—Photo by Glenn P. Knoblock

Forest Preserve District Advances Major Extensions and Repairs on Plum Creek Greenway Trail in Crete Township

Spread the love

Article Summary: The Forest Preserve District is currently undertaking dual construction projects on the Plum Creek Greenway Trail, initiating a massive 1.5-mile southern extension through Plum Valley Preserve and commencing repairs on an 80-foot bridge damaged by a fallen tree in Goodenow Grove Nature Preserve.

Plum Creek Greenway Trail Projects Key Points:

  • A new 1.5-mile trail extension will connect Plum Valley Preserve to Goodenow Grove Nature Preserve in Crete Township, with an estimated completion date of fall 2026.

  • The extension features the installation of 800 feet of elevated concrete boardwalks and a 150-foot bridge over Plum Creek, which will become the District’s largest single-span bridge.

  • Repairs began in early March on an 80-foot bridge in Goodenow Grove that was heavily damaged by a fallen tree in January 2025. Contractors are installing new footings, supports, and decking.

  • Future phases of the trail extension aim to connect the path north into Cook County and south to Beecher via the proposed Vincennes Trail.

  • The projects are locally funded by the Forest Preserve District’s Capital Improvement Program and a 2024–2028 grant from the Chicago Metropolitan Agency for Planning.

The Forest Preserve District announced in early March that dual construction projects are currently underway to expand and repair the Plum Creek Greenway Trail, promising significant upgrades for outdoor recreation in Crete Township and the surrounding Will County communities.

The most expansive of the two projects is a new 1.5-mile trail extension that will head south, winding through a hilly section of Plum Valley Preserve. The new multi-use trail will feature a 10-foot-wide path with 3-foot turf shoulders on each side. The extension will consist of a half-mile of crushed limestone, a half-mile of asphalt, and a half-mile street route.

The short street connection will be marked with explicit street signs and pavement directions, leading path users from the newly built trail section to an existing 3.15-mile leg of the Plum Creek Greenway Trail at Goodenow Grove Nature Preserve. The new construction is being added to an existing 1-mile crushed limestone segment that extends south from the Plum Valley Preserve entrance and dog park.

“Upon completion, the project will eliminate a gap in the existing trail system, resulting in a continuous greenway trail connection between Goodenow Grove Nature Preserve and the Plum Valley Preserve – Burville Road access,” said Colleen Novander, the Forest Preserve District’s director of planning and land preservation.

To navigate sensitive ecological areas, contractors are actively installing sections of a precast concrete pedestrian boardwalk to elevate the path. Crews will lay down one 600-foot section and another 200-foot section of boardwalk, utilizing massive concrete components that weigh 4,000 pounds each.

Additionally, concrete abutments are being poured and cured to support a new bridge spanning Plum Creek. Expected to be installed later in April, the 150-foot structure will be the largest single-span bridge in the District.

To minimize environmental impact to existing natural features like wetlands, ravines, and sensitive habitats, the engineering phase dictated that construction remain confined to a designated corridor with a maximum width of 100 feet.

The extension project, which carries an estimated completion date of fall 2026, is funded by the Forest Preserve District’s Capital Improvement Program. Supplemental funding support is provided through the Chicago Metropolitan Agency for Planning’s (CMAP) 2024–2028 Locally Programmed Transportation Alternatives Program (TAP-L).

Looking ahead, District officials noted that future phases of the trail will provide a critical north–south connection, eventually extending the path north into Cook County and south to the Village of Beecher via the proposed Vincennes Trail.

Goodenow Grove Bridge Repairs
While the extension moves forward, a separate set of contractors began repair work in early March on an existing bridge located in the eastern section of Goodenow Grove Nature Preserve, near East Bemes Road.

The 80-foot bridge, which sits just north of the preserve’s well-known “big bridge,” was significantly damaged in January 2025 when a large tree fell on the structure. Following the incident, the District consulted engineers to determine if the bridge required a total replacement or if it could be salvaged. Engineers ultimately concluded that the structure could be repaired.

Originally built in 2011 in tandem with the initial construction of the Plum Creek Greenway Trail and a capital redesign project at Goodenow Grove, the bridge requires extensive rehabilitation. Contractors are currently replacing one of the bridge’s main support structures and pouring new concrete footings. Additionally, all of the bridge’s decking and railings will be entirely replaced.

“It will look like a brand new bridge,” stated Chris Moeller, a Forest Preserve operations department supervisor.

The section of the Plum Creek Greenway Trail affected by the damage has been closed to the public since the tree fell in January. District officials anticipate the repairs will take several weeks to complete, noting that weather and other factors could impact the timeline. The trail segment will officially reopen once the reconstruction is finalized.

—Photo by Glenn P. Knoblock

⚠️ Flood Watch issued June 11 at 10:05AM CDT until June 11 at 11:00PM CDT by NWS Chicago IL
Today Jun 10
Partly Sunny then Showers And Thunderstorms Likely
81° 59°

Partly Sunny then Showers And Thunderstorms Likely

💨 10 to 20 mph 💧 56%

Leave a Comment





Latest News Stories

Screenshot 2025-11-27 at 7.18.58 PM

New Lenox Approves 24/7 Cybersecurity Monitoring

Village of New Lenox Meeting | Nov. 24, 2025 Article Summary: The New Lenox Village Board approved a new contract for around-the-clock cybersecurity detection and response to protect village financial...
Weather-Winter

New Lenox Buried Under 12.3 Inches of Snow; Sub-Zero Cold Snap Approaching Friday

Article Summary: New Lenox residents are digging out from a major winter storm that dropped more than a foot of snow over the weekend. The active weather pattern is forecast...
Will County Board Graphic.01

Frankfort Turns to County for Wildlife & Dangerous Animal Control

Will County Board Meeting | November 2025 Article Summary: The Village of Frankfort has entered into a two-year agreement with Will County Animal Protection Services to handle calls regarding bats...
joliet junior college foundation

JJC Foundation Director Kristin Mulvey to Retire After 25 Years of Transformative Leadership

Joliet Junior College Meeting | November 12, 2025 Article Summary:Kristin Mulvey, the longtime Executive Director of Institutional Advancement and the JJC Foundation, was honored by the Board of Trustees as...
nl-food-pantry-horizontal___22114454354

New Lenox Township Hires Full-Time Maintenance Position Amid Surging Food Pantry Demand

New Lenox Township Meeting | October 2025 Article Summary: The New Lenox Township Board of Trustees unanimously approved the creation of a new full-time maintenance position to help manage the...
under armor logo

Lincoln-Way 210 Switches to Under Armour for Athletic Apparel

Lincoln-Way Community High School District 210 Meeting | November 20, 2025 Article Summary: The Lincoln-Way District 210 Board of Education has approved a new 3.5-year agreement with BSN and Under Armour...
Screenshot 2025-11-27 at 7.18.21 PM

Baldermann Defends Investment Strategy, Blasts Social Media Critics

Village of New Lenox Meeting | Nov. 24, 2025 Article Summary: New Lenox Mayor Tim Baldermann issued a fiery defense of the Village Board's decision to suspend the property tax...
Will County Logo Graphic

Crete “Group Care” Home Approved for Senior Living

Will County Board Meeting | November 2025 Article Summary: The Will County Board unanimously approved a special use permit for a senior group care home in Crete Township. The facility...
Meeting Briefs

Meeting Summary and Briefs: New Lenox School District 122 for October 21, 2025

New Lenox School District 122 Meeting | October 21, 2025 The New Lenox School District 122 Board of Education held a public hearing and subsequently approved the issuance of up...
About Us Website Header - 1

New Lenox Library Reviews Strategic Plan Draft Following Robust Community Feedback

New Lenox Public Library District Meeting | October 20, 2025 Article Summary: The New Lenox Public Library District Board of Trustees is reviewing a draft of its 2026-2028 Strategic Plan,...
Meeting Briefs

Meeting Summary and Briefs: New Lenox Community Park District for October 15, 2025

New Lenox Community Park District Meeting | October 15, 2025 The New Lenox Community Park District Board of Commissioners on Wednesday, October 15, 2025, discussed plans for a future indoor...
will county board graphic

New Bar Approved in Frankfort Despite Board Opposition

Will County Board Meeting | November 2025 Article Summary: The Will County Board narrowly approved a special use permit for a new bar in Frankfort Township, paving the way for...
joliet junior college logo

JJC Board Approves Grundy County Land Purchase Amid Heated Debate

Joliet Junior College Meeting | November 12, 2025 Article Summary:The Joliet Junior College Board of Trustees voted 6-2 to approve a real estate contract for a new campus in Grundy...
Screenshot 2025-11-21 at 10.20.03 AM

Support Staff Urge Lincoln-Way 210 Board for ‘Fair Contract’ During Public Comment

Lincoln-Way Community High School District 210 Meeting | November 20, 2025 Article Summary: Three members of Lincoln-Way District 210's support staff addressed the Board of Education, voicing frustrations over working without...
New-Lenox-School-122.6

New Lenox SD 122 Approves Community Solar Agreement, Anticipates $62K in Annual Savings

New Lenox School District 122 Meeting | October 21, 2025 Article Summary: New Lenox School District 122 will join a community solar program after the Board of Education approved a...