New Lenox School District 122 Approves $908,900 Equipment Purchase for Tyler Elementary HVAC Overhaul

Spread the love

Meeting Summary and Briefs: New Lenox School District 122 Meeting | August 2025

Article Summary: The New Lenox School District 122 Board of Education has authorized the pre-purchase of $908,900 in HVAC equipment for a major renovation at Tyler Elementary School, slated for the summer of 2026. The total project, estimated at over $8.1 million, will modernize the school’s 1980s-era heating and cooling systems and include numerous other building upgrades.

Tyler HVAC Renovation Key Points:

  • The board approved a $908,900 equipment order through the OMNIA Partners Purchasing Cooperative.

  • The total projected cost for the renovation, including installation and other improvements, is $8,148,000.

  • The project will replace the school’s original 1980 heating infrastructure with a modern, energy-efficient V.R.F. system.

  • Additional upgrades will include new ceilings, dimmable LED lighting, a new Public Address system, and a new Fire Alarm System.

The New Lenox School District 122 Board of Education on Tuesday, August 19, 2025, approved a significant first step in a multi-million dollar renovation of Tyler Elementary School, authorizing the pre-purchase of $908,900 in new HVAC equipment. The total project, with an estimated cost of $8,148,000, aims to completely overhaul the school’s mechanical systems during the summer of 2026.

Business Manager/CSBO Robert Groos explained that the equipment must be purchased well in advance to ensure it is delivered before installation work begins. The district is using the OMNIA Partners Purchasing Cooperative to comply with state purchasing laws while securing competitive pricing.

Rob Wroble of Legat Architects presented the project’s design and timeline to the board, detailing the necessity of the upgrades. “Tyler School relies on the original heating system infrastructure which dates back to 1980 when the building was opened,” Wroble’s presentation noted, identifying Tyler as the last of four older district schools to receive such a modernization.

The current system is supplied by centralized hot water boilers and uses original pneumatic tubing, valves, and thermostats for temperature control. The aging infrastructure also includes two air-cooled condensing units and cabinet unit ventilators that are beyond their life expectancy.

The proposed replacement is a Variable Refrigerant Flow (V.R.F.) mechanical system, which separates heating and cooling from ventilation. This design is more energy-efficient as it reduces the need to pre-heat or cool large amounts of outside air. Instead of a boiler and chiller, the V.R.F. system uses heat pumps and circulates refrigerant through a two-pipe network to fan coil units in each room. The district is already familiar with this technology, as it is currently operating in three other schools.

Benefits of the new system, according to the presentation, include lower operating costs, smaller equipment, and excellent temperature and humidity control, with thermostats located in every room.

Beyond the mechanical overhaul, the project will fund a host of other improvements throughout the school. These include new bookshelves and storage cabinets in every classroom, new ceilings with dimmable LED light fixtures, a new Public Address System, and a new Fire Alarm System.

During the meeting, board members asked clarifying questions about the project’s logistics. Member Al Haring inquired about equipment storage, to which Mr. Wroble confirmed it would be stored off-site by the contractor or a third party. In response to a question from Member Nicole DeGrave, Wroble noted that while different companies installed the V.R.F. systems at other schools, the equipment and warranties are the same, ensuring consistency.

The project timeline calls for the board to approve the final construction contracts in December 2025. Final bond financing options to fund the project will be reviewed and approved by the board later in the fall of 2025.

Leave a Comment





Latest News Stories

Don’t count on lower electricity prices in 2026

Don’t count on lower electricity prices in 2026

By Lauren JessopThe Center Square For 67 million people relying on electricity from the regional power grid, PJM, cheaper utility bills in 2026 are little more than a pipe dream....
NL School District 122 Graphic

District 122 Authorizes $8 Million in Bonds for HVAC; Partners with Park District on Playgrounds

New Lenox School District 122 Board Meeting | Nov. 2025 Article Summary:The School Board moved forward with major capital projects, authorizing the issuance of $8 million in Life Safety Bonds...
Screenshot 2025-12-20 at 12.27.11 PM

Lincoln-Way Board Approves $731,000 Freshman Laptop Purchase

Lincoln-Way Community High School District 210 Meeting | December 18, 2025 Article Summary: The District 210 Board of Education authorized the purchase of 1,750 Lenovo laptops to equip the incoming...
Will County Board Graphic.01

Monee Solar Farm Projects Granted Extensions

Will County Board Meeting | December 18, 2025 Article Summary: The Will County Board granted six-month extensions for two special use permits related to commercial solar energy facilities in Monee...

WATCH: Report: Americans are still paying off credit debt from last Christmas

By Carleen JohnsonThe Center Square If your last-minute Christmas shopping requires a credit card, you are not alone. According to a new WalletHub report, many Americans are still paying off...
Congressional Conflicts: Curb on lawmakers’ stock trades draws fire for being weak

Congressional Conflicts: Curb on lawmakers’ stock trades draws fire for being weak

By Mark StricherzThe Center Square A limited ban on stock trading by Congress might get a vote next year after a 2012 law did not do enough to stem the...
Wyoming's year in review: Education savings, contentious spending

Wyoming’s year in review: Education savings, contentious spending

By Andrew RiceThe Center Square Wyoming lawmakers passed legislation to expand education savings accounts and property tax protections in 2025. However, the legislature remained divided on substantial spending increases to...
U.S. House advances GOP-backed energy reliability bill

U.S. House advances GOP-backed energy reliability bill

By Elyse ApelThe Center Square Legislation looking to lower energy prices nationally successfully passed the U.S. House on a slightly bipartisan vote. H.R. 3628, titled the “State Planning for Reliability...
Illinois’ safe gun storage law goes into effect Jan. 1

Illinois’ safe gun storage law goes into effect Jan. 1

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – Components of Illinois Safe Gun Storage Act go into effect Jan. 1. Supporters of Senate Bill 8,...
New-Lenox-School-122.7

New Lenox School Board Approves “Balloon” Tax Levy; Actual Increase Expected at 4.7%

New Lenox School District 122 Board Meeting | Nov. 2025 Article Summary:The New Lenox School District 122 Board of Education approved its 2025 property tax levy following a public hearing....
New Lenox Township.3

New Lenox Township Sets Preliminary Tax Levies; No Public Hearing Required

New Lenox Township Board Meeting | Nov. 13, 2025 Article Summary: The New Lenox Township Board of Trustees determined that the 2025 tax levies for both the township and the...
Sufyan Farhan

Frankfort Man Arrested in Gas Station Robbery Found Hiding in McDonald’s Restroom

Article Summary: Sufyan Farhan, 27, was arrested on December 21 following an armed robbery at a Frankfort Circle K. Deputies located the suspect hiding in a nearby McDonald's restroom after...
New-Lenox-Village-Board.1

Village Moves to Upgrade Police Fleet and Sewer Infrastructure

New Lenox Village Board Meeting | December 15, 2025 Article Summary: The New Lenox Village Board on Monday, Dec. 15, 2025, authorized the purchase of three new police interceptors and...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Executive Committee for December 11, 2025

Will County Board Executive Committee Meeting | December 11, 2025 Overall Meeting SummaryThe Will County Board Executive Committee met on Thursday, December 11, 2025, tackling a diverse agenda that included...
Planning & Zoning Graphic.4

New Lenox Homeowner Granted Variance for 4,000-Square-Foot Accessory Space

Will County Planning and Zoning Commission Meeting | December 16, 2025 Article Summary: A New Lenox homeowner received approval to build a large pole barn that exceeds the county's size limits...