Commission Approves Massive Lake Michigan Water Infrastructure Project for Troy Township

Spread the love

Will County Planning and Zoning Commission Meeting | May 5, 2026

Article Summary: The Will County Planning and Zoning Commission on May 5, 2026, unanimously approved two major public utility requests and associated fence variances to facilitate the construction of regional water storage and pumping facilities. The 40-acre development at Black Road and County Line Road is a critical component of a $1.446 billion initiative to deliver Lake Michigan water to six Will County municipalities by 2030.

Water Infrastructure Key Points:

  • Project Scope: The development includes a 1.5 million-gallon “spheroid” elevated storage tank standing 145 feet tall, a pump station, and a public works garage.

  • Dual Ownership: The site is divided into two 20-acre parcels—one owned by the Grand Prairie Water Commission (ZC-26-019) and one by the City of Joliet (ZC-26-018).

  • Regional Impact: The facilities will serve 250,000 residents across Joliet, Shorewood, Crest Hill, Channahon, Minooka, and Romeoville.

  • Security Measures: Both parcels were granted variances to install 8-foot-tall security fences (7-foot chain link with 1 foot of barbed wire), exceeding the standard 7-foot limit for the A-1 district.

JOLIET — A massive regional effort to secure a sustainable water supply for Will County took a significant step forward Tuesday, May 5, 2026, as the Planning and Zoning Commission cleared the way for the Grand Prairie Water Commission (GPWC) and the City of Joliet to begin developing a critical infrastructure hub in Troy Township.

The two related cases, ZC-26-018 and ZC-26-019, involve adjacent vacant properties located at the southeast corner of Black Road and County Line Road. The project is born of necessity; Allison Swisher, Director of Public Utilities for Joliet, testified that the region’s existing deep aquifer is failing and will be unable to meet maximum demand by 2030.

“We selectioned purchasing water from the City of Chicago as the most sustainable and reliable option,” Swisher told the commission. “The majority of this project will serve Will County residents.”

Site Specifics and Security
The GPWC parcel (ZC-26-019) will house the project’s second intermediate storage facility, featuring a 1.5 million-gallon steel tank. The City of Joliet’s neighboring parcel (ZC-26-018) will include additional water storage tanks, a public works garage, and an outdoor storage yard.

Because of the “critical” nature of the water supply, the applicants requested variances to allow for 8-foot-tall fencing topped with barbed wire for security. Staff recommended approval, noting that while the area remains primarily agricultural, it is slated for future residential growth that requires this infrastructure.

Commissioner John Kiefner questioned why the properties were not being annexed into Joliet. Swisher responded that while annexation is likely in the future, the commission needs to begin construction immediately to meet the 2030 deadline for water delivery.

The commission approved the Special Use Permits and the fence variances for both parcels without a single dissenting vote.

Today Jun 9
Showers And Thunderstorms Likely
70°

Showers And Thunderstorms Likely

Leave a Comment





Latest News Stories

Meeting Briefs

Meeting Summary and Briefs: New Lenox Community Park District for August 2025

New Lenox Community Park District Meeting | August 2025 The New Lenox Community Park District Board of Commissioners reviewed major financial news and celebrated a record-breaking month for its golf...
Pavlov Media

Pavlov Media to Bring New Fiber Internet Option to New Lenox

Village of New Lenox Board of Trustees Meeting | September 22, 2025 Article Summary: The entrance to the Wintrust Crossroads Sports Complex is set to receive a major aesthetic upgrade...
Enbridge Energy

Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements

Article Summary: Will County will reimburse Enbridge Energy for costs associated with relocating its pipeline facilities to make way for roadway improvements on Exchange Street in the Monee and Crete...
diamond shaped orange red reflector street sign that reads road

Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign

Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for...
solar panels photovoltaics in solar farm

“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension

Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited "ongoing uncertainty regarding federal...
solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy...
WCO 2025-09-27 at 9.04.10 AM

Will County Board Approves Controversial Drug Recovery Retreat in Crete Township

Article Summary: The Will County Board has approved a special use permit for The Second Story Foundation to operate a long-term residential recovery program for men on a 68-acre horse...
new-lenox-fire-district-stations.3

Winter Start Unlikely for $4 Million New Lenox Fire Station 62 Remodel

New Lenox Fire Protection District Meeting | August 2025 Article Summary: The planned $4 million remodel of New Lenox Fire Station 62 faces a potential delay, as officials indicated a...
LWSRA-Blue-Logo-transparent

New LWSRA Sensory Bus Hits the Road Thanks to $30,000 Donation

New Lenox Community Park District Meeting | August 2025 Article Summary: The Lincoln-Way Special Recreation Association's new Sensory Bus is officially in service and has been well-received at community events....
Joliet-Junior-college.-Graphic-Logo.4

Joliet Junior College Honors Seven Long-Serving Employees Upon Retirement

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College Board of Trustees formally recognized seven long-serving employees who are retiring, including Dr. Robert "Bob"...
New-Lenox-School-122.3

New Lenox Parent Challenges Busing Fee, Cites Safety Concerns and Budget Surplus

Meeting Summary and Briefs: New Lenox School District 122 Meeting | August 2025 Article Summary: A New Lenox parent addressed the School District 122 board to protest a $350 busing...
Screenshot 2025-11-03 at 11.39.46 AM

New Lenox Demands Over $422,000 From Developer to Complete Public Improvements

Village of New Lenox Board of Trustees Meeting | September 22, 2025 Article Summary: The Village of New Lenox is taking formal action to secure funds for unfinished public infrastructure...
new-lenox-fire-district-stations.4

New Lenox Fire District Pays Off Final Loan, Secures $75,000 State Grant

New Lenox Fire Protection District Meeting | August 2025 Article Summary: The New Lenox Fire Protection District has achieved a significant financial milestone by making the final payment on its...
New-Lenox-Sharons-Bay-Park

Damaged Drain Tiles at Bristol Park Face $107,000 Repair Bill

New Lenox Community Park District Meeting | August 2025 Article Summary: A comprehensive survey of the drainage system at Bristol Park has revealed that all of the clay tiles are...
Screenshot 2025-11-03 at 11.31.47 AM

New Lenox and Homer Glen Renew 20-Year Boundary Agreement, Defining Future Growth

Village of New Lenox Board of Trustees Meeting | September 22, 2025 Article Summary: The New Lenox Village Board has approved a new 20-year intergovernmental boundary agreement with the Village...