Screenshot 2026-05-10 at 4.13.40 PM

New Lenox Seeks $2.5 Million State Loan for Water Main Replacements, Sets $1.2 Million in Sureties for Spencer Meadows

Spread the love

New Lenox Village Board of Trustees Meeting | March 23, 2026

Article Summary: The New Lenox Village Board advanced several major infrastructure initiatives, waiving a second reading to apply for a $2.5 million public water supply loan while setting over $1.2 million in financial sureties to guarantee utility and grading work at the new Spencer Meadows subdivision.

Infrastructure and Loan Key Points:

  • IEPA Loan Application: Ordinance #3249 authorizes the Village to borrow $2,500,000 from the Illinois EPA Public Water Supply Loan Program.

  • Targeted Replacements: The loan funds will be used to replace aging water mains on Gall Lane, Hawthorne Lane, and Fir Street.

  • Spencer Meadows Sureties: The Board set a $937,287.50 surety for off-site water mains and a $269,201.69 surety for mass grading at the Spencer Meadows development.

  • Utility Easements: A related agreement secures a 35×36 foot storm sewer easement and temporary construction access on the Mulch-It property along Laraway Road.

The New Lenox Village Board on Monday, March 23, 2026, took significant legislative steps to secure funding for critical water infrastructure upgrades and lock in financial guarantees for ongoing residential development.

To address aging infrastructure in established neighborhoods, the Board unanimously approved Ordinance #3249, authorizing the Village to borrow $2,500,000 from the Illinois Environmental Protection Agency (IEPA) Public Water Supply Loan Program.

Mayor Tim Baldermann explained that the $2.5 million will be utilized to improve and replace the water mains on Gall Lane, Hawthorne Lane, and Fir Street. He noted that the ordinance was specifically structured by the IEPA and modified to match the Village’s particular funding request. To expedite the application process, the Board voted to waive the ordinance’s standard second reading.

Simultaneously, the Village secured the infrastructure guarantees required for the new Spencer Meadows subdivision, located at the intersection of Laraway and Spencer Roads.

The Board approved two separate financial sureties to ensure the developer completes the required public improvements. The first surety guarantees the off-site water main construction and was set at $937,287.50. The second guarantees the mass grading of the site and was set at $269,201.69. Both sureties carry an expiration date of March 23, 2028.

To physically accommodate the Spencer Meadows utility extensions, the Board also passed Resolution #26-25, executing a Grant of Easement Agreement with property owners Shawn and Donna Matthuis. Community Development Director Robin Ellis explained the easements run through the adjacent Mulch-It property and will eventually fall within the Will County right-of-way when the county expands Laraway Road.

The agreement grants the Village a 35×36 foot easement for a storm sewer connection, a 10-foot wide permanent easement, and a 25-foot wide temporary construction easement to extend the water main along Laraway. The legal document stipulates that no permanent structures, signs, or buildings can be placed within the easement boundaries.

All measures passed on unanimous 7-0 roll call votes.

Leave a Comment





Latest News Stories

Arizona recommends measles vaccine during outbreak

Arizona recommends measles vaccine during outbreak

By Chris WoodwardThe Center Square Arizona is recommending vaccinations to combat the state's worst measles outbreak since the 1990s. The latest update this week showed the state has 111 cases...
Govt. shutdown leads to over 800 flights cancelled, number growing

Govt. shutdown leads to over 800 flights cancelled, number growing

By Thérèse BoudreauxThe Center Square As the government shutdown drags into its 38th day and forced flight reductions begin taking effect, the number of daily flight cancellations Americans are experiencing...
Illinois approves $1.5B transit package, funding for long-delayed projects

Illinois approves $1.5B transit package, funding for long-delayed projects

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Illinois lawmakers approved a $1.5 billion transit package, including long-delayed Moline-to-Chicago rail, hailed by Democrats as...
Supreme Court allows Trump to withhold partial SNAP payment

Supreme Court allows Trump to withhold partial SNAP payment

By Brett RowlandThe Center Square The Supreme Court said Friday that the Trump administration could withhold a partial payment for the federal food benefits program amid the longest-ever government shutdown....
Illinois quick hits: State EPA looks to fund EV charging stations; Tax Foundation says mayor's proposal would hinder employment;

Illinois quick hits: State EPA looks to fund EV charging stations; Tax Foundation says mayor’s proposal would hinder employment;

By Jim Talamonti | The Center SquareThe Center Square State EPA looks to fund EV charging stations The Illinois Environmental Protection Agency (EPA) has announced an Electric Vehicle (EV) Charging...
Congressional Perks: Committees, caucuses cost $50 million since 2019

Congressional Perks: Committees, caucuses cost $50 million since 2019

By Arthur KaneThe Center Square Since 2019, partisan and special interest caucuses and coalitions in the U.S. House spent at least $50 million for staff, food, travel and other expenses,...
Screenshot 2025-11-06 at 4.17.15 PM

Federal Lobbyists Brief Will County on Government Shutdown, Warn of SNAP and TSA Disruptions

Meeting Summary and Briefs: Will County Legislative Committee for November 4, 2025 Article Summary: Will County’s federal lobbyists reported that the ongoing government shutdown, now the longest in U.S. history, is...
New-Lenox-Village-Board.2

New Lenox Residents Plead for Help in Escalating Neighborhood Dispute

New Lenox Village Board Meeting | October 27, 2025 Article Summary: A New Lenox couple made an emotional plea to the Village Board, detailing a year-long dispute with a neighbor that...
Will County Logo Graphic

Commission Approves Mokena-Area Garage Variance Over Village’s Objection

Will County Planning and Zoning Commission Meeting | November 4, 2025 Article Summary: The Will County Planning and Zoning Commission approved a variance for a new garage in unincorporated Frankfort Township...
Screenshot 2025-11-05 at 4.02.49 PM

Will County Committee Advances Gougar Road Bridge Project with Over $540,000 in Agreements

Will County Public Works & Transportation Committee Meeting | November 2025 Article Summary: The Will County Board approved two key agreements for the Gougar Road bridge project in New Lenox,...
Joliet-Junior-college.-Graphic-Logo.4

JJC Receives Surprise $1.9 Million from IRS Employee Retention Credit

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryJoliet Junior College has received an unexpected $1.9 million windfall from the federal Employee Retention Credit (ERC), a...
Joliet-Junior-college.-Graphic-Logo.2

JJC Advances ERP Modernization with New Vendor and Two-Year Budget

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryJoliet Junior College is entering the next phase of its Enterprise Resource Planning (ERP) system overhaul, with the...
new-lenox-fire-district-stations.3

Station 62 Remodel Advances as Fire District Seeks to Waive Permit Fees

New Lenox Fire Protection District Meeting | September 2025 Article Summary: The planned remodel of New Lenox Fire Station 62 is moving into its next phase, with officials having completed...
Screenshot 2025-11-06 at 4.17.02 PM

Will County Committee Shapes 2026 Legislative Agendas on Housing, Energy, and Health

Meeting Summary and Briefs: Will County Legislative Committee for November 4, 2025 Article Summary: The Will County Legislative Committee advanced key priorities for its 2026 state and federal legislative agendas, focusing...
New-Lenox-School-122.3

New Lenox School District 122 Considers Community Solar Program Promising $55K in Annual Savings

New Lenox School District 122 Meeting | September 2025 Article Summary: New Lenox School District 122 is exploring a 20-year subscription to a community solar program that could save the...