Monee Solar Farm Projects Granted Extensions
Will County Board Meeting | December 18, 2025
Article Summary: The Will County Board granted six-month extensions for two special use permits related to commercial solar energy facilities in Monee Township. The projects, located near Will Center Road, are moving through the permitting and development phases.
Solar Farm Extension Key Points:
-
Projects: Monee 77 LLC and Monee 32 LLC.
-
Location: Properties along South Will Center Road and West Pauling Road in Monee Township.
-
Action: First extension granted for 180 days, valid until July 17, 2026.
-
Development Status: Applicants are currently working through permitting processes.
The Will County Board on Thursday, December 18, 2025, voted to approve extensions for two commercial solar energy developments in Monee Township.
The board granted a first extension for a special use permit issued to Monee 77 LLC for a commercial solar energy facility located at 26723 South Will Center Road. The original permit, approved in January 2024, included four conditions.
Additionally, the board approved a first extension for Monee 32 LLC for a commercial solar energy facility located at the northwest corner of West Pauling Road and South Will Center Road.
Under the Will County Zoning Ordinance, special use permits can be extended on up to four separate occasions for up to 180 days each. These extensions allow the developers additional time to complete necessary permitting and pre-construction activities. Both extensions are valid until July 17, 2026.
Latest News Stories
Will County Previews ‘GuideWill’ Comprehensive Resource Management Plan
Will County Targets May Draft for Comprehensive Artificial Intelligence Policy
Sanctuary Golf Course Prepares for 30th Anniversary Following Strong January Sales and Facility Upgrades
P&Z Commission Approves Side Yard Setback Variance for Joliet Detached Garage
Executive Committee Advances Sweeping Overhaul of Will County Business Regulations
Will County Closes Out $16.2 Million Federal Rental Assistance Program, Transitions to Local Funding
Meeting Summary and Briefs: Will County Planning and Zoning Commission for March 3, 2026
Will County Leaders Debate New Construction to Escape $1.2 Million in Leases
Opioid Settlement Grants Funnel Nearly $600,000 to Local Police and Community Programs
Meeting Summary and Briefs: Will County Finance Committee for March 3, 2026
Meeting Summary and Briefs: New Lenox Public Library District Board of Trustees for February 17, 2026
New Lenox Township Cemeteries Rebound with January Profit as Maplewood Expansion Talks Progress
Tingley’s Triples, 13-Strikeout Pitching Performance Power Lincoln-Way Central Past Oswego East 12-1
Late Sixth-Inning Rally, Timely Hitting Propel Lincoln-Way Central Past St. Laurence 4-1