New Lenox Awards $1.18 Million Contract for North Side Water Main Replacement
New Lenox Village Board Meeting | October 27, 2025
Article Summary: As part of a multi-phase plan to upgrade infrastructure on the village’s north side, the New Lenox Village Board awarded a contract for over $1.18 million to P.T. Ferro Construction Co. for the replacement of water mains on Cooper, Ash, and Wood Streets. The project is the first of three parts aimed at modernizing the area’s water system.
Water Main Project Key Points:
-
The board approved a bid of $1,187,327 from P.T. Ferro Construction Co., which was the lowest of 13 bidders and came in under budget.
-
The project targets the replacement of aging water mains on Cooper, Ash, and Wood Streets.
-
The contract award is contingent on the village’s expected loan approval from the Illinois Environmental Protection Agency (IEPA).
The New Lenox Village Board on Monday, October 27, 2025, took a major step in its plan to upgrade aging infrastructure by awarding a nearly $1.2 million contract for water main replacements on the north side of the village.
The board approved a bid of $1,187,327 from P.T. Ferro Construction Co. to replace water mains on Cooper, Ash, and Wood Streets. The bid was the lowest of 13 submitted and was under the village’s budget for the project. The contract is contingent upon final loan approval from the Illinois Environmental Protection Agency (IEPA).
This work represents the first phase of a three-part initiative to systematically replace water infrastructure in the area. Public Works staff expressed confidence in P.T. Ferro, which has successfully completed projects for the village in the past.
In a related move, the board also approved a proposal for Christopher Burke Engineering to handle the design of the second phase of the project. This next stage will focus on replacing water mains on G-Lane, Hawthorne Lane, and Fur Lane, with construction anticipated to begin in the spring of 2027.
Latest News Stories
Illinois Rep faces investigation over sexual harassment
Talks with Iran to resume
Return on investment questioned as Chicago Red Line construction begins
WATCH: WA Democrat income tax supporter questions ‘necessity clause’ nixing public vote
DOJ to face audit for handling of Epstein files release
ISU strike enters third week; union sues over alleged strikebreaking
Trump extends Jones Act waiver, citing national securit
Trump admin continues to crack down on fraudulent visa schemes
Virginia 1 of 4 in courtroom battles for congressional redistricting
Illinois Quick Hits: State gaming board renew Rockford casino license
Arizona GOP pushes to protect Colorado River’s limited water
Republicans challenge Clyde in Georgia’s 9th District