Will County Landfill Committee Meeting | Jan. 13, 2026

Article Summary: The Landfill Committee voted to move forward with engineering estimates for a fourth compressor at the Prairie View Renewable Natural Gas (RNG) facility. The $1.8 million investment aims to reduce downtime and increase revenue, despite concerns about funding sources and timing.

RNG Plant Key Points:

  • Downtime Costs: Data shows that feed compressor failures account for nearly 36% of plant downtime, costing the county an estimated $600,000 annually in lost revenue.

  • Proposed Solution: Installing a fourth compressor would ensure three units are always operational, maximizing gas production and revenue. The estimated cost is $1.8 million with a 3-5 year return on investment.

  • Budget Concerns: The purchase was not included in the current fiscal year budget. Officials discussed using remaining funds from the previous year or splitting the cost across two budget cycles due to a 46-week lead time for the equipment.

Will County officials are taking steps to boost efficiency and revenue at the Prairie View Renewable Natural Gas (RNG) plant by pursuing the addition of a fourth feed compressor.

At the Landfill Committee meeting on Tuesday, January 13, 2026, Dave Hartke, Director of the Resource Recovery & Energy Division, presented data highlighting the financial impact of equipment failures. The facility’s three existing compressors are the primary cause of outages, leading to significant revenue losses.

“If we have three feed compressors operating at all times… we’re going to be producing closer to 27 to 2900 mm BTUs,” Hartke explained, noting this would allow the plant to hit higher revenue tiers faster each month.

The proposed fourth unit, estimated at $1.8 million fully installed, would provide redundancy. However, the plan faced scrutiny regarding its financing. Board Member Sherry Newquist questioned the timing, noting, “This kind of stuff is so much easier to deal with during the budget process.”

Hartke admitted the request was not in the original budget due to a prior focus on austerity. “I wasn’t quite expecting the response… that we should move forward with it,” he said, referencing earlier informal discussions with committee leadership.

Despite the budget hurdle, the committee saw the long-term value. With a 46-week lead time for the equipment, Finance Director Marcy indicated the cost could potentially be split across two fiscal years.

Board Member Jim Richmond emphasized the need for a deeper analysis before cutting a check. “This is a massive business decision… We need to actually look at that plant and make sure that it is spec’d properly from the front door to the back door,” Richmond said.

Ultimately, the committee voted unanimously to authorize staff to proceed with obtaining firm engineering costs and a project plan, which will then be brought back for final financial approval.

Today Jun 12
Mostly Sunny then Slight Chance Showers And Thunderstorms
87° 61°

Mostly Sunny then Slight Chance Showers And Thunderstorms

💨 15 mph 💧 17%

Leave a Comment





Latest News Stories

NL Police Chief

New Lenox Swears In New Police Chief Micah Nuesse, Deputy Chief Brandon Tilton

Article Summary: The New Lenox Police Department has new leadership after the Village Board formally swore in Micah Nuesse as the new Chief of Police and Brandon Tilton as Deputy...
Public education budgets balloon while enrollment, proficiency, standards drop

Public education budgets balloon while enrollment, proficiency, standards drop

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – In return for soaring state spending on education, Illinois taxpayers are getting chronic absenteeism, poor academic proficiency...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Executive Committee for August 14, 2025

The Will County Board Executive Committee received a comprehensive update on the county's expenditure of $134 million in federal ARPA pandemic relief funds, learning that 61% of the total has...
new-lenox-fire-district-stations.3

New Lenox Fire District Approves Contract for $4 Million Station 62 Remodel

New Lenox Fire Protection District Meeting | July 2025 Article Summary: The New Lenox Fire Protection District Board of Trustees has approved a contract with Northern Builders to manage the...
NL VB 8.11.25

New Lenox to Reinstate 1% Grocery Tax, Mayor Blames State Politics

Article Summary: The New Lenox Village Board is moving to locally reimpose the 1% grocery tax that the state is eliminating, a move Mayor Tim Baldermann called necessary to avoid...
new-lenox-township.2

New Lenox Township Receives Clean Audit, Praised for Fiscal Strength

New Lenox Township Board of Trustees Meeting | July 10, 2025 Article Summary: The New Lenox Township Board of Trustees accepted its annual audit for the fiscal year ending March...
Screenshot-2025-08-19-at-7.14.24-PM

Frankfort Approves Over $19 Million in Surplus Fund Transfers for Future Projects

Article Summary: The Frankfort Village Board has approved the transfer of more than $19 million in surplus operating revenues to its capital funds to finance future infrastructure projects, equipment purchases,...
frankfort-village-hall-graphic-logo.7

Frankfort Advances Plans for New Multi-Use Paths to Boost Pedestrian Safety

Article SummaryThe Frankfort Village Board has approved a $77,500 agreement with Robinson Engineering, Ltd. to design two new multi-use paths aimed at improving safety and connectivity in Main Park and...
frankfort village hall graphic logo.1

Frankfort Police Department to Purchase New Portable Radios for $31,000

Article SummaryThe Frankfort Village Board has approved the purchase of 14 new Kenwood portable radios for the police department at a cost not to exceed $31,000. The new equipment will...
Meeting-Briefs

Meeting Summary and Briefs: Village of Frankfort Board for August 18, 2025

The Village of Frankfort Board leveraged a significant budget surplus at its August 18 meeting, approving the transfer of over $19 million into capital funds designated for future infrastructure, equipment,...
Exec Cmte 8.14.25.4

Executive Committee Details Spending of $134 Million in Pandemic Relief Funds

Article Summary: Will County has expended 61% of its $134 million in federal American Rescue Plan Act (ARPA) funds, with significant investments made in infrastructure, health, and economic development. Officials...
Report: Human Rights Campaign pressures transgender procedures on minors

Report: Human Rights Campaign pressures transgender procedures on minors

By Tate MillerThe Center Square (By Tate Miller) – The Human Rights Campaign pressures children’s hospitals into performing transgender procedures on minors, according to a Do No Harm report. Do...
Everyday Economics: Housing market and Fed policy in focus in the week ahead

Everyday Economics: Housing market and Fed policy in focus in the week ahead

By Orphe DivounguyThe Center Square This week brings crucial updates on America's housing market struggles and hints about where interest rates might head next. Housing Data Dump Several major housing...
new-lenox-township.2

New Lenox Township Approves 5% Rent Increase for Guy Sell Senior Housing

New Lenox Township Board of Trustees Meeting | July 10, 2025 Article Summary: The New Lenox Township Board of Trustees has unanimously approved an approximate 5% rent increase for its...
Businesses brace for new tax challenges amid global tariff focus

Businesses brace for new tax challenges amid global tariff focus

By Brett RowlandThe Center Square U.S. businesses and their partners across the globe are looking to make sure they comply with the highest import duties in decades amid a worldwide...