New Lenox Fire District Holds Public Hearing on $3.25 Million Bond as Station 2 Expansion Pushes Ahead of Schedule
New Lenox Fire Protection District Meeting | March 16, 2026
Article Summary:
The New Lenox Fire Protection District Board of Trustees held a mandated public hearing regarding the issuance of up to $3.25 million in General Obligation Bonds to finance the ongoing Station 2 remodel. Meanwhile, fire officials reported the massive construction project is moving faster than anticipated, currently running a full month ahead of schedule.
Fire Station 2 Expansion Key Points:
-
Bond Hearing: The Board opened a public hearing concerning the intent to sell up to $3,250,000 in General Obligation Bonds (Alternate Revenue Source).
-
Construction Progress: Deputy Chief Randolph reported that the expansion and remodeling work at Fire Station #2 is currently about a month ahead of schedule.
-
No Public Objection: The public hearing was opened and closed rapidly, with no members of the public stepping forward to ask questions or raise concerns regarding the bond issuance.
The New Lenox Fire Protection District Board of Trustees on Monday, March 16, 2026, executed the next necessary legislative step to secure funding for the District’s primary capital improvement project, while receiving highly positive updates on the facility’s construction timeline.
The Board opened a formal public hearing concerning the District’s intent to sell not to exceed $3,250,000 of General Obligation Bonds (Alternate Revenue Source). The bond funds are strictly dedicated to financing the ongoing expansion and remodeling of Fire Station #2.
The public hearing was opened at 6:02 p.m. following a motion by Trustee Scanlan and a second by Trustee Popp. The hearing generated no questions or comments from the public and was subsequently closed at 6:02 p.m. following a motion by Trustee Levey and a second by Trustee Scanlan. The procedural closure passed on a 4-0 roll call vote, with Trustee Sauter absent from the meeting.
While the financing mechanisms are being finalized, the physical work at the site is exceeding expectations. During his departmental report, Deputy Chief Randolph updated the Board on the status of the renovations.
“The Station 2 project looks to be about a month ahead of schedule,” Randolph stated.
The accelerated timeline comes after the Board authorized critical concrete, asphalt, and storm sewer work for the site during its February meeting. The Board took no further action regarding Station 2 during the March meeting.
Latest News Stories
Executive Committee Considers $12,000 Strategic Planning Initiative with University of St. Francis
Illinois takes over health insurance marketplace in 2026 amid skepticism
WATCH: IL state reps challenge IEMA-OHS responses to local agencies
Judge expands restraining order against ‘Beto’ O’Rourke, adds ActBlue
Reversing Biden’s precedent, students complete FAFSA in minutes at beta-testing event
Trump, Zelenskyy to meet Monday in steps toward peace with Russia
Executive Committee Members Decry Roadside Litter, Call for Action Against Garbage Haulers
Possible ‘agreement’ reached in Trump-Putin meeting; more discussion likely
WATCH: Gun rights supporters celebrate 9th Circuit’s ruling against CA gun rationing law
Feds sue California over emission standards for trucks
Illinois quick hits: ‘Lawsuit inferno’ bill takes effect after Pritzker signed 267 measures Friday
WATCH: UW-authored study on surgery times contradicts CMS basis for reimbursement cuts