Will County Board Graphic.03

Landfill Committee Advances Plan to Purchase Fourth Compressor for RNG Plant

Spread the love

Will County Landfill Committee Meeting | Jan. 13, 2026

Article Summary: The Landfill Committee voted to move forward with engineering estimates for a fourth compressor at the Prairie View Renewable Natural Gas (RNG) facility. The $1.8 million investment aims to reduce downtime and increase revenue, despite concerns about funding sources and timing.

RNG Plant Key Points:

  • Downtime Costs: Data shows that feed compressor failures account for nearly 36% of plant downtime, costing the county an estimated $600,000 annually in lost revenue.

  • Proposed Solution: Installing a fourth compressor would ensure three units are always operational, maximizing gas production and revenue. The estimated cost is $1.8 million with a 3-5 year return on investment.

  • Budget Concerns: The purchase was not included in the current fiscal year budget. Officials discussed using remaining funds from the previous year or splitting the cost across two budget cycles due to a 46-week lead time for the equipment.

Will County officials are taking steps to boost efficiency and revenue at the Prairie View Renewable Natural Gas (RNG) plant by pursuing the addition of a fourth feed compressor.

At the Landfill Committee meeting on Tuesday, January 13, 2026, Dave Hartke, Director of the Resource Recovery & Energy Division, presented data highlighting the financial impact of equipment failures. The facility’s three existing compressors are the primary cause of outages, leading to significant revenue losses.

“If we have three feed compressors operating at all times… we’re going to be producing closer to 27 to 2900 mm BTUs,” Hartke explained, noting this would allow the plant to hit higher revenue tiers faster each month.

The proposed fourth unit, estimated at $1.8 million fully installed, would provide redundancy. However, the plan faced scrutiny regarding its financing. Board Member Sherry Newquist questioned the timing, noting, “This kind of stuff is so much easier to deal with during the budget process.”

Hartke admitted the request was not in the original budget due to a prior focus on austerity. “I wasn’t quite expecting the response… that we should move forward with it,” he said, referencing earlier informal discussions with committee leadership.

Despite the budget hurdle, the committee saw the long-term value. With a 46-week lead time for the equipment, Finance Director Marcy indicated the cost could potentially be split across two fiscal years.

Board Member Jim Richmond emphasized the need for a deeper analysis before cutting a check. “This is a massive business decision… We need to actually look at that plant and make sure that it is spec’d properly from the front door to the back door,” Richmond said.

Ultimately, the committee voted unanimously to authorize staff to proceed with obtaining firm engineering costs and a project plan, which will then be brought back for final financial approval.

Fri Jun 12
Sunny
85° 61°

Sunny

💨 5 to 15 mph 💧 11%

Leave a Comment





Latest News Stories

Meeting-Briefs

Meeting Summary and Briefs: New Lenox Fire Protection District for October 2025

New Lenox Fire Protection District Meeting | October 2025 The New Lenox Fire Protection District Board of Trustees on Monday, October 27, 2025, held a swearing-in ceremony promoting two firefighters...
Will County Board Graphic.01

County Takes Over “Central Will” Dial-A-Ride in Major Consolidation

Will County Board Meeting | November 2025 Article Summary: The Will County Board approved an intergovernmental agreement to absorb the "Central Will" Dial-A-Ride system into the county-wide "Access Will County"...
nl-food-pantry-horizontal___22114454354

New Lenox Food Pantry Reports Busiest Month Ever, Serving Over 1,100 Individuals in September

New Lenox Township Meeting | October 2025 Article Summary: The New Lenox Township food pantry experienced its busiest month on record in September, serving 430 families, which included 1,116 individuals....
Nl Park Graphic.2

New Lenox Park District Board Approves 9% Health Insurance Hike, New Truck Lease

New Lenox Community Park District Meeting | October 15, 2025 Article Summary: The New Lenox Community Park District Board of Commissioners unanimously approved a 9% increase for its 2026 employee...
Will County Board Graphic.02

Board Denies Appeal for “Tiny Home” RV Living in Crete

Will County Board Meeting | November 2025 Article Summary: The Will County Board voted 19-2 to uphold a denial of a temporary use permit for a recreational vehicle (RV) being...
joliet junior college logo

JJC Board Censures Trustee Broderick Twice, Denies Request to Restore Good Standing

Joliet Junior College Meeting | November 12, 2025 Article Summary:In a series of contentious votes, the Joliet Junior College Board of Trustees censured Trustee Maureen Broderick for two separate alleged...
mental health awareness day bipolar disorder anxiety stress emot

Will County Board Compromises on Mental Health Levy, Approves $10 Million After Debate

Will County Board Regular Meeting | October 16, 2025 Article Summary: The Will County Board on Thursday, October 16, 2025, approved a $10 million tax levy for the Community Mental Health...
The Wild Flowe rFarm

Green Garden’s Wildflower Farm Granted Second Extension for Rural Events Permit

Will County Board Regular Meeting | October 16, 2025 Article Summary: Bengston Land Management, LLC, operators of The Wildflower Farm in Green Garden Township, received a second 180-day extension from the...
Screenshot 2025-10-17 at 3.14.53 PM

Will County Board Rejects Proposed Tax Hike, Approves 0% Levy Increase in Contentious Vote

Will County Board Regular Meeting | October 16, 2025 Article Summary: In a significant move providing relief to taxpayers, the Will County Board on Thursday, October 16, 2025, voted to approve...
Screenshot 2025-10-17 at 3.14.41 PM

Will County Awards $10.4 Million Contract for Bell Road Widening Project

Will County Board Regular Meeting | October 16, 2025 Article Summary: The Will County Board has approved a $10.4 million contract with P.T. Ferro Construction Co. for a major roadway widening...
Screenshot 2025-10-17 at 3.15.09 PM

Regional Office of Education Highlights School Safety, New Learning Programs in Update

Will County Board Regular Meeting | October 16, 2025 Article Summary: Will County Regional Superintendent Dr. Lisa Caparelli-Ruff updated the County Board on key initiatives, including the installation of shooter-resistant window...
Screenshot 2025-10-25 at 10.48.48 AM

New Lenox Solar Farm Proposal Advances with Conditions, Following Village and Forest Preserve Input

Will County Planning and Zoning Commission Meeting | October 21, 2025 Article Summary: The Will County Planning and Zoning Commission recommended approval for a 62.7-acre commercial solar energy facility in...
Meeting Briefs

Meeting Summary and Briefs: Will County Board for October 16, 2025

Will County Board Regular Meeting | October 16, 2025 The Will County Board took major action on property taxes at its meeting on Thursday, October 16, 2025, narrowly voting to...
30 MPH Speed Limit

Will County Board Approves New 30 MPH Speed Limit for Frankfort Township Road

Will County Board Regular Meeting | October 16, 2025 Article Summary: The Will County Board approved a new 30 MPH speed limit for a section of 78th Avenue in Frankfort Township,...
Screenshot 2025-10-25 at 12.42.59 PM

Will County Committee Grapples with $8.9 Million Budget Gap After Contentious 0% Tax Levy Vote

Will County Board Finance Committee Meeting | October 21, 2025 Article Summary: The Will County Board Finance Committee held a contentious debate over how to close an $8.9 million budget shortfall...