’s three existing compressors are the primary cause of outages, leading to significant revenue losses.

“If we have three feed compressors operating at all times… we’re going to be producing closer to 27 to 2900 mm BTUs,” Hartke explained, noting this would allow the plant to hit higher revenue tiers faster each month.

The proposed fourth unit, estimated at $1.8 million fully installed, would provide redundancy. However, the plan faced scrutiny regarding its financing. Board Member Sherry Newquist questioned the timing, noting, “This kind of stuff is so much easier to deal with during the budget process.”

Hartke admitted the request was not in the original budget due to a prior focus on austerity. “I wasn’t quite expecting the response… that we should move forward with it,” he said, referencing earlier informal discussions with committee leadership.

Despite the budget hurdle, the committee saw the long-term value. With a 46-week lead time for the equipment, Finance Director Marcy indicated the cost could potentially be split across two fiscal years.

Board Member Jim Richmond emphasized the need for a deeper analysis before cutting a check. “This is a massive business decision… We need to actually look at that plant and make sure that it is spec’d properly from the front door to the back door,” Richmond said.

Ultimately, the committee voted unanimously to authorize staff to proceed with obtaining firm engineering costs and a project plan, which will then be brought back for final financial approval.

Leave a Comment





Latest News Stories

Screenshot 2025-10-25 at 10.49.15 AM

Frankfort Township Board Objects, but County Commission Recommends Bar with Video Gaming

Will County Planning and Zoning Commission Meeting | October 21, 2025 Article Summary: Despite a formal objection from the Frankfort Township Board, the Will County Planning and Zoning Commission recommended...
Screenshot 2025-10-25 at 10.49.23 AM

Senior Shared Housing Facility Recommended for Approval in Crete Township

Will County Planning and Zoning Commission Meeting | October 21, 2025 Article Summary: The Will County Planning and Zoning Commission has recommended approval for a special use permit that would...
Screenshot 2025-10-25 at 10.49.32 AM

Crete Township ‘Tiny Home’ Owner Appeals Permit Denial

Will County Planning and Zoning Commission Meeting | October 21, 2025 Article Summary: A Crete Township property owner has appealed to the Will County Planning and Zoning Commission after being...
Will County Finance Logo

Will County Finance Committee Forwards 1.75% Compromise Property Tax Levy to Full Board

Will County Finance Committee Forwards 1.75% Compromise Property Tax Levy to Full Board Article Summary:The Will County Board’s Finance Committee on Tuesday, November 12, 2025, narrowly approved a series of...
Screenshot 2025-11-21 at 10.19.55 AM

Lincoln-Way 210 Receives Clean Audit, Financial Profile Score Downgraded to ‘Review’

Lincoln-Way Community High School District 210 Meeting | November 20, 2025 Article Summary: Lincoln-Way District 210 received a clean, unmodified opinion for its Fiscal Year 2025 audit, the highest rating possible....
Will County P&Z Logo Planning Zoning.2

Committee Grants Lenox Solar Farm Project Six-Month Variance Extension

Will County Planning and Zoning Commission Meeting | November 18, 2025 Article Summary:The Will County Planning and Zoning Commission has approved a 180-day extension for variances tied to a commercial...
Will County Logo Graphic

Speed Limits Lowered in Green Garden and Frankfort Neighborhoods

Will County Board Meeting | November 2025 Article Summary: The Will County Board adopted ordinances to establish new, lower speed limits in specific areas of Green Garden and Frankfort Townships....
Will County Board Graphic.02

Engineering Firm Hired for Gougar Road Bridge Replacement

Will County Board Meeting | November 2025 Article Summary: The Will County Board authorized a $301,000 contract for the design of a new bridge carrying Gougar Road over the Canadian...
Will County Board Graphic.03

Unpermitted Log Cabin and Stage Prompt Rezoning in Beecher

Will County Board Meeting | November 2025 Article Summary: The Will County Board approved a zoning map amendment and variances for a property in Beecher to bring existing unpermitted structures...
New-Lenox-School-122.2

New Lenox School District 122 Receives ‘Clean’ Audit for Fiscal Year 2025

New Lenox School District 122 Meeting | October 21, 2025 Article Summary: New Lenox School District 122 has received an "unmodified opinion"—the highest level of assurance—on its 2024-2025 annual financial...
new-lenox-fire-district-stations.2

New Lenox Fire District Promotes Two to Lieutenant, Swears In Two Firefighters

New Lenox Fire Protection District Meeting | October 2025 Article Summary: The New Lenox Fire Protection District celebrated the career advancements of four members during a swearing-in ceremony at its...
New Lenox Park District

‘Empty Bowls’ Event Success Highlights Robust Fall Programs for New Lenox Park District

New Lenox Community Park District Meeting | October 15, 2025 Article Summary: The New Lenox Community Park District's fall season was highlighted by a successful "Empty Bowls" charity event that...
solar panels photovoltaics in solar farm

New Lenox to Host Large Pollinator-Friendly Solar Farm

Will County Board Meeting | November 2025 Article Summary: The Will County Board unanimously approved a special use permit for a commercial solar energy facility spanning approximately 63 acres in...
joliet junior college logo

JJC Receives Clean Audit, Reports $21.6 Million Increase in Net Position

Joliet Junior College Meeting | November 12, 2025 Article Summary:Joliet Junior College received a "clean unmodified audit opinion" for the fiscal year ending June 30, 2025, the highest level of...
Poll: Majority of Americans still support legal immigration

Poll: Majority of Americans still support legal immigration

By Andrew RiceThe Center Square A majority of Americans say that legal immigration is good for the United States, according to a new poll commissioned by The Center Square. The...