Committee Grants Lenox Solar Farm Project Six-Month Variance Extension

Spread the love

Will County Planning and Zoning Commission Meeting | November 18, 2025

Article Summary:
The Will County Planning and Zoning Commission has approved a 180-day extension for variances tied to a commercial solar energy facility in New Lenox Township. The extension provides the developer, Greenpath New Lenox LandCo LLC, with the necessary time to prepare the site for planting pollinator-friendly ground cover in the spring of 2026.

Solar Farm Variance Extension Key Points:

  • Location: Vacant property on South Spencer Road, New Lenox Township.

  • Project: A 4.95-megawatt commercial solar energy facility.

  • Variances Extended: Four variances related to increasing ground cover height to 36 inches and reducing required mowings from five times to one time per year.

  • New Expiration Date: The variances will now expire on August 16, 2026.

JOLIET, IL – A commercial solar energy project planned for New Lenox Township received a procedural green light on Tuesday, November 18, 2025, as the Will County Planning and Zoning Commission granted a six-month extension for its previously approved zoning variances.

The applicant, Greenpath New Lenox LandCo LLC, requested the 180-day extension to prevent the variances from expiring on February 18, 2026. According to a staff memo, favorable planting conditions for the pollinator-friendly ground cover planned for the site are not expected until after that date. The extension was the first of two possible 180-day extensions allowed by the ordinance.

The commission originally approved the variances in February 2025. They allow the developer to increase the maximum height of ground cover plants from 13 inches to 36 inches and reduce the number of required mowings from five times per year to just once. These changes are designed to support the establishment of a native pollinator habitat on the site, a practice encouraged by the Illinois Pollinator-Friendly Solar Site Act.

The project involves two parcels on South Spencer Road and is planned as a 4.95 MWac commercial solar energy facility. With the unanimous approval of the extension, the variances will now remain valid until August 16, 2026, allowing the developer to proceed with site preparation and planting in the spring.

Events

No events

Leave a Comment





Latest News Stories

Illinois approves $1.5B transit package, funding for long-delayed projects

Illinois approves $1.5B transit package, funding for long-delayed projects

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Illinois lawmakers approved a $1.5 billion transit package, including long-delayed Moline-to-Chicago rail, hailed by Democrats as...
Supreme Court allows Trump to withhold partial SNAP payment

Supreme Court allows Trump to withhold partial SNAP payment

By Brett RowlandThe Center Square The Supreme Court said Friday that the Trump administration could withhold a partial payment for the federal food benefits program amid the longest-ever government shutdown....
Illinois quick hits: State EPA looks to fund EV charging stations; Tax Foundation says mayor's proposal would hinder employment;

Illinois quick hits: State EPA looks to fund EV charging stations; Tax Foundation says mayor’s proposal would hinder employment;

By Jim Talamonti | The Center SquareThe Center Square State EPA looks to fund EV charging stations The Illinois Environmental Protection Agency (EPA) has announced an Electric Vehicle (EV) Charging...
Congressional Perks: Committees, caucuses cost $50 million since 2019

Congressional Perks: Committees, caucuses cost $50 million since 2019

By Arthur KaneThe Center Square Since 2019, partisan and special interest caucuses and coalitions in the U.S. House spent at least $50 million for staff, food, travel and other expenses,...
Screenshot 2025-11-06 at 4.17.15 PM

Federal Lobbyists Brief Will County on Government Shutdown, Warn of SNAP and TSA Disruptions

Meeting Summary and Briefs: Will County Legislative Committee for November 4, 2025 Article Summary: Will County’s federal lobbyists reported that the ongoing government shutdown, now the longest in U.S. history, is...
New-Lenox-Village-Board.2

New Lenox Residents Plead for Help in Escalating Neighborhood Dispute

New Lenox Village Board Meeting | October 27, 2025 Article Summary: A New Lenox couple made an emotional plea to the Village Board, detailing a year-long dispute with a neighbor that...
Will County Logo Graphic

Commission Approves Mokena-Area Garage Variance Over Village’s Objection

Will County Planning and Zoning Commission Meeting | November 4, 2025 Article Summary: The Will County Planning and Zoning Commission approved a variance for a new garage in unincorporated Frankfort Township...
Screenshot 2025-11-05 at 4.02.49 PM

Will County Committee Advances Gougar Road Bridge Project with Over $540,000 in Agreements

Will County Public Works & Transportation Committee Meeting | November 2025 Article Summary: The Will County Board approved two key agreements for the Gougar Road bridge project in New Lenox,...
Joliet-Junior-college.-Graphic-Logo.4

JJC Receives Surprise $1.9 Million from IRS Employee Retention Credit

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryJoliet Junior College has received an unexpected $1.9 million windfall from the federal Employee Retention Credit (ERC), a...
Joliet-Junior-college.-Graphic-Logo.2

JJC Advances ERP Modernization with New Vendor and Two-Year Budget

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryJoliet Junior College is entering the next phase of its Enterprise Resource Planning (ERP) system overhaul, with the...
new-lenox-fire-district-stations.3

Station 62 Remodel Advances as Fire District Seeks to Waive Permit Fees

New Lenox Fire Protection District Meeting | September 2025 Article Summary: The planned remodel of New Lenox Fire Station 62 is moving into its next phase, with officials having completed...
Screenshot 2025-11-06 at 4.17.02 PM

Will County Committee Shapes 2026 Legislative Agendas on Housing, Energy, and Health

Meeting Summary and Briefs: Will County Legislative Committee for November 4, 2025 Article Summary: The Will County Legislative Committee advanced key priorities for its 2026 state and federal legislative agendas, focusing...
New-Lenox-School-122.3

New Lenox School District 122 Considers Community Solar Program Promising $55K in Annual Savings

New Lenox School District 122 Meeting | September 2025 Article Summary: New Lenox School District 122 is exploring a 20-year subscription to a community solar program that could save the...
FAA funding problems hit airports in California, elsewhere

FAA funding problems hit airports in California, elsewhere

By Madeline ShannonThe Center Square As Christine Finch helped her father, Graham Finch, gather his luggage at the San Francisco International Airport, she was worried about how flight delays caused...
Judge bars ICE from acting against ‘protestors,’ ‘rapid response’ activists

Judge bars ICE from acting against ‘protestors,’ ‘rapid response’ activists

By Jonathan Bilyk | Legal NewslineThe Center Square A Chicago federal judge has barred federal agents from U.S. Border Patrol and ICE from conducting crowd control actions anywhere in northern...