District 210 Awards $24.4 Million Contract for Major HVAC Upgrades
Lincoln-Way Community High School District 210 Meeting | December 18, 2025
Article Summary: The District 210 Board of Education awarded a $24.4 million bid to BEAR Construction Company for comprehensive mechanical and HVAC upgrades at Lincoln-Way Central and East high schools. The project is funded through life safety bonds approved in 2025 and is scheduled to be executed over the next two summers.
Mechanical Upgrades Key Points:
-
Total Contract Value: $24,419,400 awarded to BEAR Construction Company.
-
Equipment Direct Purchase: An additional $3,750,000 was approved for the direct purchase of mechanical equipment through the OMNIA co-op.
-
Timeline: The majority of the work at Lincoln-Way Central is slated for completion in the summer of 2026, with carryover work at both Central and East in 2027.
-
Budget Status: Total project projections, including fees and equipment, stand at $30,415,862, remaining within the $30,420,000 bond funding.
The Lincoln-Way Community High School District 210 Board of Education on Thursday, Dec. 18, 2025, moved forward with its massive life safety initiative by awarding a $24,419,400 bid for HVAC and mechanical upgrades.
The board selected BEAR Construction Company as the lowest qualified bidder for “Base Bid C,” which covers comprehensive work at both Lincoln-Way Central and Lincoln-Way East. The contract includes several alternates, such as the replacement of controls for existing equipment and the installation of conduit for new ComEd primary conductors at Lincoln-Way East.
District officials worked with DLA Architects to structure the bid process, eventually opting to “sole-source” or direct-purchase certain mechanical units through the OMNIA co-op to ensure proper fit and compliance with existing infrastructure. This equipment purchase, totaling $3.75 million from Thermosystems, was approved in a separate motion.
“We are right on budget in terms of life safety,” Assistant Superintendent Michael Duback told the board. “If there were any sort of unknown costs that exceed the life safety bond total, we will draw from budgeted capital projects funding.”
One remaining variable is the potential cost from ComEd related to switchgear upgrades, which is currently estimated at approximately $15,000.
Director of Buildings and Grounds Charles Welke has already begun scheduling meetings with the construction manager to finalize timelines. The plan prioritizes the bulk of the work at Central during the upcoming summer to minimize disruption to the 2026-27 school year.
Latest News Stories
Meeting Summary and Briefs: New Lenox Public Library District Board of Trustees for January 19, 2026
Board Approves $479,000 Wireless Network Overhaul to Replace Aging Tech
California lawmakers talk about impacts of H.R. 1 for food aid
FBI searches Los Angeles schools superintendent’s home
Illinois quick hits: Guaranteed income for moms on Medicaid
Trump administration halts $259M in Medicaid funds to Minnesota
State of Union criticized by Southwest Dems, praised by GOP
Consumer advocates, Illinois lawmakers target ‘unnecessary’ utility costs
Large taxpayer costs coming to Indiana or Illinois for new Bears stadium
Trump’s tariffs set to rise to 15% for some countries, Greer says
Clintons to face questions from lawmakers this week over Epstein ties
Auditor general nomination approved unanimously in Illinois