Village Board Approves Industrial Rezoning on Gougar Road Over Resident Protests, But Freezes Construction for Years

Spread the love

New Lenox Village Board of Trustees Meeting | April 27, 2026

Article Summary:
Following intense pushback from neighboring residents, the New Lenox Village Board approved a development agreement and rezoning for a Northern Builders industrial project south of Laraway Road. However, to mitigate traffic concerns, the Village mandated a strict freeze preventing the developer from starting construction or receiving occupancy until major county road and overpass improvements are completed.

Gougar Road Industrial Development Key Points:

  • Zoning Approval: The Board passed ordinances authorizing a Development Agreement and rezoning the property at the southwest corner of Laraway Road and Gougar Road (extended) to I-1 Limited Industrial.

  • Resident Backlash: Multiple residents from nearby subdivisions like Jacob’s Field and Country View argued the warehouses will bring dangerous truck traffic near schools and destroy the residential character of the area.

  • Construction Freeze: Northern Builders cannot obtain a building permit until the county begins widening Gougar Road and constructing the CN railroad overpass, or a period of three years expires.

  • Occupancy Block: The developer cannot receive a Certificate of Occupancy until the road improvements are completely finished, or four years expire.

The New Lenox Village Board on Monday, April 27, 2026, voted to approve the rezoning of agricultural land for industrial warehouse use along Gougar Road, balancing developer rights with resident fury by attaching strict, multi-year road construction contingencies to the project.

The Board passed an Ordinance Authorizing a Development Agreement with Cherry Hill Laraway LLC (Northern Builders) and a subsequent Ordinance Rezoning the property at the southwest corner of Laraway Road and the future Gougar Road extension.

The approvals followed a second round of intense public comment from residents representing nearby subdivisions, including Jacob’s Field and Country View. Residents fiercely objected to the prospect of heavy semi-truck traffic bleeding into residential zones.

“I don’t understand how more trucks on our roads near a high school, near grade schools… makes that statement true when this gets built,” said resident Mike Gian Paulo. “I don’t understand how this benefits New Lenox… I see how it benefits certain corporations.”

Resident Dennis McLaclin argued the development was encroaching on established neighborhoods that have been there since the 1970s.

“No one wanted that there. No one wants these warehouses there, and they’re being shoved on them,” McLaclin told the Board. “There’s plenty of open spots for these warehouses. They got hundreds of available acres in that park.”

In response to the public outcry, the Village forced Northern Builders to accept a highly unusual timeline restriction. Community Development Director Robin Ellis explained that the developer must dedicate the right-of-way along their entire frontage and construct a landscaped berm. Crucially, they are legally barred from receiving a building permit until construction physically begins on the county’s widening of Gougar Road and the new CN railroad overpass, or until three years have passed. Furthermore, the Village will not issue a Certificate of Occupancy until those road improvements are entirely complete, or four years have passed.

Matthew Garci, representing Northern Builders, confirmed the developer had agreed to the terms and was actively working with the Illinois Department of Transportation (IDOT) and Will County to dedicate the necessary land for the overpass.

“Based on our first reading of this, to be responsive and to work appropriately with staff, we resided to the idea that okay, we’re going to carry this… we’re going to sit on it for three years,” Garci said. “We have that carry cost for that period of time, which is fine.”

Mayor Tim Baldermann defended the Board’s decision, noting that the Village has kept its long-standing promise to prevent industrial development from crossing east of Gougar Road. He pointed out that the Village previously relocated the new Water Resource Recovery Facility away from residential areas to accommodate public demand, leaving this specific parcel open for commercial or industrial growth.

“Our commitment was to keep everything west of Gougar, which this is, and to say, ‘Okay, they’re ready to go now. No, you need to wait,'” Baldermann said. “That’s very unusual for us to say that… But we’re doing everything we can to accommodate the residents and the business owner.”

Both the Development Agreement and the rezoning ordinances passed on 6-0 roll call votes.

Leave a Comment





Latest News Stories

WCO-PZ-July-15

Will County Planners OK Oversized Garage Near Naperville, Overriding Staff Recommendation

The Will County Planning and Zoning Commission on Tuesday approved variances for a new oversized accessory garage in Wheatland Township, siding with a homeowner and builder over a staff recommendation...
WCO-PZ-July-15

Green Garden Landscaping Business Gains Permit Amid Strong Neighbor Support

A small landscaping and lawn maintenance business operating on a residential property in Green Garden Township received official approval Tuesday after neighbors voiced overwhelming support for the operation. The Will...
Meeting-Briefs

Meeting Briefs: Will County Planning and Zoning Commission for July 15, 2025

Frankfort Shed Relocation Approved: A homeowner on West Harvest Drive in Frankfort Township received a variance to reduce an east side-yard setback from 10 to 4 feet. The variance, sought by...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves ‘Whisk & Flame’ Culinary Studio, Slashes Parking Requirement for Downtown Property

An experiential culinary studio named Whisk & Flame is set to open in downtown Frankfort after the Village Board approved a series of special use permits and a significant parking...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Village Board Adopts $59.4 Million Appropriation for Fiscal Year 2026

The Frankfort Village Board has formally set its maximum legal spending limit for the upcoming fiscal year, adopting a $59,366,900 appropriation ordinance for fiscal year 2026. The measure was passed...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Establishes New Zoning Rules to Attract Data Centers

The Village of Frankfort has amended its zoning ordinance to create a specific use category for data centers, a move designed to regulate and attract high-tech development. The Village Board...
Frankfort-Village-Board-Meeting-Graphic

Currie Motors Expansion Gets Approval with Site Modifications

Currie Motors on Lincoln Highway received approval from the Frankfort Village Board on Monday for a major change to its site plan, allowing for the construction of seven new parking...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves $134,531 Maintenance Contract for Wastewater Plant Filters

The Frankfort Village Board has approved a $134,531.17 agreement with Veolia Water Technologies, Inc. for critical preventative maintenance at the Regional Wastewater Treatment Plant. The contract is for the complete...
Frankfort-Village-Board-Meeting-Graphic

Meeting Briefs: Frankfort Village Board for July 14, 2025

'Whisk & Flame' Culinary Studio Approved: The board approved "Whisk & Flame," an experiential culinary studio, for 10-12 Elwood Street. The project includes four special use permits for entertainment, liquor sales,...
WCO-Exec-Cmte-July-10.1

County Approves School Resource Officer, Multi-Year Planning Requirements

Will County approved hiring an additional sheriff's deputy for a school resource officer position that will be fully funded by Summit Hill School District 161, while also passing new transparency...
WCO-Exec-Cmte-July-10.2

County Addresses Senior Tax Exemption Processing Error

A processing error that cost County Board member Julie Berkowicz $600 in senior tax exemptions has prompted discussions about improving verification systems for property tax breaks. Will County Chief Assessment...
Meeting-Briefs

Executive Committee Meeting July 10 Meeting Briefs

Liquor License Expansion: The county approved increasing Class C1 liquor licenses from eight to nine to accommodate Lockport Gas and Food LLC at 14747 W. 159th Street in Homer Glen....
frankfort-park-district

Meeting Briefs: Frankfort Park District Board for June 10, 2025

The Frankfort Park District Board of Commissioners discussed a legal dispute with the Five Oaks homeowners association over park development rules at its Tuesday meeting. Executive Director Gina Hassett reported...
Will-County-Land-Use-July-3.1

Committee Rejects Troy Township Solar Projects Amid Strong Local Opposition

The Will County Land Use and Development Committee recommended denial for two controversial commercial solar energy projects in Troy Township on Thursday, following a wave of opposition from local municipalities,...
Will-County-Land-Use-July3.2

Controversial DuPage Township Rezoning for Outdoor Storage Advances

A contentious proposal to rezone a 20-acre parcel in DuPage Township from agricultural (A-1) to heavy industrial (I-3) for an outdoor vehicle storage facility narrowly passed the Will County Land...