Lincoln-Way 210 Awards $1.98 Million Contract for Network Cabling Upgrades

Spread the love

Lincoln-Way Community High School District 210 Meeting | March 19, 2026

Article Summary: The Board of Education approved a $1.98 million contract with CDW/Greatline Solutions to upgrade aging wired infrastructure at the Central and East campuses to support modern technology and faster network speeds.

Cabling Upgrade Key Points:

  • A contract for a total cost of $1,982,901.00 was awarded to CDW/Greatline Solutions.

  • The project replaces 20-to-25-year-old CAT 5e cabling with CAT 6A, supporting up to 10 gigabits per second.

  • The district anticipates receiving $480,000 in reimbursements through the federal E-Rate program.

  • The new cabling comes with a 25-year manufacturer warranty.

The Lincoln-Way Community High School District 210 Board of Education on Thursday, March 19, 2026, unanimously approved a contract for a total cost of $1,982,901.00 with CDW/Greatline Solutions for a district-wide wired infrastructure upgrade.

The district issued a Request for Proposals (RFP) in January 2026 to upgrade components of its wired infrastructure through the federal E-Rate process. According to Director of Technology Cheryl Kay, much of the existing cabling at Lincoln-Way Central and East is 20 to 25 years old. The older CAT 5 and CAT 5e cabling standards do not support the faster speed capabilities of modern switching and wireless equipment recently purchased by the district.

“To put this into perspective for you, CAT 5e cabling supports speeds up to 1 gigabit per second, while CAT 6A cabling can support speeds up to 10 gigabits per second,” Kay explained to the Board. “I’ve used the garden hose versus the fire hose analogy in the past. So essentially, the new cabling allows more data to move through the network at one time.”

The upgraded infrastructure will also establish a foundation for future technology projects, including IP communication systems, digital signage, emergency alerting, and intercom systems that are nearing the end of their usable life.

The district received three proposals. While Netsource Solutions submitted a lower bid of $1,885,001.00, the district rejected it because the company only had 25 total employees. Kay noted that the district had significant concerns about a company of that size being able to complete the massive scope of work on time across multiple buildings. CDW/Greatline, a vendor the district has successfully used for past fiber projects, was selected instead.

The project is included in the district’s 5-year technology plan. Because a significant portion of the work qualifies for E-Rate reimbursements, the district anticipates receiving roughly $480,000 back after the project is completed. The installation work will be completed between April 1, 2026, and September 30, 2027, working around the district’s upcoming HVAC construction schedule.

Leave a Comment





Latest News Stories

Will-County-Land-Use-July3.2

Residents Allege Health Crises, Violations from Peotone Grain Facility

Two residents of unincorporated Peotone delivered emotional testimony to the Will County Land Use and Development Committee Thursday, alleging that a neighboring grain facility is causing severe health problems and...
Will-County-Public-Health-Safety-Committee-Meeting-July-3-2025

Health Department May Seek Property Tax Increase to Maintain Critical Services

The Will County Health Department is grappling with significant budget shortfalls as multiple federal grants have been terminated or reduced, potentially forcing the agency to seek additional property tax revenue...
Will-County-Land-Use-July-3.1

Crete Township Solar Project Approved Despite Township Objections

A 21-acre commercial solar project in Crete Township received a favorable recommendation from the Will County Land Use and Development Committee on Thursday, despite an official objection from the township....
Will-County-Public-Health-Safety-Committee-Meeting-July-3-2025

Health Department Opens Second Breast Milk Depot in Bolingbrook

The Will County Health Department has opened its second breast milk depot in partnership with Mother's Milk Bank of the Western Great Lakes, expanding access to donated breast milk for...
Will-County-Land-Use-July3.2

Lockport Township Solar Farm Gains Committee Approval

The Will County Land Use and Development Committee on Thursday approved a special use permit for a 25-acre commercial solar energy facility in Lockport Township. The project, proposed by Daniel...
Will-County-Public-Health-Safety-Committee-Meeting-July-3-2025

Health Department Plans Back-to-School Fair July 12

The Will County Health Department will host a Back-to-School Health Fair Saturday, July 12, from 10 a.m. to 2 p.m. at the Community Health Center, 1106 Neal Ave., Joliet. The...
Meeting-Briefs

Meeting Briefs: Will County Land Use & Development Committee for July 3, 2025

Green Garden Township Rezoning for Future Subdivision ApprovedThe committee recommended approval of a map amendment for an 81-acre property on South 88th Avenue in Green Garden Township. The applicant, represented...
Meeting-Briefs

Will County Public Health & Safety Committee July 3 Meeting Briefs

Grain Dust Complaint Prompts Investigation: Will County resident Tracy Henning of unincorporated Peotone addressed the committee about health problems she attributes to grain dust from a neighboring facility. Henning, who...
Will-County-Legislative-Committee-Meeting-July-1-2025

Will County Seeks Asian Carp Provision in Federal Legislative Agenda

Will County Board member Julie Berkowicz is pushing to add specific language addressing Asian carp invasion to the county's federal legislative agenda, citing the ongoing threat to local waterways as...
Will-County-Legislative-Committee-Meeting-July-1-2025

State Legislative Session Update: Transit, Energy Bills Stall Despite Democratic Control

Illinois lawmakers failed to advance major transit funding and comprehensive energy legislation during the recently concluded spring session, leaving key issues unresolved despite Democratic supermajorities in both chambers, according to...
Will-County-Capital-Improvements-IT-Committee-Meeting-July-1-2025

Will County’s Major Capital Projects Hit Key Milestones, VAC Buildout on “Aggressive Schedule”

Will County is making significant headway on several major capital improvement projects, with the new Veterans Assistance Commission (VAC) & Support Center in Joliet on an “aggressive schedule” for a...
Will-County-Public-Works-Transportation-Committee-Meeting-July-1-2025

County Board Approves 2026-2031 Transportation Plan Despite Project Opposition

Will County board members approved a contested five-year transportation improvement plan Tuesday after heated debate over a controversial Homer Glen road project that has drawn sustained community opposition. The Will...
Will-County-Planning-and-Zoning-Commission-Meeting-July-1-2025

Contentious I-3 Rezoning for DuPage Township Storage Yard Narrowly Advances

A proposal to rezone a 20-acre parcel in DuPage Township from agricultural to the county's most intensive industrial classification narrowly earned a recommendation for approval from the Will County Planning...
Meeting-Briefs

Will County Legislative Committee July 1 Meeting Briefs

Federal Budget Impact: Will County could face significant funding challenges if federal budget reconciliation measures reduce Medicaid and SNAP benefits. The county health department and social services rely heavily on...
Will-County-Finance-Committee-Meeting-July-1-2025

County Moves Forward with $200.8 Million Bond Refinancing Plan

Will County Finance Committee members on July 1 approved moving forward with a comprehensive bond refinancing ordinance that could save taxpayers more than $716,000 over the life of the bonds...