New Lenox Greenlights Early Work Package for Crossroads Fieldhouse Project

Spread the love

Meeting Summary and Briefs: New Lenox Village Board for May 18, 2026

Article Summary: The New Lenox Village Board on Monday, May 18, 2026, approved a resolution waiving competitive bidding and authorizing an early work package proposal with Northern Builders LLC for the Crossroads Fieldhouse project, allowing ground clearing and geotechnical work to begin while the full construction contract is finalized for the June 8 meeting.

Crossroads Fieldhouse Early Work Key Points:

  • The board approved a resolution waiving competitive bidding and authorizing Northern Builders LLC to begin initial site work.
  • The early package covers ground clearing, geotechnical work, and bonding and insurance for the entire fieldhouse project.
  • The full construction contract with Northern Builders is targeted for approval at the June 8, 2026, board meeting.
  • The early start is intended to maintain the village’s construction schedule for the fieldhouse.

NEW LENOX — The New Lenox Village Board on Monday, May 18, 2026, unanimously approved a resolution waiving competitive bidding and authorizing an early work package proposal with Northern Builders LLC for the Crossroads Fieldhouse project.

Mayor Tim Baldermann described the action as a schedule-preservation move, telling trustees that the village has been “doing quite a bit of work with our team and with TRIA architecture, as well as Northern” in preparation for the project.

“This in order to maintain the schedule that we want is just the initial work that will be out there: the ground clearing, geotech, that sort of thing,” Baldermann said. “By the time we have our next board meeting June 8th, we’re hoping to have the complete contract with Northern for this.”

What the Early Package Covers

According to the mayor’s explanation, the approved early work package includes more than just the initial site preparation. The cost figure presented to the board also encompasses bonding and insurance for the entire Crossroads Fieldhouse project, which Baldermann said accounted for the size of the dollar amount associated with the early package.

The specific dollar figure for the early work package was not stated aloud during the open portion of the meeting. The waiver of competitive bidding was incorporated directly into the resolution rather than handled as a separate motion, as had been the case for several other waiver actions Monday night.

The resolution was approved by unanimous roll call vote. Trustee Keith Madsen made the motion, and Trustee Katie Christopherson provided the second. Trustees Madsen, Bryan Reiser, Jim Wilson and Christopherson all voted yes, joined by Baldermann. Trustees Lindsay Scalise and Amy Gugliuzza were absent.

The Crossroads Fieldhouse project is expected to return to the village board on June 8, 2026, when the full construction contract with Northern Builders is scheduled for consideration.

Leave a Comment





Latest News Stories

Will County Board Graphic.04

Will County Animal Protection Services Advises Against Multi-Campus Shelter Model

Will County Public Health & Safety Committee Meeting | April 2, 2026 Article Summary: Following a request for research, the Will County Animal Protection Services administrator reported that Will County...
Will County Board Graphic.02

Executive Committee Advances $15,000 Strategic Plan Initiative

Will County Board Executive Committee Meeting | April 9, 2026 Article Summary: The Will County Board Executive Committee unanimously approved a $15,000 agreement with Leap HR Consulting to develop the...
Rich States Poor States: Tax policy largely determines states’ economic competitiveness

Rich States Poor States: Tax policy largely determines states’ economic competitiveness

By Morgan SweeneyThe Center Square No matter what a state offers in terms of natural beauty, work and social opportunities, tax and economic policy — as unglamorous as they sound...
Will County P&Z Logo Planning Zoning

P&Z Commission Overrides Staff Denials, Rescuing Special Use Permits for Joliet Wedding Venue and Romeoville Barge Terminal

Will County Planning and Zoning Commission Meeting | April 7, 2026 Article Summary: The Will County Planning and Zoning Commission voted to overturn administrative denials for two delayed commercial projects—a...
Will County P&Z Logo Planning Zoning

Will County P&Z Commission Grants Extensions for Joliet Township Solar Farm Ground Cover

Will County Planning and Zoning Commission Meeting | April 7, 2026 Article Summary: The Will County Planning and Zoning Commission unanimously granted a final deadline extension for a commercial solar...
Will County P&Z Logo Planning Zoning.2

P&Z Approves Lockport Bounce House Business Expansion

Will County Planning and Zoning Commission Meeting | April 7, 2026 The commission unanimously approved Zoning Case #ZC-25-137 for Victor H. Lule Huerta, owner of 3262 S. State Street in...
78 pro-life orgs ask DOJ to stop undermining state laws by favoring aborting drug industry

78 pro-life orgs ask DOJ to stop undermining state laws by favoring aborting drug industry

By Tate MillerThe Center Square Susan B. Anthony Pro-Life America led 77 of its pro-life organization colleagues in sending the acting U.S. attorney general a letter asking the Department of...
Illinois Quick Hits: Two of ComEd four released; new trial expected

Illinois Quick Hits: Two of ComEd four released; new trial expected

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – A U.S. appellate court has ordered two defendants in the ComEd Four case to be released pending...
Will County Finance Logo

Will County Treasurer Seeks Policy on Cash Payments as U.S. Mint Discontinues the Penny

Briefs: Will County Board Finance Committee Meeting | April 7, 2026 Article Summary: With the U.S. Mint ceasing production of the penny, the Will County Treasurer's Office is asking the...
—Photo by Glenn P. Knoblock

Lend a hand this spring at Volunteer Morning programs

Volunteers are being sought for spring programs that help spruce up the preserves by removing invasive species, controlling brush and planting native plants. Here are the spring Volunteer Morning programs....
Track and Field Graphic

Lincoln-Way East Boys Outpace West and Stagg to Claim SWSC Triangular Victory

The Lincoln-Way East Griffins showcased their formidable depth Tuesday afternoon, securing a first-place finish at the boys SouthWest Suburban Conference (SWSC) triangular meet hosted by Lincoln-Way West. The Griffins compiled...
Track and Field Graphic

Lincoln-Way East Girls Track Dominates Triangular Meet Against West and Stagg

The Lincoln-Way East Griffins girls track and field team delivered a commanding performance on their home turf Tuesday, April 14, 2026, easily outdistancing Lincoln-Way West and Stagg in a triangular...
Will County Board Graphic.03

Proposed State Legislation Sparks Debate Over Will County Veterans Assistance Commission Budget Control

Will County Board Legislative Committee Meeting | April 7, 2026 Article Summary: State legislation aimed at granting county boards ultimate approval power over Veterans Assistance Commission (VAC) budgets sparked debate...
Chicago suit vs oil cos. may yet survive SCOTUS ruling, judge hints

Chicago suit vs oil cos. may yet survive SCOTUS ruling, judge hints

By Jonathan Bilyk | Legal NewslineThe Center Square Even as the Supreme Court considers a Colorado case that oil companies believe will decide if city and state governments can sue...
Two of ComEd Four released. new trial pending

Two of ComEd Four released. new trial pending

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – A U.S. appellate court has ordered two defendants in the ComEd Four case to be released pending...