Consensus for power supply solution still elusive

Consensus for power supply solution still elusive

Spread the love

(The Center Square) – Rapid expansion of data centers in the mid-Atlantic region has leaves its power grid’s operator, PJM, standing at a crossroads: how can electricity supply keep up with exponential growth in demand without spiking bills for ratepayers?

After a Wednesday meeting with all of the organizations members – which include utility companies, state regulators, power plants, transmission providers, project developers, and commercial and industrial businesses – there’s still no path forward.

This, despite 12 proposals put forward for a vote. None earned majority support.

“The growth of data centers is colliding with the reality of the power grid,” said Tom Rutigliano, senior advocate for climate and energy at Natural Resources Defense Council. The advocacy group worked with Sen. Katy Fry Hester, D-Md., on one of the rejected plans.

Rutigliano told The Center Square that data centers are showing up and quickly adding cities’ worth of electric demand to the grid. Figuring out how to build power plants quickly enough to meet that demand is a $100 billion question, and reliability is at stake.

He surmises that PJM members ultimately backed proposals that served their own interests, preventing any real solution from advancing and leaving the grid’s board of directors with a hard choice – one he is optimistic will incorporate the best of each plan.

“We hope they fulfill their obligation to the 67 million people in the PJM region and commit to protecting reliability, treat all customers fairly, and not subsidize data centers at public expense,” Rutigliano said.

In addition to grappling with the core issues of reliability and affordability, open access is just as critical, Rutigliano said. It ensures all generators, including clean energy projects, have an equal opportunity to connect to the grid.

He warned that some proposed fast-track processes would heavily favor large fossil fuel plants, creating a permanent two-tier system where fossil fuel “gets a kind of concierge class connect to the grid and clean energy sits in coach.” From where NRDC sits, he added, that would be an unacceptable outcome.

Rutiglio acknowledged that while renewables alone aren’t enough to guarantee grid reliability, strategically combining them with storage and maintaining a diverse energy mix can create a reliable grid.

It is absolutely feasible, he said, to achieve 80-95% renewable integration. And, though the last stretch is the most difficult, it’s nowhere near being a problem – renewables make up single-digit percentages on PJM’s grid.

He said that renewables, combined with energy storage, can be built far faster than new gas turbines; often in 18 to 24 months, compared to years-long turbine waitlists and pipeline delays. Because storage is quicker to deploy and easier to site, he hopes the final policy outcome will encourage tech companies toward large-scale storage solutions. The goal, he added, isn’t to block data centers but to ensure they don’t shift risks onto the public, which is the goal of the “bring your own” proposals.

Roughly one-third of a data center’s cost is the power plant needed to serve it, he stated, and under the current system, taxpayers foot the bill for speculative projects – whether they get built or not – which he suggests is one of the main drivers for “bring your own.”

The voting at the Nov. 19 meeting resulted in none of the 12 proposal packages obtaining a requisite “passing” vote, Jeffrey Shields, PJM spokesman, told The Center Square via email.

“PJM opened this conversation about the integration of large loads and greatly appreciates our stakeholders for their contributions to this effort,” he said. ”The stakeholder process produced many thoughtful proposals, some of which were introduced late in the process and require additional development.”

This vote, Shields said, is advisory to PJM’s independent board, which can and does expect to act on large load additions to the system and will make its decision known in the next few weeks.

Leave a Comment





Latest News Stories

Meeting Briefs

Meeting Summary and Briefs: Lincoln-Way District 210 Board of Education for February 19, 2026

Lincoln-Way District 210 Board of Education Meeting | February 19, 2026 NEW LENOX – The Lincoln-Way Community High School District 210 Board of Education met on Thursday, February 19, 2026, to...
Will County Board Graphic.04

County Approves $1.9 Million for Wilmington-Peotone Road Engineering

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board authorized nearly $2 million in Motor Fuel Tax funds to begin Phase I design engineering for improvements...
Police Crime

County Board Authorizes Audit of Homer Glen Policing Contract; Officials Seek ‘True Cost’ of Services

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board unanimously approved a $75,000 contract to audit the cost of law enforcement services provided to the Village...
solar panels photovoltaics in solar farm

Soltage Drops Battery Storage Plans, Secures Extensions for Two Crete Solar Projects

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board granted second extensions to special use permits for two solar energy projects in Crete Township. The developer,...
Will County Board Graphic.02

Scrap Metal Drop-Off Near Mokena Approved by Single Vote

Will County Board Meeting | February 19, 2026 Article Summary: A contested proposal for an outdoor recyclable material drop-off facility in Frankfort Township passed by a single vote following objections from...
Will County Board Graphic.01

Landscape Business Approved on Cedar Road Despite ‘Dangerous Curve’ Concerns

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board approved a special use permit for a landscape business on Cedar Road in Homer Glen, despite concerns...
Screenshot 2026-05-10 at 3.41.28 PM

New Lenox and Manhattan Approve Updated 20-Year Jurisdictional Boundary Agreement

New Lenox Village Board of Trustees Meeting | February 23, 2026 Article Summary: The Village of New Lenox formally adopted an updated Intergovernmental Cooperative Planning and Jurisdictional Boundary Agreement with...
Committee-Ad-Hoc.Graphic

Meeting Summary and Briefs: Will County Ad-Hoc Ordinance Review Committee for February 10, 2026

Will County Ad-Hoc Ordinance Review Committee Meeting | February 10, 2026 Meeting SummaryThe Will County Board Ad-Hoc Ordinance Review Committee met on Tuesday, February 10, 2026, to continue its comprehensive...
Committee-Land Use.Graphic

Meeting Summary and Briefs: Will County Land Use & Development Committee for February 5, 2026

Will County Land Use & Development Committee Meeting | February 5, 2026 The Will County Land Use and Development Committee met on Thursday, February 5, 2026, to deliberate on several...
Screenshot 2026-02-22 at 5.06.42 PM

Meeting Summary and Briefs: Joliet Junior College Board of Trustees for February 18, 2026

Joliet Junior College Board of Trustees Meeting | February 18, 2026 Meeting SummaryThe Joliet Junior College Board of Trustees met on Wednesday, February 18, 2026, for a regular meeting dominated...
Committee-Executive.Graphic

Meeting Summary and Briefs: Will County Executive Committee for February 11, 2026

Will County Executive Committee Meeting | February 11, 2026 Meeting SummaryThe Will County Board Executive Committee met on Wednesday, February 11, 2026, tackling a heavy agenda focused on economic development...
Screenshot 2026-02-22 at 4.29.56 PM

Advisory Committee Debates Rigor of Online Summer School Options

Lincoln-Way District 210 Board of Education Meeting | February 19, 2026 Article Summary: The District 210 Advisory Committee reported on discussions regarding the potential expansion of online summer school offerings,...
Election Vote Graphic

Group Presents Allegations of 2024 Voter Roll Errors to County Board

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board approved a resolution calling for the review of election systems and integrity, following public comments alleging inaccuracies...
Screenshot 2026-05-10 at 3.41.28 PM

New Lenox Injects Over $250,000 into Crossroads Sports Complex Upgrades and Secures Major Tournament Contracts

New Lenox Village Board of Trustees Meeting | February 23, 2026 Article Summary: To maximize utility and revenue at the Crossroads Sports Complex, the New Lenox Village Board authorized substantial...
Will County Board Graphic.04

Will County Board Advised on Strict “Judicial” Role Ahead of Landfill Expansion Application

Will County Landfill Committee Meeting | February 10, 2026 Article Summary: During a detailed legal briefing on Tuesday, the Will County Landfill Committee received strict instructions regarding their conduct during...