District 210 Awards $24.4 Million Contract for Major HVAC Upgrades

Spread the love

Lincoln-Way Community High School District 210 Meeting | December 18, 2025

Article Summary: The District 210 Board of Education awarded a $24.4 million bid to BEAR Construction Company for comprehensive mechanical and HVAC upgrades at Lincoln-Way Central and East high schools. The project is funded through life safety bonds approved in 2025 and is scheduled to be executed over the next two summers.

Mechanical Upgrades Key Points:

  • Total Contract Value: $24,419,400 awarded to BEAR Construction Company.

  • Equipment Direct Purchase: An additional $3,750,000 was approved for the direct purchase of mechanical equipment through the OMNIA co-op.

  • Timeline: The majority of the work at Lincoln-Way Central is slated for completion in the summer of 2026, with carryover work at both Central and East in 2027.

  • Budget Status: Total project projections, including fees and equipment, stand at $30,415,862, remaining within the $30,420,000 bond funding.

The Lincoln-Way Community High School District 210 Board of Education on Thursday, Dec. 18, 2025, moved forward with its massive life safety initiative by awarding a $24,419,400 bid for HVAC and mechanical upgrades.

The board selected BEAR Construction Company as the lowest qualified bidder for “Base Bid C,” which covers comprehensive work at both Lincoln-Way Central and Lincoln-Way East. The contract includes several alternates, such as the replacement of controls for existing equipment and the installation of conduit for new ComEd primary conductors at Lincoln-Way East.

District officials worked with DLA Architects to structure the bid process, eventually opting to “sole-source” or direct-purchase certain mechanical units through the OMNIA co-op to ensure proper fit and compliance with existing infrastructure. This equipment purchase, totaling $3.75 million from Thermosystems, was approved in a separate motion.

“We are right on budget in terms of life safety,” Assistant Superintendent Michael Duback told the board. “If there were any sort of unknown costs that exceed the life safety bond total, we will draw from budgeted capital projects funding.”

One remaining variable is the potential cost from ComEd related to switchgear upgrades, which is currently estimated at approximately $15,000.

Director of Buildings and Grounds Charles Welke has already begun scheduling meetings with the construction manager to finalize timelines. The plan prioritizes the bulk of the work at Central during the upcoming summer to minimize disruption to the 2026-27 school year.

Leave a Comment





Latest News Stories

New Lenox Park District

New Lenox Park District Secures $698,256 Bond Issue at 3.1% Interest Rate, Receives Moody’s Rating Upgrade

New Lenox Community Park District Board of Commissioners Meeting | January 21, 2026 Article Summary:The New Lenox Community Park District Board of Commissioners officially authorized a $698,256 General Obligation Limited...
About Us Website Header - 1

New Lenox Library Completes Café Construction, Prepares for February Grand Opening

New Lenox Public Library District Board of Trustees Meeting | January 19, 2026 Article Summary:The New Lenox Public Library District has finalized the construction of its new in-house café, with...
new-lenox-fire-district-stations.3

New Lenox Fire Board Approves $3.1 Million Budget for Station 2 Construction

New Lenox Fire Protection District Board of Trustees Meeting | January 19, 2026 Article Summary:The New Lenox Fire Protection District Board of Trustees unanimously approved a $3.1 million construction budget...
New Lenox Township.2

Meeting Summary and Briefs: New Lenox Township Board of Trustees for January 8, 2026

New Lenox Township Board of Trustees Meeting | January 8, 2026 The New Lenox Township Board of Trustees kicked off its first meeting of the new year on Thursday, January...
New Lenox Township.2

New Lenox Township Food Pantry Reports Heavy December Demand, Secures New Community Partnerships

New Lenox Township Board of Trustees Meeting | January 8, 2026 Article Summary:New Lenox Township’s community services saw heavy utilization through the end of 2025, with the Food Pantry serving...
Screenshot 2026-02-04 at 2.03.49 PM

State of the College: Local Legislators Bolster Student Support Services

Joliet Junior College State of the College | February 4, 2026 Article Summary: Joliet Junior College recognized state legislators for their direct support of the Wolves Essential Pantry, which aids...
Meeting Briefs

Meeting Summary and Briefs: Public Health & Safety Committee for February 5, 2026

Public Health & Safety Committee Meeting | February 5, 2026 Meeting SummaryThe Will County Board Public Health & Safety Committee met on Tuesday, February 5, 2026, to review departmental reports...
New Lenox Township.2

New Lenox Township Prepares to Defend Marshall Cemetery Boundaries Amid Mokena Annexation Proposal

New Lenox Township Board of Trustees Meeting | January 8, 2026 Article Summary:The New Lenox Township Board of Trustees is preparing to present formal concerns to the Village of Mokena...
Joliet Junior College Graphic.5

State of the College: Dual Credit Program Enrollment Hits 6,000 Students

Joliet Junior College State of the College | February 4, 2026 Article Summary: The "12x12x12" dual credit initiative has driven a surge in high school participation, with nearly half of...
Will County Finance Logo

Meeting Summary and Briefs: Finance Committee for February 3, 2026

Finance Committee Meeting | February 3, 2026 The Will County Finance Committee met on Tuesday, February 3, 2026, to address critical facility needs and review the county's financial standing. The...
Will County P&Z Logo Planning Zoning

Fairmont Neighborhood Plan Update Prioritizes Infrastructure and Beautification Following Demographic Shift

Planning and Zoning Commission Meeting | February 3, 2026 Article Summary: The Will County Planning and Zoning Commission unanimously approved an update to the Fairmont Neighborhood Plan, addressing significant demographic...
Meeting Briefs

Meeting Summary and Briefs: New Lenox Village Board for February 9, 2026

New Lenox Village Board Meeting | February 9, 2026 The New Lenox Village Board of Trustees met on Monday, February 9, 2026, to handle a slate of contracts and financial...
Will County Board Graphic.04

Health & Safety Committee: Monee Church Kitchen Project Highlighted in County Health Impact Report

Public Health & Safety Committee Meeting | February 5, 2026 Article Summary: The Will County MAPP Collaborative presented its impact report, highlighting ARPA-funded community kitchen projects in Monee and Joliet...
Screenshot 2026-02-04 at 2.03.49 PM

State of the College: President Namuo Pushes for Bachelor’s Degrees, Cites Record Graduation Rates

Joliet Junior College State of the College | February 4, 2026 Article Summary: JJC President Dr. Clyne Namuo highlighted the college’s legislative push to offer bachelor's degrees in applied fields...
Will County Finance Logo

Emergency Freezer Replacement Approved for Adult Detention Facility

Finance Committee Meeting | February 3, 2026 Article Summary: The committee authorized an emergency expenditure of $155,000 to replace a failed walk-in freezer system at the Adult Detention Facility (ADF)....