New Lenox Park District

New Lenox Park District Initiates Nearly Half of its 45-Site ADA Audits, Prepares for Massive Spring Construction

Spread the love

New Lenox Community Park District Board of Commissioners Meeting | March 18, 2026

Article Summary:
The New Lenox Community Park District is moving rapidly on its district-wide accessibility audit, completing evaluations at 19 parks in less than a week. The swift administrative progress mirrors an aggressive spring construction schedule, highlighted by the imminent resumption of the Sharon’s Bay Park redevelopment and the ordering of a new playground for Cherry Hill.

Park Development and Audits Key Points:

  • ADA Audits: The district successfully audited 19 park sites between March 9 and March 13, marking nearly 50% completion of the ADA Transition Plan assessment.

  • Cherry Hill Playground: A new playground has been ordered for Cherry Hill through Sourcewell, funded by bond money.

  • Crossroads Repairs: Maintenance staff are working with the Motz group to repair a sinkhole on Field 8 and set new concrete base pegs at the Crossroads Sports Complex.

  • Spring Resumption: Major site work at both Sharon’s Bay Park and Teerling Lakes Central Park will resume as soon as the weather breaks.

The New Lenox Community Park District Board of Commissioners on Wednesday, March 18, 2026, reviewed an aggressive timeline of ongoing park audits and imminent spring construction projects designed to modernize the district’s aging infrastructure.

Commissioner Larson provided a highly positive update on the district’s sweeping ADA Assessment Transition Plan. He reported that between March 9 and March 13, specialized teams successfully audited 19 separate park sites for accessibility compliance. With roughly half of the district’s 45 sites evaluated in less than a week, Larson noted the teams are well on track to complete the remaining audits shortly.

As the audits map out future accessibility upgrades, the district’s maintenance department is preparing to break ground on several major capital projects. Director of Parks-Maintenance Ken Stephens announced that a new playground replacement for Cherry Hill has been officially ordered through the Sourcewell cooperative purchasing program. The project is being fully funded by recently issued bond money.

Stephens also reported that the Bristol Park Land Drainage Mitigation project is ready for the market. The project was scheduled to go out to bid on March 23, with an official bid opening date set for April 8.

As the weather thaws, heavy machinery will return to several ongoing massive developments. Stephens confirmed that all work on the highly anticipated Sharon’s Bay Park Redevelopment, funded by an OSLAD Grant, will resume in April or May. Furthermore, all site work for the Teerling Lakes Central Park Development is slated to begin this spring.

Maintenance crews are also troubleshooting minor issues at the newly opened Crossroads Sports Complex. Larson reported that a sinkhole identified on Field 8 is scheduled to be repaired. Additionally, the district is working with the specialized turf group Motz to set base pegs in concrete, allowing the home plate turf to be easily interchangeable for both baseball and softball configurations.

While managing existing properties, Executive Director Greg Lewis informed the Board that the district is actively participating in meetings with the Village of New Lenox regarding several new residential developments approaching the village. Lewis emphasized that the park district intends to work closely with developers to secure “turnkey parks” for the community as part of any new residential expansions.

Leave a Comment





Latest News Stories

Meeting-Briefs

Meeting Briefs: Frankfort Village Board for June 2, 2025

Wendy's Project Approved with Multiple Variances: The Village Board gave final approval for a new Wendy's restaurant at U.S. Route 30 and Frankfort Square Road. The project required a major change...
frankfort-park-district.1

Frankfort Park Board Holds Closed-Door Talks on Five Oaks HOA Dispute

The Frankfort Park District Board of Commissioners entered into a closed executive session on Tuesday, May 27, to discuss pending litigation concerning the Five Oaks Park parcel, signaling a deepening...
Frankfort-Township-Logo-Graphic

Frankfort Township Approves Employee Raises, Details Major Infrastructure and Service Projects

Frankfort Township employees will receive a 2.5% cost-of-living pay increase after the Board of Trustees unanimously approved the adjustment at its Monday, May 19 meeting. The move came as Supervisor...
Frankfort-Township-Logo-Graphic

New High-End Bar ‘Ace & Vine’ Gets Green Light from Township Board

A new bar focused on high-end liquor and an extensive wine collection is one step closer to opening in Frankfort Township after the Board of Trustees voted to recommend a...
Frankfort-Township-Logo-Graphic

Golf Carts Not Permitted on Township Roads, Supervisor Clarifies

Residents hoping to drive golf carts on roads in unincorporated Frankfort Township are out of luck, as the practice is illegal under state law, Supervisor Nick George clarified at the...
Frankfort-Township-Logo-Graphic

Meeting Briefs: Frankfort Township Board for May 19, 2025

The Frankfort Township Board approved a 2.5% cost-of-living raise for its employees and discussed several major projects at its meeting on Monday, May 19. Supervisor Nick George announced that the...
Screenshot-2025-06-16-at-3.26.08-PM

Will County Board Rejects Two Solar Farm Projects After Heated Public Opposition

New Lenox area residents cite safety concerns, property values in opposing commercial solar facilities The Will County Board voted decisively against two proposed commercial solar energy facilities during its May...
will-county-board.3

County Approves $15 Million Water System Takeover for Southeast Joliet Area

700 homes to receive upgraded service as Joliet takes control of failing sanitary district The Will County Board voted 20-1 to support dissolving the Southeast Joliet Sanitary District and transferring...
will-county-board

Board Postpones County Purchasing Code Overhaul Amid Union Contractor Debate

Members seek clarification on requirements that could favor unionized businesses The Will County Board postponed action on proposed changes to county purchasing ordinances after members raised concerns about language that...
frankfort-square-park-district.2

New Frankfort Square Park Board Takes Helm Amid Strong Financials, Maksymiak and Moore Elected Leaders

The Frankfort Square Park District Board of Commissioners seated four new members and re-elected its leadership during a productive annual organizational meeting on May 15, all while celebrating a robust...
will-county-board.2

Animal Permit Hearing Reveals Neighborhood Disputes Over Horses, Roosters in Crete Township

Board postpones decision on Torres family request pending barn variance appeal A contentious hearing over Fernando Torres' request to keep horses on his Crete Township property exposed deep neighborhood divisions...
frankfort-square-park-district.1

Park District Awards Eight Scholarships to Lincoln-Way East Seniors

The Frankfort Square Park District awarded $1,000 scholarships to eight graduating seniors from Lincoln-Way East High School at the school’s Community Scholarship Night on May 7. Park Board Commissioners Frank...
will-county-board.3

Transportation Projects Advance as Board Approves Vision Zero, Road Improvements

County adopts traffic safety initiative while funding major infrastructure upgrades The Will County Board approved a comprehensive transportation agenda including adoption of Vision Zero principles and multiple road improvement projects...
County-Board-Room

Health Department Receives Budget Boost, Sunny Hill Admission Policy Updated

Board approves funding increases and policy changes for county health services The Will County Board approved budget appropriations for the health department and updated admission policies for Sunny Hill Nursing...
Meeting-Briefs

Meeting Briefs: Frankfort Square Park District for May 15, 2025

At its annual organizational meeting, the Frankfort Square Park District Board of Commissioners swore in four members, re-elected its leadership, and reviewed its strong end-of-year financial report. The district’s funds...