New Lenox Community Park District Board of Commissioners Meeting | March 18, 2026

Article Summary:
The New Lenox Community Park District is moving rapidly on its district-wide accessibility audit, completing evaluations at 19 parks in less than a week. The swift administrative progress mirrors an aggressive spring construction schedule, highlighted by the imminent resumption of the Sharon’s Bay Park redevelopment and the ordering of a new playground for Cherry Hill.

Park Development and Audits Key Points:

  • ADA Audits: The district successfully audited 19 park sites between March 9 and March 13, marking nearly 50% completion of the ADA Transition Plan assessment.

  • Cherry Hill Playground: A new playground has been ordered for Cherry Hill through Sourcewell, funded by bond money.

  • Crossroads Repairs: Maintenance staff are working with the Motz group to repair a sinkhole on Field 8 and set new concrete base pegs at the Crossroads Sports Complex.

  • Spring Resumption: Major site work at both Sharon’s Bay Park and Teerling Lakes Central Park will resume as soon as the weather breaks.

The New Lenox Community Park District Board of Commissioners on Wednesday, March 18, 2026, reviewed an aggressive timeline of ongoing park audits and imminent spring construction projects designed to modernize the district’s aging infrastructure.

Commissioner Larson provided a highly positive update on the district’s sweeping ADA Assessment Transition Plan. He reported that between March 9 and March 13, specialized teams successfully audited 19 separate park sites for accessibility compliance. With roughly half of the district’s 45 sites evaluated in less than a week, Larson noted the teams are well on track to complete the remaining audits shortly.

As the audits map out future accessibility upgrades, the district’s maintenance department is preparing to break ground on several major capital projects. Director of Parks-Maintenance Ken Stephens announced that a new playground replacement for Cherry Hill has been officially ordered through the Sourcewell cooperative purchasing program. The project is being fully funded by recently issued bond money.

Stephens also reported that the Bristol Park Land Drainage Mitigation project is ready for the market. The project was scheduled to go out to bid on March 23, with an official bid opening date set for April 8.

As the weather thaws, heavy machinery will return to several ongoing massive developments. Stephens confirmed that all work on the highly anticipated Sharon’s Bay Park Redevelopment, funded by an OSLAD Grant, will resume in April or May. Furthermore, all site work for the Teerling Lakes Central Park Development is slated to begin this spring.

Maintenance crews are also troubleshooting minor issues at the newly opened Crossroads Sports Complex. Larson reported that a sinkhole identified on Field 8 is scheduled to be repaired. Additionally, the district is working with the specialized turf group Motz to set base pegs in concrete, allowing the home plate turf to be easily interchangeable for both baseball and softball configurations.

While managing existing properties, Executive Director Greg Lewis informed the Board that the district is actively participating in meetings with the Village of New Lenox regarding several new residential developments approaching the village. Lewis emphasized that the park district intends to work closely with developers to secure “turnkey parks” for the community as part of any new residential expansions.

Leave a Comment





Latest News Stories

Screenshot-2025-08-13-at-2.15.28-PM

Monee to Receive $250,000 Donation in Solar Project Agreement

Article Summary: The Village of Monee will receive a $250,000 donation from TPE IL W1202, LLC, after the Village Board authorized a community benefit agreement for a planned 5-megawatt solar...
new-lenox-park-district.6

New Lenox Park District Board Approves 2025-2026 Budget

NEW LENOX – The New Lenox Community Park District Board of Commissioners unanimously approved the budget and appropriation ordinance for the 2025-2026 fiscal year during its regular meeting on June...
New-Lenox-School-122.6

Staffing Shortage Leads D122 to Renew Contract for School Psychologist

Facing a persistent staffing shortage for a critical role, the New Lenox School District 122 Board of Education has renewed its contract with an outside agency to provide a school...
Meeting-Briefs

Meeting Summary: New Lenox Township for June 12, 2025

At its June 12 meeting, the New Lenox Township Board of Trustees heard reports on rising demand for community services, discussed ongoing maintenance projects, and assigned responsibilities to its newly...
New-Lenox-Village-Board.4

New Lenox Approves Major Residential Subdivision, Paves Way for Route 6 Commercial Growth

NEW LENOX – The Village Board took decisive action on two major developments Monday, giving final approval to a 55-lot residential subdivision for "empty nesters" and clearing a key hurdle...
New-Lenox-Sharons-Bay-Park

Contractor Selected for Sharon’s Bay Park Redevelopment

NEW LENOX – The New Lenox Community Park District is moving forward with plans to redevelop Sharon's Bay Park, having approved a contractor for the project at its Wednesday meeting....
New-Lenox-Sharons-Bay-Park

Contractor Selected for Sharon’s Bay Park Redevelopment

NEW LENOX – The New Lenox Community Park District is moving forward with plans to redevelop Sharon's Bay Park, having approved a contractor for the project at its Wednesday meeting....
New-Lenox-School-122.5

Handbook Changes at D122 Include Swapping PSAT for PreACT

Students in New Lenox School District 122 will see several changes in the upcoming school year, as the Board of Education approved updates to the 2025-2026 Parent/Student Handbook that affect...
New-Lenox-Police.3

New Dining Options Coming as Village Approves Hot Dog Stand, Restaurant Patio

NEW LENOX – The local dining scene is set for a boost after the Village Board on Monday approved plans for a new hot dog stand and an outdoor patio...
Meeting-Briefs

Meeting Summary: New Lenox Park District for June 18, 2025

The New Lenox Community Park District Board of Commissioners met on June 18, 2025, to approve its annual budget, advance key park projects, and hear updates on a wide range...
Screenshot-2025-08-13-at-2.11.44-PM

Monee Board Sets Spending Plan with 2025-2026 Appropriations Ordinance

Article Summary: The Monee Village Board has approved its annual appropriations ordinance, which acts as the village's legal spending authority for the fiscal year that began May 1, 2025. The...
New-Lenox-School-122.3

New Lenox School District 122 Honors State Track and Field Athletes

New Lenox School District 122 took time during its June 17 board meeting to celebrate the outstanding achievements of its junior high athletes at the 2025 IESA State Track and...

Fiber Optic Internet Competition Coming to New Lenox

NEW LENOX – Residents may soon have a new choice for high-speed internet, as Champaign-based Pavlov Media announced its intention to build out a fiber optic network across the village....
Screenshot-2025-08-13-at-2.15.28-PM

Monee Officials Issue Pool Safety Alert Amid Summer Heat

Article Summary: Following an increase in new pool installations, Monee's Building Services department is reminding residents of mandatory permit and safety requirements. Officials are emphasizing life-safety measures to prevent drownings,...
New-Lenox-Village-Board

Village Board Approves Millions in Spending on Roads, Parks, and Museum

NEW LENOX – The New Lenox Village Board authorized millions of dollars in spending on Monday for its annual road program and for continued investment in its newest community amenities,...