NAACP sues xAI over air pollution near Memphis data center

NAACP sues xAI over air pollution near Memphis data center

Spread the love

The NAACP filed a lawsuit in federal court Tuesday against Elon Musk’s xAI, saying the company is illegally operating 27 methane gas turbines in Mississippi to power its Colossus 2 data center complex across the state line in Memphis.

In the lawsuit filed in the U.S. District Court for the Northern District of Mississippi, the NAACP says emissions from the gas turbines violate the Clean Air Act. The Colossus 2 data center near Memphis is the primary training facility for Grok-4, xAI’s next generation chatbot.

The NAACP says between August and December, xAI and its subsidiary MZX Tech, operated 27 gas turbines in Southaven, Miss., “without an air permit or regard for the health and safety of people living nearby.”

Represented by Earthjustice and the Southern Environmental Law Center, the NAACP is suing to halt xAI’s operations until the company obtains permits, installs the most effective pollution controls available, and pays financial penalties for every day that air quality violations occurred.

In response to the legal action, xAI confirmed commitment to environmental standards.

“The temporary power generation units are operating in compliance with all applicable laws,” a company statement said.

“A data center should not be a potential death sentence for a community’s health,” said Abre’ Conner, NAACP director of environmental and climate justice. “By looking to evade clean air laws to operate dirty turbines that emit pollution and known carcinogens, these companies are following a shameful, familiar pattern: asking Black and frontline communities to bear the toxic brunt of ‘innovation.’”

The Southern Environmental Law Center says xAI’s failure to obtain a permit for the power generation plant created health risks for families in northern Mississippi and Memphis in violation of the Clean Air Act, which requires major sources of pollution to obtain air permits before beginning construction or operations.

The plaintiffs contend the gas turbines emit pollutants like formaldehyde and nitrogen oxides into predominantly Black communities already overburdened by industrial pollution.

The NAACP says in the lawsuit that the gas turbines on the Colossus 2 site could potentially emit over 1,700 tons of nitrogen oxides annually, which would make it the largest industrial source of the pollutant in the 11-county Memphis metropolitan area.

The lawsuit filed Tuesday by the NAACP follows a legal fight in 2025 over xAI’s use of gas turbines without permits to power the Colossus 1 data center. In 2024, Mississippi and Tennessee officials allowed xAI to operate gas turbines without a permit because they were classified as “temporary” and “mobile” units intended to run for less than a year. Under this “temporary-mobile” exemption, no official tracking of toxic releases was required.

In June 2025, after the NAACP and the Southern Environmental Law Center issued a formal notice of intent to sue, xAI removed 20 turbines from the Colossus 1 site and eventually obtained permits for the remaining 15 units.

The Colossus 2 data center will host 555,000 Nvidia GPUs and that potentially require 2 gigawatts of generation capacity, according to xAI. At the Colossus 2 site, the company plans to train chatbots with improvements over previous versions that include advanced reasoning abilities, faster data processing, and near-instant response times for end users.

To help manage the massive power load, xAI reports it has deployed about 600 industrial-grade batteries with approximately 2.3 gigawatt-hours of storage designed to provide energy buffer at times of high energy usage by the Colossus data center while also capable of supplying the local grid during peak demand.

According to the NAACP, the gas turbines at the site still pose a significant risk, with potential annual emissions of 180 tons of fine particulate matter, 500 tons of carbon monoxide, and 19 tons of formaldehyde – a toxic, cancer-causing chemical.

“xAI’s continued operation of these turbines without a permit and without adequate pollution controls is not only illegal, it’s an insult to families living nearby who for months have expressed serious concerns about how air pollution from the company’s personal power plant could impact their health and well-being,” said Ben Grillot, senior attorney at the Southern Environmental Law Center, a party in the lawsuit.

Leave a Comment





Latest News Stories

Will County Board Land Use Committee Graphic.2

Land Use & Development Committee forwards Women’s Residential Recovery Center

Will County Land Use & Development Committee Meeting | December 2025 Article Summary: The Will County Land Use and Development Committee unanimously recommended approval for a new women-specific residential rehabilitation...
Screenshot 2025-12-10 at 12.18.47 PM

Board Reviews Special Use for Landscape Business Near Cedar Road S-Curve

New Lenox Village Board of Trustees Meeting | Dec. 8, 2025 Article Summary: The Village Board voted not to object to a Will County special use request for a landscaping...
WCO Committee of the Whole

Will County Board Members Question Fairness of New Transit Tax Structure

Will County Committee of the Whole Meeting | December 2025 Article Summary: Will County Board members expressed concerns regarding the funding mechanisms and governance structure of the incoming Northern Illinois...
Will County P&Z Logo Planning Zoning

P&Z Commission Advances Plan for Construction Debris Fill Operation on Brandon Road

Will County Planning and Zoning Commission Meeting | December 2, 2025 Article Summary: The Will County Planning and Zoning Commission recommended approval for a map amendment and special use permit...
WCO Committee of the Whole

Regional Transit Agencies Tout New State Funding, Prepare for Shift to ‘NITA’

Will County Committee of the Whole Meeting | December 2025 Article Summary: Regional transit leaders presented their 2026 budgets to the Will County Board, highlighting that the recent passage of...
Screenshot 2025-12-10 at 12.18.04 PM

Village Considers Phasing Out Impact Fee Reductions as Growth Continues

New Lenox Village Board of Trustees Meeting | Dec. 8, 2025 Article Summary: The New Lenox Village Board advanced a proposal to gradually phase out a long-standing 30% reduction in...
Will County Board Land Use Committee Graphic.3

New Lenox Used Car Dealership Approved by Land Use & Development Committee

Will County Land Use & Development Committee Meeting | December 2025 Article Summary: A special use permit for a used car dealership on Ford Drive in New Lenox Township was...
Will County Board Land Use Committee Graphic.1

Land Use Committee: Monee Solar Projects Granted Extensions; Battery Storage Plans Dropped

Will County Land Use & Development Committee Meeting | December 2025 Article Summary: The Will County Land Use and Development Committee granted time extensions for two separate solar farm projects...
Will County P&Z Logo Planning Zoning.2

P&Z Commission: New Women’s Recovery Center Proposed for Patterson Road Receives Support

Will County Planning and Zoning Commission Meeting | December 2, 2025 Article Summary: The Planning and Zoning Commission unanimously recommended approval for a new inpatient drug and alcohol rehabilitation facility...
Judy Ogalla

Ogalla Blasts New State Solar Legislation

Will County Land Use & Development Committee Meeting | December 2025 Article Summary: During a discussion on zoning matters, Will County Board Member Judy Ogalla strongly criticized the passage of...
Will County Board Land Use Committee Graphic.4

Committee Postpones Vote on Brandon Road Fill Operation After Tree Clearing Allegations

Will County Land Use & Development Committee Meeting | December 2025 Article Summary: The Will County Land Use and Development Committee voted to postpone a decision on a proposed clean...
Meeting Briefs

Meeting Summary and Briefs: Will County Planning and Zoning Commission for December 2, 2025

Will County Planning and Zoning Commission Meeting | December 2, 2025 Overall Meeting SummaryThe Will County Planning and Zoning Commission met on December 2, 2025, to consider a variety of...
Metra

Metra Announces No Fare Hikes; Highlights Bridge Projects in Joliet and Mokena

Will County Committee of the Whole Meeting | December 2025 Article Summary: Metra officials presented a balanced 2026 budget to the Will County Board, confirming that riders will not see...
Screenshot 2025-12-10 at 12.22.10 PM

New Lenox Village Board Approves 2025 Tax Levy; Tax Rate Projected to Decrease

New Lenox Village Board of Trustees Meeting | Dec. 8, 2025 Article Summary: The New Lenox Village Board of Trustees approved the 2025 tax levy following a public hearing, with...

Public Works Committee: Will County Consolidates Paratransit Services Amid Funding Debates

Public Works & Transportation Committee Meeting | December 2, 2025 Article Summary: The Will County Board’s Public Works Committee advanced an agreement to consolidate paratransit services into a single countywide...