New Lenox Fire District Approves $2.5 Million Station 2 Budget and Construction Bids
New Lenox Fire Protection District Meeting | Dec. 15, 2025
Article Summary: The New Lenox Fire Protection District Board of Trustees authorized a budget of over $2.5 million for Station 2, which includes recent adjustments for door replacements. Trustees also awarded a specific construction bid to United Door & Dock to facilitate improvements at Station 2.
New Lenox Fire Protection District Key Points:
-
Station 2 Budget: The Board approved a total budget of $2,531,319.84, which reflects an increase to accommodate door additions.
-
Construction Bid Award: A bid was awarded to United Door & Dock for $36,117.90 for door replacements at Station 2.
-
Vote Outcome: Both financial measures passed with a unanimous vote of 5-0.
The New Lenox Fire Protection District Board of Trustees on Monday, December 15, 2025, moved forward with significant infrastructure investments, approving a multi-million dollar budget for Station 2 and awarding construction contracts for facility improvements.
During the meeting, the Board voted unanimously to approve the Station 2 budget, which now totals $2,531,319.84. According to the meeting minutes, the budget figure was increased specifically to account for the addition of doors to the project.
In related construction business, the Trustees discussed bids presented by Northern Builders regarding improvements at Station 2. The original bid process only yielded results for two rear doors, necessitating a re-bid for all doors. Following the recommendation of Northern Builders, the Board voted to award the contract for the Station 2 door replacement to United Door & Dock for $36,117.90.
Both motions were supported by Trustees Sauter, Scanlan, Fischer, Popp, and Levey.
Latest News Stories
Board Meeting Shorts
Student Council Presidents Highlight Senior Year Accomplishments
Will County Board Meeting Briefs Package
Frankfort Park District Reorganizes Board, Explores Options for Tax-Impacting Projects
Aging Sara Park Building Poses Challenge for Park District
Meeting Briefs: Frankfort Park District Board for May 13, 2025
Lincoln-Way Board Approves Up to $31.3 Million Bond Sale for Safety, Security Upgrades
Frankfort Square Park District Approves Budget Amid County Tax Adjustment, Funds Major Projects
Lincoln-Way School Board Certifies Election, Re-elects Janik as President
New Electricity Contract to Save Lincoln-Way Over $500,000 Next Year
Four New Commissioners to Join Frankfort Square Park District Board in May
Meeting Briefs: Frankfort Square Park District for April 17, 2025