Will County Landfill Committee Meeting | Jan. 13, 2026

Article Summary: Geologic Associates presented a detailed status update on the proposed expansion of the Prairie View Landfill, outlining a dual approach that includes both vertical and horizontal growth. Consultants revealed a complex engineering solution involving a diversion berm and pulley system to manage leachate collection as new cells are constructed over existing infrastructure.

Landfill Expansion Key Points:

  • Expansion Strategy: The county is pursuing both vertical (upward) and horizontal (outward) expansion simultaneously.

  • Engineering Challenge: A significant hurdle involves maintaining leachate collection from the existing landfill while building new cells on top of it. Consultants designed a 94-foot-wide phase delineation berm and a “pipe within a pipe” pulley system to address this.

  • Soil Pile Obstacle: A large soil stockpile remains on site without a current plan for relocation, necessitating the dual-track design approach. Discussions with neighboring Local 150 regarding land acquisition have stalled but may be restarted.

The Will County Board Landfill Committee received a comprehensive update on Tuesday, January 13, 2026, regarding the ongoing design and planning for the Prairie View Landfill expansion.

Marty Fallon of Geologic Associates, the county’s landfill consultant, presented the latest engineering schematics, highlighting the project’s complexity. The expansion strategy involves a “piggyback” design where new landfill cells will be constructed partially on top of the existing waste mound.

“One of the challenges that we’ve had here with this horizontal expansion… we’re going to cover up a portion of the existing landfill,” Fallon explained. This creates a conflict with the existing leachate collection sumps.

To solve this, consultants have designed a massive 94-foot-wide “phase delineation berm” to separate the old and new sections. Within this berm, they plan to install a specialized diversion system featuring a 24-inch pipe housing a smaller 12-inch pipe with a pulley mechanism. This “straw within a straw” design will allow pumps to be retrieved for maintenance even after they are buried under tons of new waste.

Fallon also addressed a critical logistical issue: a large soil stockpile currently occupying space needed for the horizontal expansion. “Currently we don’t have a plan to move that,” Fallon stated, noting that off-site relocation is required.

This issue sparked discussion about reviving negotiations with Local 150, which owns adjacent property. Chuck Helston, outside counsel for the county, confirmed that previous confidential discussions had stalled but expressed willingness to re-engage at the committee’s direction.

Committee Chair David Oxley suggested a creative solution for the union: “Perhaps they could use that as training for their employees and their apprentices to move that dirt to that pile.” Helston agreed to raise the idea again.

The expansion is not expected to disrupt operations at the adjacent Renewable Natural Gas (RNG) plant. “It won’t be any disruption to the [RNG plant] none,” Fallon assured the committee.

Leave a Comment





Latest News Stories

Screenshot 2025-10-17 at 11.31.38 AM

Lincoln-Way Board Honors Students with Perfect ACT Scores, Music Educator of the Year

LW210 Board of Education Meeting | October 16, 2025 Article Summary: Lincoln-Way District 210 celebrated exceptional academic and faculty achievement by formally recognizing nine students who earned a perfect composite...
Screenshot 2025-11-03 at 11.45.01 AM

New Lenox Locks in Three-Year Fireworks Contract to Stabilize Costs

Village of New Lenox Board of Trustees Meeting | October 13, 2025 Article Summary: The New Lenox Village Board has approved a three-year contract with Pyrotecnico Fireworks, Inc. to secure...
Screenshot 2025-10-17 at 11.32.04 AM

Lincoln-Way Support Staff Union Rejects Tentative Contract Agreement

LW210 Board of Education Meeting | October 16, 2025 Article Summary: Members of the Lincoln-Way Community High School District 210 support staff union have voted down a tentative five-year contract...
new-lenox-township.2

New Lenox Township Explores Land Purchase for Cemetery Expansion

New Lenox Township Board of Trustees Meeting | September Article Summary: New Lenox Township is considering the purchase of church-owned property adjacent to the Maplewood cemetery for a potential expansion....
Meeting Briefs

Meeting Summary and Briefs: Will County Board Legislative Committee for October 7, 2025

The Will County Legislative Committee held a long and contentious meeting on Tuesday, October 7, 2025, highlighted by the narrow 4-3 passage of a controversial resolution supporting protections for immigrant...
Screenshot 2025-11-03 at 11.44.21 AM

Developer Changes Landings Business Center Plan from Two Stories to One

Village of New Lenox Board of Trustees Meeting | October 13, 2025 Article Summary: The New Lenox Village Board has approved a modified site plan for The Landings Business Center,...
Screenshot 2025-10-10 at 12.05.55 PM

Will County Board Committee Passes Contentious ‘Live and Work Without Fear’ Resolution on 4-3 Vote

Will County Legislative Committee Meeting October 7, 2025 Article Summary: The Will County Legislative Committee on Tuesday narrowly passed a controversial resolution affirming the county's commitment to ensuring all residents...
Meeting Briefs

Will County Awards $10.4 Million Contract for Bell Road Widening in Homer Glen Area

Will County Public Works & Transportation Committee Meeting October 7, 2025 Article Summary: The Will County Public Works & Transportation Committee on Tuesday confirmed the award of a $10.4 million...
Screenshot 2025-10-10 at 12.12.16 PM

Meeting Summary and Briefs: Will County Public Works & Transportation Committee for October 7, 2025

The Will County Public Works & Transportation Committee on Tuesday, October 7, 2025, approved a major construction contract and reviewed extensive plans for both county and state transportation initiatives. The...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Finance Committee for October 7, 2025

The Will County Finance Committee on Tuesday, October 7, 2025, held a contentious meeting centered on the county’s finances, narrowly approving a preliminary $161.6 million county-wide tax levy on a...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Capital Improvements & IT Committee for October 7, 2025

The Will County Capital Improvements & IT Committee spent the bulk of its meeting on Tuesday, October 7, 2025, discussing the county’s long-term facilities master plan. Faced with an aging...
Screenshot 2025-11-03 at 11.43.03 AM

New Lenox Waives $38,000 in Fees for Fire District’s $4 Million Station Expansion

Village of New Lenox Board of Trustees Meeting | October 13, 2025 Article Summary: The New Lenox Village Board has unanimously voted to waive $38,000 in building permit and plan...
New Lenox Township.3

New Lenox to Consolidate Meals on Wheels Program with Frankfort Township

New Lenox Township Board of Trustees Meeting | September Article Summary: The New Lenox Township Meals on Wheels program, currently operated from its senior housing building, will be discontinued at...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Public Health & Safety Committee for October 2, 2025

The Will County Public Health & Safety Committee on Thursday, October 2, 2025, heard a mix of alarming and encouraging public health news, as officials reported a dramatic 50% drop...
Screenshot 2025-10-10 at 12.05.41 PM

Will County Shapes 2026 Federal Agenda, Prioritizing Health, Housing, and Workforce Funding

Will County Legislative Committee Meeting October 7, 2025 Article Summary: The Will County Legislative Committee on Tuesday began finalizing its 2026 Federal Legislative Agenda, formally adopting key priorities that include...