New Lenox Park District

New Lenox Park District Initiates Nearly Half of its 45-Site ADA Audits, Prepares for Massive Spring Construction

Spread the love

New Lenox Community Park District Board of Commissioners Meeting | March 18, 2026

Article Summary:
The New Lenox Community Park District is moving rapidly on its district-wide accessibility audit, completing evaluations at 19 parks in less than a week. The swift administrative progress mirrors an aggressive spring construction schedule, highlighted by the imminent resumption of the Sharon’s Bay Park redevelopment and the ordering of a new playground for Cherry Hill.

Park Development and Audits Key Points:

  • ADA Audits: The district successfully audited 19 park sites between March 9 and March 13, marking nearly 50% completion of the ADA Transition Plan assessment.

  • Cherry Hill Playground: A new playground has been ordered for Cherry Hill through Sourcewell, funded by bond money.

  • Crossroads Repairs: Maintenance staff are working with the Motz group to repair a sinkhole on Field 8 and set new concrete base pegs at the Crossroads Sports Complex.

  • Spring Resumption: Major site work at both Sharon’s Bay Park and Teerling Lakes Central Park will resume as soon as the weather breaks.

The New Lenox Community Park District Board of Commissioners on Wednesday, March 18, 2026, reviewed an aggressive timeline of ongoing park audits and imminent spring construction projects designed to modernize the district’s aging infrastructure.

Commissioner Larson provided a highly positive update on the district’s sweeping ADA Assessment Transition Plan. He reported that between March 9 and March 13, specialized teams successfully audited 19 separate park sites for accessibility compliance. With roughly half of the district’s 45 sites evaluated in less than a week, Larson noted the teams are well on track to complete the remaining audits shortly.

As the audits map out future accessibility upgrades, the district’s maintenance department is preparing to break ground on several major capital projects. Director of Parks-Maintenance Ken Stephens announced that a new playground replacement for Cherry Hill has been officially ordered through the Sourcewell cooperative purchasing program. The project is being fully funded by recently issued bond money.

Stephens also reported that the Bristol Park Land Drainage Mitigation project is ready for the market. The project was scheduled to go out to bid on March 23, with an official bid opening date set for April 8.

As the weather thaws, heavy machinery will return to several ongoing massive developments. Stephens confirmed that all work on the highly anticipated Sharon’s Bay Park Redevelopment, funded by an OSLAD Grant, will resume in April or May. Furthermore, all site work for the Teerling Lakes Central Park Development is slated to begin this spring.

Maintenance crews are also troubleshooting minor issues at the newly opened Crossroads Sports Complex. Larson reported that a sinkhole identified on Field 8 is scheduled to be repaired. Additionally, the district is working with the specialized turf group Motz to set base pegs in concrete, allowing the home plate turf to be easily interchangeable for both baseball and softball configurations.

While managing existing properties, Executive Director Greg Lewis informed the Board that the district is actively participating in meetings with the Village of New Lenox regarding several new residential developments approaching the village. Lewis emphasized that the park district intends to work closely with developers to secure “turnkey parks” for the community as part of any new residential expansions.

Leave a Comment





Latest News Stories

Will County Previews ‘GuideWill’ Comprehensive Resource Management Plan

Will County Land Use & Development Committee Meeting | March 2026 Article Summary: Will County's Land Use Department unveiled the branding, interactive tools, and initial timeline for its updated Resource Management...
Will County Board Graphic.04

Will County Targets May Draft for Comprehensive Artificial Intelligence Policy

Capital Improvements & IT Committee Meeting | March 2026 Article Summary:Will County is moving closer to adopting a formal Artificial Intelligence policy, with IT staff planning to deliver a comprehensive...
New Lenox Park District

Sanctuary Golf Course Prepares for 30th Anniversary Following Strong January Sales and Facility Upgrades

New Lenox Community Park District Board of Commissioners Meeting | February 18, 2026 Article Summary:The Sanctuary Golf Course outperformed the previous year's winter metrics, buoyed by the popularity of its...
Will County P&Z Logo Planning Zoning.2

P&Z Commission Approves Side Yard Setback Variance for Joliet Detached Garage

Will County Planning and Zoning Commission Meeting | March 3, 2026 Article Summary: The Will County Planning and Zoning Commission approved a variance to reduce a side yard setback on...
Will County Board Graphic.01

Executive Committee Advances Sweeping Overhaul of Will County Business Regulations

Will County Executive Committee Meeting | March 12, 2026 Article Summary: Will County is poised to modernize its business regulations following the Executive Committee's unanimous approval of a massive ordinance overhaul....
Will County Finance Logo

Will County Closes Out $16.2 Million Federal Rental Assistance Program, Transitions to Local Funding

Will County Finance Committee Meeting | March 3, 2026 Article Summary: Will County has officially closed out its massive federal Emergency Rental Assistance program after distributing millions to keep nearly 2,000...
Will County P&Z Logo Planning Zoning

Meeting Summary and Briefs: Will County Planning and Zoning Commission for March 3, 2026

Will County Planning and Zoning Commission Meeting | March 3, 2026 Overall Meeting SummaryThe Will County Planning and Zoning Commission convened on Tuesday, March 3, 2026, to review a series...
will county Committee-Capital Improvement.Graphic

Will County Leaders Debate New Construction to Escape $1.2 Million in Leases

Capital Improvements & IT Committee Meeting | March 2026 Article Summary: The Will County Capital Improvements and IT Committee is aggressively exploring options to consolidate county offices and exit leased...
Will County Finance Logo

Opioid Settlement Grants Funnel Nearly $600,000 to Local Police and Community Programs

Will County Finance Committee Meeting | March 3, 2026 Article Summary: Will County is distributing a significant portion of its opioid settlement funds to hyper-local agencies, including the Peotone and Manhattan...
Will County Finance Logo

Meeting Summary and Briefs: Will County Finance Committee for March 3, 2026

Will County Finance Committee Meeting | March 3, 2026 The Will County Board Finance Committee met on Tuesday to review a slate of year-end financial reports and approve routine budget...
About Us Website Header - 1

Meeting Summary and Briefs: New Lenox Public Library District Board of Trustees for February 17, 2026

New Lenox Public Library District Board of Trustees Meeting | February 17, 2026 The New Lenox Public Library District Board of Trustees managed a concise agenda during its regular meeting...
New Lenox Township.2

New Lenox Township Cemeteries Rebound with January Profit as Maplewood Expansion Talks Progress

New Lenox Township Board of Trustees Meeting | February 12, 2026 Article Summary:Following a net loss at the end of 2025, New Lenox Township's cemetery operations posted a $5,490.62 profit...
Lincoln Way Central Baseball Graphic

Tingley’s Triples, 13-Strikeout Pitching Performance Power Lincoln-Way Central Past Oswego East 12-1

OSWEGO, Ill. — The Lincoln-Way Central varsity baseball team combined a dominant, two-hit pitching performance with an explosive late-inning offense to roll past Oswego East 12-1 in a non-conference road...
Lincoln Way Central Softball Graphic

Late Sixth-Inning Rally, Timely Hitting Propel Lincoln-Way Central Past St. Laurence 4-1

NEW LENOX, Ill. — A decisive three-run outburst in the bottom of the sixth inning and reliable pitching from the bullpen lifted the Lincoln-Way Central varsity softball team to a...
New Lenox Park District

New Lenox Park District Referendum Task Force Evaluates Funding and Scope for Major Capital Projects

New Lenox Community Park District Board of Commissioners Meeting | February 18, 2026 Article Summary:The New Lenox Community Park District's newly formed Referendum Task Force has officially launched, holding its...