Key Stretch of Bell Road on Track for Thanksgiving Reopening, Committee Approves Additional Funds
ARTICLE SUMMARY Construction on Bell Road between 159th and 151st Streets is scheduled to have all lanes open by Thanksgiving, officials announced as the Public Works & Transportation Committee approved a $652,896 supplemental contract for engineering services.
Key Points:
-
The Thanksgiving target for reopening all lanes was confirmed by Director of Transportation Jeff Ronaldson.
-
The supplemental agreement with AECOM Technical Services, Inc., is for continued construction engineering oversight as the project extends due to utility conflict delays.
JOLIET—Commuters navigating construction on Bell Road received good news Tuesday, as Will County’s transportation director announced that all lanes on the key stretch between 159th Street and 151st Street are expected to be open by Thanksgiving.
The update came as the Will County Public Works & Transportation Committee approved a supplemental professional services agreement for $652,896 with AECOM Technical Services, Inc., for continued construction engineering on the project.
“Essentially all lanes will be open by Thanksgiving,” Director of Transportation Jeff Ronaldson told the committee. He added that some minor work, such as landscaping and final surfacing, could carry over into the spring.
The contract extension with AECOM covers the cost of having the resident engineer and consulting firm oversee construction, which was extended due to delays caused by utility conflicts. The project involves the reconstruction and widening of the heavily traveled corridor in County Board District 4.
Board Member Steve Balich (R-Homer Glen) questioned Ronaldson about the timeline, noting that residents are “jumping up and down out there, which I get it.” Ronaldson confirmed the Thanksgiving target, solidifying the timeline for the much-anticipated reopening. The committee approved the supplemental agreement unanimously.
Latest News Stories
Meeting Summary and Briefs: New Lenox Village Board for October 27, 2025
Meeting Summary and Briefs: Will County Capital Improvements & IT Committee for November 4, 2025
New Lenox Announces 5.51% Increase in 2025 Property Tax Levy
New Gas N Wash and Dutch Bros. Coffee Projects Advance in New Lenox
New Lenox Approves Final Plans for The Patio Restaurant, Construction to Begin in December
New Lenox Awards $1.18 Million Contract for North Side Water Main Replacement
Meeting Summary and Briefs: Will County Public Works & Transportation Committee for November 2025
Will County Committee Members Debate Future Capital Priorities, Clash on Borrowing
Meeting Summary and Briefs: Will County Planning and Zoning Commission for November 4, 2025
Meeting Summary and Briefs: Will County Legislative Committee for November 4, 2025
Will County Saves $5.7 Million in Bond Refinancing, Maintains High Credit Ratings
Meeting Summary and Briefs: Joliet Junior College Board of Trustees for October 2025
New Lenox Approves Solar Subscription, Projects Over $100,000 in Annual Savings