Village Board Approves Industrial Rezoning on Gougar Road Over Resident Protests, But Freezes Construction for Years

Spread the love

New Lenox Village Board of Trustees Meeting | April 27, 2026

Article Summary:
Following intense pushback from neighboring residents, the New Lenox Village Board approved a development agreement and rezoning for a Northern Builders industrial project south of Laraway Road. However, to mitigate traffic concerns, the Village mandated a strict freeze preventing the developer from starting construction or receiving occupancy until major county road and overpass improvements are completed.

Gougar Road Industrial Development Key Points:

  • Zoning Approval: The Board passed ordinances authorizing a Development Agreement and rezoning the property at the southwest corner of Laraway Road and Gougar Road (extended) to I-1 Limited Industrial.

  • Resident Backlash: Multiple residents from nearby subdivisions like Jacob’s Field and Country View argued the warehouses will bring dangerous truck traffic near schools and destroy the residential character of the area.

  • Construction Freeze: Northern Builders cannot obtain a building permit until the county begins widening Gougar Road and constructing the CN railroad overpass, or a period of three years expires.

  • Occupancy Block: The developer cannot receive a Certificate of Occupancy until the road improvements are completely finished, or four years expire.

The New Lenox Village Board on Monday, April 27, 2026, voted to approve the rezoning of agricultural land for industrial warehouse use along Gougar Road, balancing developer rights with resident fury by attaching strict, multi-year road construction contingencies to the project.

The Board passed an Ordinance Authorizing a Development Agreement with Cherry Hill Laraway LLC (Northern Builders) and a subsequent Ordinance Rezoning the property at the southwest corner of Laraway Road and the future Gougar Road extension.

The approvals followed a second round of intense public comment from residents representing nearby subdivisions, including Jacob’s Field and Country View. Residents fiercely objected to the prospect of heavy semi-truck traffic bleeding into residential zones.

“I don’t understand how more trucks on our roads near a high school, near grade schools… makes that statement true when this gets built,” said resident Mike Gian Paulo. “I don’t understand how this benefits New Lenox… I see how it benefits certain corporations.”

Resident Dennis McLaclin argued the development was encroaching on established neighborhoods that have been there since the 1970s.

“No one wanted that there. No one wants these warehouses there, and they’re being shoved on them,” McLaclin told the Board. “There’s plenty of open spots for these warehouses. They got hundreds of available acres in that park.”

In response to the public outcry, the Village forced Northern Builders to accept a highly unusual timeline restriction. Community Development Director Robin Ellis explained that the developer must dedicate the right-of-way along their entire frontage and construct a landscaped berm. Crucially, they are legally barred from receiving a building permit until construction physically begins on the county’s widening of Gougar Road and the new CN railroad overpass, or until three years have passed. Furthermore, the Village will not issue a Certificate of Occupancy until those road improvements are entirely complete, or four years have passed.

Matthew Garci, representing Northern Builders, confirmed the developer had agreed to the terms and was actively working with the Illinois Department of Transportation (IDOT) and Will County to dedicate the necessary land for the overpass.

“Based on our first reading of this, to be responsive and to work appropriately with staff, we resided to the idea that okay, we’re going to carry this… we’re going to sit on it for three years,” Garci said. “We have that carry cost for that period of time, which is fine.”

Mayor Tim Baldermann defended the Board’s decision, noting that the Village has kept its long-standing promise to prevent industrial development from crossing east of Gougar Road. He pointed out that the Village previously relocated the new Water Resource Recovery Facility away from residential areas to accommodate public demand, leaving this specific parcel open for commercial or industrial growth.

“Our commitment was to keep everything west of Gougar, which this is, and to say, ‘Okay, they’re ready to go now. No, you need to wait,'” Baldermann said. “That’s very unusual for us to say that… But we’re doing everything we can to accommodate the residents and the business owner.”

Both the Development Agreement and the rezoning ordinances passed on 6-0 roll call votes.

Leave a Comment





Latest News Stories

Will County Board Graphic.04

Will County Animal Protection Services Advises Against Multi-Campus Shelter Model

Will County Public Health & Safety Committee Meeting | April 2, 2026 Article Summary: Following a request for research, the Will County Animal Protection Services administrator reported that Will County...
Will County Board Graphic.02

Executive Committee Advances $15,000 Strategic Plan Initiative

Will County Board Executive Committee Meeting | April 9, 2026 Article Summary: The Will County Board Executive Committee unanimously approved a $15,000 agreement with Leap HR Consulting to develop the...
Rich States Poor States: Tax policy largely determines states’ economic competitiveness

Rich States Poor States: Tax policy largely determines states’ economic competitiveness

By Morgan SweeneyThe Center Square No matter what a state offers in terms of natural beauty, work and social opportunities, tax and economic policy — as unglamorous as they sound...
Will County P&Z Logo Planning Zoning

P&Z Commission Overrides Staff Denials, Rescuing Special Use Permits for Joliet Wedding Venue and Romeoville Barge Terminal

Will County Planning and Zoning Commission Meeting | April 7, 2026 Article Summary: The Will County Planning and Zoning Commission voted to overturn administrative denials for two delayed commercial projects—a...
Will County P&Z Logo Planning Zoning

Will County P&Z Commission Grants Extensions for Joliet Township Solar Farm Ground Cover

Will County Planning and Zoning Commission Meeting | April 7, 2026 Article Summary: The Will County Planning and Zoning Commission unanimously granted a final deadline extension for a commercial solar...
Will County P&Z Logo Planning Zoning.2

P&Z Approves Lockport Bounce House Business Expansion

Will County Planning and Zoning Commission Meeting | April 7, 2026 The commission unanimously approved Zoning Case #ZC-25-137 for Victor H. Lule Huerta, owner of 3262 S. State Street in...
78 pro-life orgs ask DOJ to stop undermining state laws by favoring aborting drug industry

78 pro-life orgs ask DOJ to stop undermining state laws by favoring aborting drug industry

By Tate MillerThe Center Square Susan B. Anthony Pro-Life America led 77 of its pro-life organization colleagues in sending the acting U.S. attorney general a letter asking the Department of...
Illinois Quick Hits: Two of ComEd four released; new trial expected

Illinois Quick Hits: Two of ComEd four released; new trial expected

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – A U.S. appellate court has ordered two defendants in the ComEd Four case to be released pending...
Will County Finance Logo

Will County Treasurer Seeks Policy on Cash Payments as U.S. Mint Discontinues the Penny

Briefs: Will County Board Finance Committee Meeting | April 7, 2026 Article Summary: With the U.S. Mint ceasing production of the penny, the Will County Treasurer's Office is asking the...
—Photo by Glenn P. Knoblock

Lend a hand this spring at Volunteer Morning programs

Volunteers are being sought for spring programs that help spruce up the preserves by removing invasive species, controlling brush and planting native plants. Here are the spring Volunteer Morning programs....
Track and Field Graphic

Lincoln-Way East Boys Outpace West and Stagg to Claim SWSC Triangular Victory

The Lincoln-Way East Griffins showcased their formidable depth Tuesday afternoon, securing a first-place finish at the boys SouthWest Suburban Conference (SWSC) triangular meet hosted by Lincoln-Way West. The Griffins compiled...
Track and Field Graphic

Lincoln-Way East Girls Track Dominates Triangular Meet Against West and Stagg

The Lincoln-Way East Griffins girls track and field team delivered a commanding performance on their home turf Tuesday, April 14, 2026, easily outdistancing Lincoln-Way West and Stagg in a triangular...
Will County Board Graphic.03

Proposed State Legislation Sparks Debate Over Will County Veterans Assistance Commission Budget Control

Will County Board Legislative Committee Meeting | April 7, 2026 Article Summary: State legislation aimed at granting county boards ultimate approval power over Veterans Assistance Commission (VAC) budgets sparked debate...
Chicago suit vs oil cos. may yet survive SCOTUS ruling, judge hints

Chicago suit vs oil cos. may yet survive SCOTUS ruling, judge hints

By Jonathan Bilyk | Legal NewslineThe Center Square Even as the Supreme Court considers a Colorado case that oil companies believe will decide if city and state governments can sue...
Two of ComEd Four released. new trial pending

Two of ComEd Four released. new trial pending

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – A U.S. appellate court has ordered two defendants in the ComEd Four case to be released pending...