'Ghost projects' haunt power grid planners and taxpayers

‘Ghost projects’ haunt power grid planners and taxpayers

Spread the love

(The Center Square) – As the country braces for a surge in electricity demand driven by large energy users like data centers, two questions lie at the center of the debate over the grid’s future: can it remain reliable and who will pay for it?

Utility experts warn that rising load forecasts are colliding with projected supply shortfalls. And, while PJM works to finalize new rules for connecting large load customers to the grid, some state officials, consumer advocates, and industry groups are zeroing in on the affordability piece of the puzzle.

Accurate load forecasting is essential in meeting rising demand without wasting capital on infrastructure that may never be used, and it affects everything – from keeping the lights on to the prices customers pay each month.

“Ghost projects” are a big part of the issues that are creating uncertainty, Todd Snitchler, president and CEO of the Electric Power Supply Association, or EPSA, told The Center Square.

A ghost project is a generation or transmission project that is announced or funded but never gets built.

Snitchler said gigawatts of new demand are being reported to the system, but there are duplications. Data center developers and hyperscalers routinely scout multiple locations at once, so the same potential project gets counted several times, artificially inflating the load forecast – leading to the risk of overbuilding, stranded costs, or unnecessary spending.

According to Snitchler, there are utilities pointing to these numbers to justify getting back into the business of rate-based generation, claiming they can deliver new plants faster and more cheaply, and with no impact on customers.

None of this can be true, he added, “because they’re subject to the same pressures we are as independent power producers.” And under their business model, they recover their costs plus a reasonable rate of return through a non-bypassable charge paid by customers.

Some states, he said, are tightening their tariffs to include only credible, large-load projects in forecasts. When AEP Ohio applied its new tariff, its projected growth over five years dropped from 30 GW to 13 GW – a 60% reduction. The former is equivalent to powering 26 million homes, while the latter is enough for 1.1 million.

“That suggests to me,” he said, “they can’t be alone in experiencing that.”

He noted that the load forecast for most Pennsylvania utilities was surprisingly flat, with others having only 1-1.5% annual growth, while PPL’s amounted to a 200% increase over 10 years. Something he says is wildly out of step with their peer utilities and raises questions about how thoroughly they are vetting projects, and how many are real.

He argued that overstated demand forecasts suggest developers need to build like crazy, justifying the utilities’ preference to get back into the rate-based generation business – and forcing customers to pay for new power plants instead of relying on the competitive market.

In these cases, Snitchler questions whether the projects are real, or simply advocacy tools designed to help publicly traded utilities grow their rate base and boost shareholder returns, as opposed to competitive developers who invest their own capital and bear the risk themselves.

His concern is that in addition to not having the best answer, there’s an incentive to have the wrong answer, because that helps advance policy objectives that may be better for some organizations, but are intentionally harmful to others.

The bottom line, EPSA says, is that realistic, data-driven planning ensures reliability for the 67 million customers in the PJM region. The solution to meeting demand is continued investment through competitive electricity markets in new and existing power generation, guided by disciplined, transparent forecasting that reflects the projects most likely to materialize.

“There is no silver bullet for this – and I’m not even convinced there’s silver buckshot. Because there’s so much happening that needs coordination for us to deliver and do our best, to ensure a reliable, affordable, and growing system,” Snitchler said. “I think everyone is aiming in the right direction, and we’d do a little better if we bickered less and cooperated more. But it doesn’t feel like where we are at the moment.”

“PJM is doing everything within our authority to reform our processes so they reflect load growth that is likely to occur, not just speculative activity,” Jeffrey Shields, PJM spokesperson, told The Center Square via email.

He said the potential for duplicative requests is one issue they are addressing with their stakeholders in the Critical Information Fast Path process for Large Load Additions, which will conclude on Nov. 19 with a recommendation to the PJM Board of Managers. The CIFP process was initiated by the Board in August to explore ways to continue to connect large loads to the system quickly and reliably without risking electricity shortages.

As part of the CIFP discussions, they are recommending several improvements to the load forecasting process, building on existing enhancements that incorporate large load adjustments into the long-term forecast. They have also standardized the system that load-serving entities use to request large load additions, to include evidence of binding commitments that facilities will be built.

PJM has also recommended a specific review process involving the states and utilities that operate within their borders; those states and their utilities also have authority to set rates and require commitments from data centers and other “large load” customers.

A summary of their proposal to deal with the issue will be considered along with 11 others.

Leave a Comment





Latest News Stories

Police Crime

Pursuit following railroad theft ends in New Lenox; one suspect at large

NEW LENOX, Ill. – A reported cargo theft in Wilmington Township sparked a multi-jurisdictional pursuit Saturday morning that ended with a crash and a manhunt in a New Lenox neighborhood. The...
Will County Board Graphic.04

Waste Management Commits to Expanded Litter Patrols Around Landfill

Will County Landfill Committee Meeting | Jan. 13, 2026 Article Summary: Following complaints from county officials, Waste Management has agreed to significantly expand its litter collection efforts along roadways surrounding...
Meeting Briefs

Meeting Summary and Briefs: Will County Ad-Hoc Ordinance Review Committee for Jan. 13, 2026

Will County Ad-Hoc Ordinance Review Committee Meeting | Jan. 13, 2026 The Will County Board Ad-Hoc Ordinance Review Committee met on Tuesday, January 13, 2026, to continue its comprehensive update...
Will County Board Graphic.01

County Approves $22 Million in Road Projects for Lorenzo Road and Mills Road

Will County Board Meeting | January 15, 2026 Article Summary: The Will County Board approved major infrastructure contracts, including an $18.8 million bridge replacement on Lorenzo Road and a $3.2...
Will County Board Graphic.03

Landfill Committee Advances Plan to Purchase Fourth Compressor for RNG Plant

Will County Landfill Committee Meeting | Jan. 13, 2026 Article Summary: The Landfill Committee voted to move forward with engineering estimates for a fourth compressor at the Prairie View Renewable...
Will County Board Graphic.03

Ad-Hoc Committee Retains Noise Ordinance Despite Enforcement Frustrations

Will County Ad-Hoc Ordinance Review Committee Meeting | Jan. 13, 2026 Article Summary: The Ad-Hoc Ordinance Review Committee voted to retain the county’s public nuisance noise ordinance despite members describing...
Will County Board Graphic.03

Will County Commits $15M to Transfer Sanitary District Operations to City of Joliet

Will County Board Meeting | January 15, 2026 Article Summary: The Will County Board has authorized an intergovernmental agreement to dissolve the Southeast Joliet Sanitary District and transfer its water...
Attorneys review Chicago Teachers Union audits following congressional request

Attorneys review Chicago Teachers Union audits following congressional request

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – The Chicago Teachers Union says it has complied with a U.S. House committee’s request to release financial...
DHS: ICE agent shoots, kills armed Minneapolis man; protests erupt

DHS: ICE agent shoots, kills armed Minneapolis man; protests erupt

By Elyse ApelThe Center Square Federal agents shot and killed an armed man in Minneapolis Saturday morning, the U.S. Department of Homeland Security said. "At 9:05 AM CT, as DHS...
'They deserve their story': Bill aims to open foster care files

‘They deserve their story’: Bill aims to open foster care files

By Cat Barker | The Center Square contributorThe Center Square (The Center Square) – Illinois lawmakers are moving to ensure families adopting children from the state’s foster care system receive...
Under Trump, Big Bend CBP Sector in Texas making history

Under Trump, Big Bend CBP Sector in Texas making history

By Bethany BlankleyThe Center Square The far west Texas U.S. Customs and Border Protection sector of Big Bend made history under the Biden and Trump administrations – for different reasons....
lincoln way school district 210 logo.1

Meeting Summary and Briefs: Lincoln-Way 210 Board of Education for Jan. 15, 2026

Lincoln-Way 210 Board of Education Meeting | Jan. 15, 2026 Overall Meeting SummaryThe Lincoln-Way Community High School District 210 Board of Education met on Thursday, January 15, 2026, covering a...
will county board meeting graphic.5

Prairie View Landfill Expansion Plans Take Shape as Consultants Navigate Design Challenges

Will County Landfill Committee Meeting | Jan. 13, 2026 Article Summary: Geologic Associates presented a detailed status update on the proposed expansion of the Prairie View Landfill, outlining a dual...
Pro-life marchers say fight against abortion isn't over

Pro-life marchers say fight against abortion isn’t over

By Emily RodriguezThe Center Square Despite the overturn of Roe v. Wade, the March for Life continues. With the decision to ban or support abortion now in the hands of...
Govt. funding process close to finish line as Senate preps for final vote

Govt. funding process close to finish line as Senate preps for final vote

By Thérèse BoudreauxThe Center Square The ball is in the U.S. Senate’s court to avert a government shutdown Jan. 30, with six fiscal year 2026 appropriations bills signed into law...