Minnesota, Illinois AGs challenge federal orders to keep coal plants running

Minnesota, Illinois AGs challenge federal orders to keep coal plants running

Spread the love

Minnesota Attorney General Keith Ellison is challenging the Trump administration over orders requiring coal-fired power plants in Indiana to remain open past their planned retirement dates.

Ellison, joined by Illinois Attorney General Kwame Raoul, filed the petitions for judicial review against U.S. Energy Secretary Chris Wright in the U.S. Court of Appeals for the District of Columbia Circuit.

Ellison argued the U.S. Department of Energy “unlawfully” invoked emergency powers to keep the plants operating, a move he said will increase costs for ratepayers throughout the Midwest, including those in Minnesota.

The states are challenging federal orders affecting the R.M. Schahfer power plant in Wheatfield, Indiana, and the F.B. Culley generating station in Newburgh, Indiana. Both facilities had been slated for retirement.

“It makes no sense for the federal government to force old, out-of-date, expensive, and polluting coal plants to continue operating far past when they were supposed to shut down,” Ellison said. “Continuing to operate these plants will ultimately raise energy costs for ratepayers.”

The orders were issued in December under Section 202(c) of the Federal Power Act, which allows federal intervention in the electric grid during emergencies. Additional extensions were filed by the federal government on March 23.

Ellison and Raoul argue no such emergency exists and say the administration exceeded its legal authority.

“Donald Trump doesn’t even have the legal authority to order these plans to continue operating,” Ellison said. “I’m suing to stop this unlawful action and prevent the Trump administration from raising Minnesotans’ energy costs and increasing pollution that leads to climate change.”

The Trump administration has defended similar actions as necessary to maintain grid reliability as electricity demand rises and more traditional power plants retire.

When President Donald Trump took office he issued executive orders declaring an unlawful “national energy emergency” and “terminating the Green New Deal.”

A July report from the U.S. Department of Energy last year warned the country could face a significantly increased risk of power outages by 2030 if coal and natural gas plants continue to shut down as planned.

The report, ordered by Trump as part of an April 2025 executive order, found closures could increase outage risks by as much as 100 times without intervention and urged keeping existing generation capacity online.

“Our nation possesses abundant energy resources and capabilities such as oil and gas, coal, and nuclear,” the report said.

It applauded deregulation and permitting reform by the Trump administration, but argued that won’t be enough if plants continue to close.

“However, even with these foundational strengths, the accelerated retirement of existing generation capacity . . . undermine this energy outlook,” it said. “Absent decisive intervention, the nation’s power grid will be unable to meet projected demand for manufacturing, re-industrialization, and data centers driving artificial intelligence (AI) innovation.”

That report faces a lawsuit for a multi-state coalition, as previously reported by The Center Square.

Wright said emergency orders are intended to ensure sufficient generation capacity throughout the Midwest.

“The last administration’s energy subtraction policies had the United States on track to likely experience significantly more blackouts in the coming years—thankfully, President Trump won’t let that happen,” Wright said of the March extension. “The Trump Administration will continue taking action to keep America’s coal plants running to ensure we don’t lose critical generation sources.”

A similar dispute is playing out in Michigan. Just hours before its planned closure last May, the J.H. Campbell coal-fired plant in West Olive was ordered to remain open under a federal emergency directive.

Michigan Attorney General Dana Nessel challenged the move in July, calling it a “manufactured emergency” and arguing the federal government was overstepping its authority to keep open coal plants. She also warned the plant’s extension would significantly raise costs for consumers, with some reports stating an additional $134 million for just six months of operation.

Wright has filed multiple extensions for that plant since last year and it still remains operational. Nessel has challenged each of those extensions to no avail.

Similar concerns are central to Minnesota’s lawsuit.

Ellison argued the Indiana plants require significant maintenance, repairs and fuel to continue operating, particularly after running down resources ahead of their planned retirements. Those costs would ultimately be passed on to customers across the Midcontinent Independent System Operator region.

“This comes at a significant loss that will be passed on to Minnesota rate payers,” Ellison’s office said. “There is no evidence the coal plants could reasonably address any emergency need, because they are inefficient, in disrepair, and operate on a long timetable.”

Leave a Comment





Latest News Stories

New Lenox Village Board Graphic.1

Meeting Summary and Briefs: New Lenox Village Board for June 8, 2026

New Lenox Village Board Meeting | June 8, 2026 The New Lenox Village Board moved through a lengthy agenda on Monday, June 8, 2026, with Trustees Lindsay Scalise and Amy...
Will County Board Graphic.04

Meeting Summary and Briefs: Will County Board Executive Committee for June 11, 2026

Will County Board Executive Committee Meeting | June 11, 2026 The Will County Board Executive Committee met Thursday, June 11, 2026, in Joliet, advancing a slate of items to the...
Will County Board Graphic.02

Will County Mental Health Board Touts Crisis Program in Quarterly Report

Will County Board Executive Committee Meeting | June 11, 2026 Article Summary: The Will County Community Mental Health Board's quarterly report to the Executive Committee on Thursday, June 11, 2026,...
Will County Finance Logo

Meeting Summary and Briefs: Will County Board Finance Committee for June 2, 2026

Will County Board Finance Committee Meeting | June 2, 2026 The Will County Board Finance Committee took up a short slate of budget and appropriation items at its regular meeting...
New Lenox Village Board Graphic.1

New Lenox Approves $92,954 Purchase for Railroad Quiet Zone Delineators

New Lenox Village Board Meeting | June 8, 2026 Article Summary: The New Lenox Village Board on June 8 waived formal bidding and approved a purchase of about $92,954 for...
Will County Board Graphic.03

Will County Coroner Reports Nearly 8,000 Death Investigations in 2025

Will County Board Executive Committee Meeting | June 11, 2026 Article Summary: Will County Coroner Laurie Summers presented her 2025 annual report to the Executive Committee on Thursday, June 11,...
Will County Board Graphic.01

Will County Committee Advances Three New Assistant State’s Attorneys

Will County Board Executive Committee Meeting | June 11, 2026 Article Summary: The Will County Board Executive Committee on Thursday, June 11, 2026, recommended increasing the authorized number of assistant...
Will County Finance Logo

Will County Committee Advances $75,000 for U of I Extension

Will County Board Finance Committee Meeting | June 2, 2026 Article Summary: The Will County Board Finance Committee on Tuesday, June 2, 2026, voted to advance a resolution committing $75,000...
New Lenox Village Board Graphic.1

Baldermann Credits Public Pressure for Stalling State Housing ‘Build Plan’

New Lenox Village Board Meeting | June 8, 2026 Article Summary: Mayor Tim Baldermann used his June 8 report to the New Lenox Village Board to detail what he described...
Will County Board Graphic.03

Will County Committee Pulls Single-Member District Referendum

Will County Board Executive Committee Meeting | June 11, 2026 Article Summary: The Will County Board Executive Committee on Thursday, June 11, 2026, removed a proposed referendum on single-member county...
Will County Board Graphic.04

Will County Land Bank Clears Committee With Two Amendments

Will County Board Executive Committee Meeting | June 11, 2026 Article Summary: The Will County Board Executive Committee on Thursday, June 11, 2026, recommended creating a Will County Land Bank...
Will County Finance Logo

Will County Committee Advances $179,000 Coroner Cot Purchase

Will County Board Finance Committee Meeting | June 2, 2026 Article Summary: The Will County Board Finance Committee on Tuesday, June 2, 2026, voted to advance a request authorizing $179,000...
New Lenox Village Board Graphic.1

147-Room Hilton Hotel Approved Near New Lenox Crossroads Sports Complex

New Lenox Village Board Meeting | June 8, 2026 Article Summary: The New Lenox Village Board on June 8 approved a site plan and set surety for a 147-room Hilton...
New Lenox Village Board Graphic.1

New Lenox Advances Cedar Pointe Annexation and Rezoning on First Read

New Lenox Village Board Meeting | June 8, 2026 Article Summary: The New Lenox Village Board held a public hearing and first readings June 8 on ordinances that would annex,...
Will County Board Graphic.01

Will County Board Members Spar Over Wheatland Township Mental Health Grant

Will County Board Executive Committee Meeting | June 11, 2026 Article Summary: A $155,000 mental health grant to Wheatland Township drew sharp questioning at the Will County Board Executive Committee...