New Lenox Awards $1.18 Million Contract for North Side Water Main Replacement
New Lenox Village Board Meeting | October 27, 2025
Article Summary: As part of a multi-phase plan to upgrade infrastructure on the village’s north side, the New Lenox Village Board awarded a contract for over $1.18 million to P.T. Ferro Construction Co. for the replacement of water mains on Cooper, Ash, and Wood Streets. The project is the first of three parts aimed at modernizing the area’s water system.
Water Main Project Key Points:
-
The board approved a bid of $1,187,327 from P.T. Ferro Construction Co., which was the lowest of 13 bidders and came in under budget.
-
The project targets the replacement of aging water mains on Cooper, Ash, and Wood Streets.
-
The contract award is contingent on the village’s expected loan approval from the Illinois Environmental Protection Agency (IEPA).
The New Lenox Village Board on Monday, October 27, 2025, took a major step in its plan to upgrade aging infrastructure by awarding a nearly $1.2 million contract for water main replacements on the north side of the village.
The board approved a bid of $1,187,327 from P.T. Ferro Construction Co. to replace water mains on Cooper, Ash, and Wood Streets. The bid was the lowest of 13 submitted and was under the village’s budget for the project. The contract is contingent upon final loan approval from the Illinois Environmental Protection Agency (IEPA).
This work represents the first phase of a three-part initiative to systematically replace water infrastructure in the area. Public Works staff expressed confidence in P.T. Ferro, which has successfully completed projects for the village in the past.
In a related move, the board also approved a proposal for Christopher Burke Engineering to handle the design of the second phase of the project. This next stage will focus on replacing water mains on G-Lane, Hawthorne Lane, and Fur Lane, with construction anticipated to begin in the spring of 2027.
Latest News Stories
Will County P&Z Approves Crete Solar Farm, Overruling Township’s General Opposition
Will County Board Approves Controversial Recovery Retreat in Crete Township Amid Strong Resident Opposition
Will County P&Z: Green Garden Township Variances Granted in Monee
Will County P&Z: Manhattan Township Rezoning Approved
Will County P&Z: Green Garden Township Rezoning Approved Amid Concerns Over Lack of a Final Plan
Zoning Commission Overrules Staff, Approves Greeen Garden Twp Variance for 3-Acre Agricultural Lot
Village-Wide Broadband Service Coming as New Lenox Approves Clearwave Fiber Agreement
Lincoln-Way Board Approves Special Education Co-op Budget Amid Concerns Over Rising Costs
Lincoln-Way Board Approves Special Education Co-op Budget Amid Concerns Over Rising Costs
Illinois trucker warns foreign firms faking logs, dodging rules, risking safety
Illinois law mandates pharmacies to sell needles, sparking safety debate
Illinois quick hits: Governor bans school fines; Target fires hundreds over fraud
Industry advocates: More state regulation will drive insurance rates higher
Lincoln-Way Board Reviews $162 Million Tentative Budget, Projects Deficit Due to Bus Purchase Timing