New Lenox Fire District Holds Public Hearing on $3.25 Million Bond as Station 2 Expansion Pushes Ahead of Schedule
New Lenox Fire Protection District Meeting | March 16, 2026
Article Summary:
The New Lenox Fire Protection District Board of Trustees held a mandated public hearing regarding the issuance of up to $3.25 million in General Obligation Bonds to finance the ongoing Station 2 remodel. Meanwhile, fire officials reported the massive construction project is moving faster than anticipated, currently running a full month ahead of schedule.
Fire Station 2 Expansion Key Points:
-
Bond Hearing: The Board opened a public hearing concerning the intent to sell up to $3,250,000 in General Obligation Bonds (Alternate Revenue Source).
-
Construction Progress: Deputy Chief Randolph reported that the expansion and remodeling work at Fire Station #2 is currently about a month ahead of schedule.
-
No Public Objection: The public hearing was opened and closed rapidly, with no members of the public stepping forward to ask questions or raise concerns regarding the bond issuance.
The New Lenox Fire Protection District Board of Trustees on Monday, March 16, 2026, executed the next necessary legislative step to secure funding for the District’s primary capital improvement project, while receiving highly positive updates on the facility’s construction timeline.
The Board opened a formal public hearing concerning the District’s intent to sell not to exceed $3,250,000 of General Obligation Bonds (Alternate Revenue Source). The bond funds are strictly dedicated to financing the ongoing expansion and remodeling of Fire Station #2.
The public hearing was opened at 6:02 p.m. following a motion by Trustee Scanlan and a second by Trustee Popp. The hearing generated no questions or comments from the public and was subsequently closed at 6:02 p.m. following a motion by Trustee Levey and a second by Trustee Scanlan. The procedural closure passed on a 4-0 roll call vote, with Trustee Sauter absent from the meeting.
While the financing mechanisms are being finalized, the physical work at the site is exceeding expectations. During his departmental report, Deputy Chief Randolph updated the Board on the status of the renovations.
“The Station 2 project looks to be about a month ahead of schedule,” Randolph stated.
The accelerated timeline comes after the Board authorized critical concrete, asphalt, and storm sewer work for the site during its February meeting. The Board took no further action regarding Station 2 during the March meeting.
Latest News Stories
Land Use Committee Advances Mokena Scrap Yard and Homer Glen Landscape Business Over Local Objections
District 210 Reports Insurance Deficit Amid National Healthcare Cost Spikes; Finances Remain Stable
Foxx to face questions about murder conviction review ‘investigations’
Illinois Quick Hits: North Chicago manufacturing expansion announced
Local government advocates oppose Pritzker plan to cut distributions
New Lenox Fire District Exploring Land Swap with Village for New Training Facility
WATCH: Illinois diversity leaders dodge questions as they slip farther from goals
Illinois Quick Hits: Road fund could help renovate Soldier Field
Planning Commission Backs 5-MW Peotone Solar Farm; Developer Pledges Pollinator Habitat and Community Funds
Joliet Junior College Board Approves $2 Tuition Increase Amidst Heated Debate Over Enrollment and Spending
New Lenox District 122 Kicks Off 2026-2027 Budget Cycle, Approves Minor Registration Fee Increase
New Lenox Park District Outlines Aggressive 2026 Development Plan, Addresses Crossroads Sinkhole
New Lenox Library Explores Rebranding Ahead of 25th Anniversary on the Commons
Lincoln-Way Board Ratifies Three-Year Support Staff Contract with Significant Hourly Raises