Lincoln-Way 210 Awards $1.98 Million Contract for Network Cabling Upgrades

Spread the love

Lincoln-Way Community High School District 210 Meeting | March 19, 2026

Article Summary: The Board of Education approved a $1.98 million contract with CDW/Greatline Solutions to upgrade aging wired infrastructure at the Central and East campuses to support modern technology and faster network speeds.

Cabling Upgrade Key Points:

  • A contract for a total cost of $1,982,901.00 was awarded to CDW/Greatline Solutions.

  • The project replaces 20-to-25-year-old CAT 5e cabling with CAT 6A, supporting up to 10 gigabits per second.

  • The district anticipates receiving $480,000 in reimbursements through the federal E-Rate program.

  • The new cabling comes with a 25-year manufacturer warranty.

The Lincoln-Way Community High School District 210 Board of Education on Thursday, March 19, 2026, unanimously approved a contract for a total cost of $1,982,901.00 with CDW/Greatline Solutions for a district-wide wired infrastructure upgrade.

The district issued a Request for Proposals (RFP) in January 2026 to upgrade components of its wired infrastructure through the federal E-Rate process. According to Director of Technology Cheryl Kay, much of the existing cabling at Lincoln-Way Central and East is 20 to 25 years old. The older CAT 5 and CAT 5e cabling standards do not support the faster speed capabilities of modern switching and wireless equipment recently purchased by the district.

“To put this into perspective for you, CAT 5e cabling supports speeds up to 1 gigabit per second, while CAT 6A cabling can support speeds up to 10 gigabits per second,” Kay explained to the Board. “I’ve used the garden hose versus the fire hose analogy in the past. So essentially, the new cabling allows more data to move through the network at one time.”

The upgraded infrastructure will also establish a foundation for future technology projects, including IP communication systems, digital signage, emergency alerting, and intercom systems that are nearing the end of their usable life.

The district received three proposals. While Netsource Solutions submitted a lower bid of $1,885,001.00, the district rejected it because the company only had 25 total employees. Kay noted that the district had significant concerns about a company of that size being able to complete the massive scope of work on time across multiple buildings. CDW/Greatline, a vendor the district has successfully used for past fiber projects, was selected instead.

The project is included in the district’s 5-year technology plan. Because a significant portion of the work qualifies for E-Rate reimbursements, the district anticipates receiving roughly $480,000 back after the project is completed. The installation work will be completed between April 1, 2026, and September 30, 2027, working around the district’s upcoming HVAC construction schedule.

Leave a Comment





Latest News Stories

Meeting-Briefs

Meeting Summary and Briefs: New Lenox School District 122 Board for Nov. 2025

New Lenox School District 122 Board Meeting | Nov. 2025 The New Lenox School District 122 Board of Education met on Tuesday, November 18, 2025, at the Haven Administration Center....
Will County Board Graphic.02

County Board Approves Women’s Residential Treatment Center in Joliet

Will County Board Meeting | December 18, 2025 Article Summary: The Will County Board unanimously approved zoning changes to allow the Existential Counselor Society to open a women’s residential treatment...
White business owners are biggest share of Illinois' diversity-preferred contract group

White business owners are biggest share of Illinois’ diversity-preferred contract group

By Jared Strong | The Center SquareThe Center Square (The Center Square) – Illinois' initiative to boost the amount of state contract money it awards to businesses owned by racial...
Meeting-Briefs

Meeting Summary and Briefs: New Lenox Village Board for December 15, 2025

New Lenox Village Board Meeting | December 15, 2025 The New Lenox Village Board on Monday, Dec. 15, 2025, met for a regular session focused on infrastructure upgrades, public safety...
new-lenox-township.2

Township Abates $285,000 in Taxes for Senior Housing Bonds

New Lenox Township Board Meeting | Nov. 13, 2025 Article Summary: The Board of Trustees passed a resolution to abate taxes related to the 2002 Senior Housing Bond payment. The...
Meeting Briefs

Meeting Summary and Briefs: Will County Board for December 18, 2025

Will County Board Meeting | December 18, 2025 The Will County Board held its regular meeting on Thursday, December 18, 2025, focusing heavily on land use, transportation infrastructure, and public...
2025 illegal entries in Texas: Nearly half the gotaways reported in previous years

2025 illegal entries in Texas: Nearly half the gotaways reported in previous years

By Bethany BlankleyThe Center Square In President Donald Trump’s first year in office, illegal border crossers in one year in Texas totaled nearly half of gotaways reported in previous years...
Nashville speaker maker plans to move overseas to avoid tariffs

Nashville speaker maker plans to move overseas to avoid tariffs

By Brett RowlandThe Center Square The owner of a storied Nashville speaker company says he'll pay lower taxes by moving overseas, rather than trying to build in the U.S. It's...
Supreme Court could redefine 14th Amendment application

Supreme Court could redefine 14th Amendment application

By Andrew RiceThe Center Square The U.S. Supreme Court will decide a case in 2026 challenging President Donald Trump’s authority to end birthright citizenship. Trump v. Barbara challenges Trump’s executive...
Missouri year in review: capital gains eliminated, Medicaid increased

Missouri year in review: capital gains eliminated, Medicaid increased

By Andrew RiceThe Center Square In 2025, Missouri lawmakers passed legislation to eliminate its capital gains tax, phase out the state income tax and expand Medicaid legislation. The Club for...
2025 in review: Historic border security actions taken by Trump

2025 in review: Historic border security actions taken by Trump

By Bethany BlankleyThe Center Square On the first day of his second term in office, President Donald Trump issued multiple executive orders, followed by multiple policy changes, that in one...
Free speech under fire nearly 300 times in 2025 on campus

Free speech under fire nearly 300 times in 2025 on campus

By Tate MillerThe Center Square Two hundred seventy-four incidents involving interference to free speech have taken place so far on college campuses in 2025, according to FIRE data, an increase...
IL rep: As if Bears 'had a plan to rob the bank' before considering Indiana

IL rep: As if Bears ‘had a plan to rob the bank’ before considering Indiana

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – The Illinois state rep whose district includes Soldier Field says the Chicago Bears are bluffing by suggesting...
New-Lenox-School-122.5

Ten New Lenox Schools Rated “Commendable” as State Changes Testing Metrics

New Lenox School District 122 Board Meeting | Nov. 2025 Article Summary:Assistant Superintendent Dr. Peggy Cucci presented the annual student achievement report, noting that all ten eligible district schools received...
Screenshot 2025-12-20 at 12.27.17 PM

Lincoln-Way High Schools Maintain Top State Rankings; EL Progress Jumps

Lincoln-Way Community High School District 210 Meeting | December 18, 2025 Article Summary: The 2025 Illinois Report Card data reveals that Lincoln-Way Central and East have maintained "Exemplary" status, while...