Capital Imp Committee: Health Dept Elevator Repair Costs Significantly Lower Than Estimates

Spread the love

Will County Capital Improvements & IT Committee Meeting | Jan. 6, 2026

Article Summary: A malfunctioning elevator at the Will County Health Department has been repaired for approximately $18,000 to $20,000, avoiding a potential replacement cost of over $1 million. Facilities staff confirmed the unit is suitable for the building’s needs.

Facilities Key Points:

  • Repair Cost: The final repair bill is estimated between $18,000 and $20,000.

  • Cost Avoidance: Initial fears suggested a full replacement could have exceeded $1 million.

  • In-House Projects: Facilities staff saved money by framing and hanging judge photos at the courthouse internally.

  • Efficiency: The department completed over 750 work orders in the last month with a 98% completion rate.

JOLIET — A potentially budget-breaking elevator issue at the Will County Health Department was resolved for a fraction of the feared cost, Facilities Director William Fern reported to the Capital Improvements and IT Committee on Tuesday, Jan. 6, 2026.

During a facilities update, Chair Mica Freeman (D-Plainfield) requested the final cost for the elevator repair, noting that previous discussions had raised concerns about the unit’s suitability and the potential need for a total replacement.

“I think it was about $18,000 to $20,000,” Fern said.

Freeman noted this was significantly under the $30,000 to $40,000 estimates discussed previously, and far below the cost of a full replacement.

“Or the over million to replace, right?” Fern added. “So I think they got to the root cause of the issue from the initial install and were able to repair it.”

Fern confirmed that the existing elevator was deemed suitable for the space, eliminating the need for major construction.

In other facilities news, Fern highlighted a project at the Will County Courthouse where maintenance staff framed and hung photos of current and past judges on the third floor.

“Originally, we got a quote. It was pretty expensive. It was over like $18,000 for a contractor to do it,” Fern said.

By utilizing the Sheriff’s carpentry staff and county facilities personnel, the project was completed in-house for a “fraction of the cost.” However, Fern noted that a few photos were hung out of order and will be corrected.

Fern also reported that the department continues to operate efficiently, saving the county over $118,000 in evaporation credits on cooling towers at the courthouse to date.

⚠️ Special Weather Statement issued June 4 at 4:25AM CDT by NWS Chicago IL
Today Jun 3
Mostly Sunny
87° 66°

Mostly Sunny

💨 5 to 15 mph 💧 0%

Leave a Comment





Latest News Stories

Will-County-Public-Works-Transportation-Committee-Meeting-July-1-2025

Access Will County Dial-a-Ride Program Sees Record Growth, Eyes Expansion

Will County's dial-a-ride transportation service for seniors and disabled residents reached record ridership levels while officials plan major expansion to cover all county townships. The Access Will County program served...
Will-County-Capital-Improvements-IT-Committee-Meeting-July-1-2025

Will County to Launch New Public Meeting Agenda System in August Amidst Data Conversion Concerns

Will County is set to launch its new public meeting agenda and records software, Granicus “OneMeeting,” in August, but the transition will see over a decade of historical records converted...
Will-County-Planning-and-Zoning-Commission-Meeting-July-1-2025

Green Garden Township Poised for First Major Subdivision in Years After Rezoning

The Will County Planning and Zoning Commission has recommended a rezoning that could pave the way for the first major residential subdivision in Green Garden Township in nearly two decades....
Will-County-Finance-Committee-Meeting-July-1-2025

County RNG Facility Shows Strong Performance Despite Solar Challenges

Will County's Renewable Natural Gas facility is exceeding production targets while officials explore options to reduce substantial electricity costs that currently impact profitability. Project manager Greg Komperda told Finance Committee...
Meeting-Briefs

PZC Briefs: Solar Farm in Crete, Post-Fire Permit for Troy Business, and More

The Will County Planning and Zoning Commission handled several other cases during its July 1 meeting, including a new solar farm, a temporary permit for a fire-damaged business, and routine...
Meeting-Briefs

In Brief: Capital & IT News

Here are other highlights from the Will County Capital Improvements & IT Committee meeting on Tuesday. Successful Fire Drill at County BuildingThe Will County Office Building held its first full...
Meeting-Briefs

Will County Finance Committee July 1 Meeting Briefs

Bond Refinancing Advances: Finance Committee approved an ordinance authorizing up to $200.8 million in bond refinancing that could save taxpayers more than $716,000. The measure moves to the full County...
Meeting-Briefs

Will County Public Works Committee Juliy 1 Meeting Briefs

ROAD CONTRACTS APPROVED Austin Tyler Construction Contract: The committee approved a $691,544 contract with Austin Tyler Construction for resurfacing River Road from East Frontage Road to Prairie Creek Bridge and...
About Us Website Header - 1

New Lenox Library Board Seats New Trustees, Reorganizes After Election

NEW LENOX – The New Lenox Public Library District Board of Trustees officially seated its newly elected members and reorganized its leadership and committee assignments for the new term at...
New-Lenox-School-122.3

New Lenox D122 Board Approves Nearly $300,000 for Summer Maintenance Projects

The New Lenox School District 122 Board of Education has approved a comprehensive list of 56 maintenance and capital improvement projects to be completed over the summer, allocating a total...
new-lenox-fire-district-stations.3

New Lenox Fire District to Launch Comfort Dog Program for First Responders, Community

NEW LENOX – The New Lenox Fire Protection District is adding a four-legged member to its team after the Board of Trustees unanimously approved the creation of a new comfort...
new-lenox-library.2-1

Library’s ‘Studio’ Draws Record Crowds with New Tech and Creative Programs

NEW LENOX – The New Lenox Public Library’s creative hub, The Studio, is experiencing a surge in popularity, shattering attendance records and successfully launching new technology-driven programs, according to a...
New-Lenox-School-122.5

D122 to Spend $24,950 on Professional Enrollment Forecast

New Lenox School District 122 will hire an outside firm to conduct a comprehensive, 10-year enrollment forecast at an estimated cost of $24,950. The Board of Education approved an agreement...
JJC-Graphic-Logo

JJC Trustees Approve Contentious FY26 Budget After Heated Debate, Failed Postponement

The Joliet Junior College Board of Trustees on Wednesday approved a $322.3 million budget for fiscal year 2026, but not before a tense debate that saw a motion to postpone...
Screenshot-2025-07-06-at-9.50.39-AM

Lincoln Way District 210 Approves $2.1 Million Budget Amendment, Maintains Strong Financial Position

Lincoln Way Community High School District 210 board members unanimously approved an amended fiscal year 2025 budget Thursday night that increases the district's operating surplus to $2.1 million while maintaining...