'Ghost projects' haunt power grid planners and taxpayers

‘Ghost projects’ haunt power grid planners and taxpayers

Spread the love

(The Center Square) – As the country braces for a surge in electricity demand driven by large energy users like data centers, two questions lie at the center of the debate over the grid’s future: can it remain reliable and who will pay for it?

Utility experts warn that rising load forecasts are colliding with projected supply shortfalls. And, while PJM works to finalize new rules for connecting large load customers to the grid, some state officials, consumer advocates, and industry groups are zeroing in on the affordability piece of the puzzle.

Accurate load forecasting is essential in meeting rising demand without wasting capital on infrastructure that may never be used, and it affects everything – from keeping the lights on to the prices customers pay each month.

“Ghost projects” are a big part of the issues that are creating uncertainty, Todd Snitchler, president and CEO of the Electric Power Supply Association, or EPSA, told The Center Square.

A ghost project is a generation or transmission project that is announced or funded but never gets built.

Snitchler said gigawatts of new demand are being reported to the system, but there are duplications. Data center developers and hyperscalers routinely scout multiple locations at once, so the same potential project gets counted several times, artificially inflating the load forecast – leading to the risk of overbuilding, stranded costs, or unnecessary spending.

According to Snitchler, there are utilities pointing to these numbers to justify getting back into the business of rate-based generation, claiming they can deliver new plants faster and more cheaply, and with no impact on customers.

None of this can be true, he added, “because they’re subject to the same pressures we are as independent power producers.” And under their business model, they recover their costs plus a reasonable rate of return through a non-bypassable charge paid by customers.

Some states, he said, are tightening their tariffs to include only credible, large-load projects in forecasts. When AEP Ohio applied its new tariff, its projected growth over five years dropped from 30 GW to 13 GW – a 60% reduction. The former is equivalent to powering 26 million homes, while the latter is enough for 1.1 million.

“That suggests to me,” he said, “they can’t be alone in experiencing that.”

He noted that the load forecast for most Pennsylvania utilities was surprisingly flat, with others having only 1-1.5% annual growth, while PPL’s amounted to a 200% increase over 10 years. Something he says is wildly out of step with their peer utilities and raises questions about how thoroughly they are vetting projects, and how many are real.

He argued that overstated demand forecasts suggest developers need to build like crazy, justifying the utilities’ preference to get back into the rate-based generation business – and forcing customers to pay for new power plants instead of relying on the competitive market.

In these cases, Snitchler questions whether the projects are real, or simply advocacy tools designed to help publicly traded utilities grow their rate base and boost shareholder returns, as opposed to competitive developers who invest their own capital and bear the risk themselves.

His concern is that in addition to not having the best answer, there’s an incentive to have the wrong answer, because that helps advance policy objectives that may be better for some organizations, but are intentionally harmful to others.

The bottom line, EPSA says, is that realistic, data-driven planning ensures reliability for the 67 million customers in the PJM region. The solution to meeting demand is continued investment through competitive electricity markets in new and existing power generation, guided by disciplined, transparent forecasting that reflects the projects most likely to materialize.

“There is no silver bullet for this – and I’m not even convinced there’s silver buckshot. Because there’s so much happening that needs coordination for us to deliver and do our best, to ensure a reliable, affordable, and growing system,” Snitchler said. “I think everyone is aiming in the right direction, and we’d do a little better if we bickered less and cooperated more. But it doesn’t feel like where we are at the moment.”

“PJM is doing everything within our authority to reform our processes so they reflect load growth that is likely to occur, not just speculative activity,” Jeffrey Shields, PJM spokesperson, told The Center Square via email.

He said the potential for duplicative requests is one issue they are addressing with their stakeholders in the Critical Information Fast Path process for Large Load Additions, which will conclude on Nov. 19 with a recommendation to the PJM Board of Managers. The CIFP process was initiated by the Board in August to explore ways to continue to connect large loads to the system quickly and reliably without risking electricity shortages.

As part of the CIFP discussions, they are recommending several improvements to the load forecasting process, building on existing enhancements that incorporate large load adjustments into the long-term forecast. They have also standardized the system that load-serving entities use to request large load additions, to include evidence of binding commitments that facilities will be built.

PJM has also recommended a specific review process involving the states and utilities that operate within their borders; those states and their utilities also have authority to set rates and require commitments from data centers and other “large load” customers.

A summary of their proposal to deal with the issue will be considered along with 11 others.

Leave a Comment





Latest News Stories

Lawmakers grill Hegseth on Iran conflict, $1.5T budget request

Lawmakers grill Hegseth on Iran conflict, $1.5T budget request

By Thérèse BoudreauxThe Center Square As the U.S.-Iran conflict continues with no end in sight, Secretary of War Pete Hegseth dodged questions from U.S. lawmakers on both sides of the...
Trump confirms Makary out at FDA

Trump confirms Makary out at FDA

By Andrew RiceThe Center Square President Donald Trump confirmed on Tuesday that Marty Makary would be leaving his post atop the U.S. Food and Drug Administration. While speaking to reporters...
Trump to 'be thinking' about red line in Iran ceasefire

Trump to ‘be thinking’ about red line in Iran ceasefire

By Andrew RiceThe Center Square President Donald Trump said he will "be thinking" about a potential red line in the ceasefire between the U.S. and Iran as he departed to...
Detroit border agents seize greatest volume of drugs at northern border

Detroit border agents seize greatest volume of drugs at northern border

By Bethany BlankleyThe Center Square Over the past seven years, Border Patrol agents working in the U.S. Customs and Border Protection Detroit Sector have seized the greatest volume of drugs...
WATCH: Ex-rep sues Pritzker, Illinois over race-based congressional map

WATCH: Ex-rep sues Pritzker, Illinois over race-based congressional map

By Sean Reed | The Center SquareThe Center Square (The Center Square) – Illinois’ congressional district map is being challenged over what some argue are unconstitutional racial requirements for districts....
Lawmakers tussle over impacts of ‘equitable’ school funding in Illinois

Lawmakers tussle over impacts of ‘equitable’ school funding in Illinois

By Sean Reed | The Center SquareThe Center Square (The Center Square) – The evidence-based funding formula for public schools in Illinois, signed into law in 2017, was under the...
Illinois Quick Hits: $42.6M UIS student library on schedule

Illinois Quick Hits: $42.6M UIS student library on schedule

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – The Illinois Capital Development Board says a $42.6 million state taxpayer-funded library project is on schedule at...
An 'arms race' for pay at elite, tax-exempt colleges

An ‘arms race’ for pay at elite, tax-exempt colleges

By Jared StrongThe Center Square Top private nonprofit universities that receive government funding pay some of their top leaders millions of dollars and one even received a $20 million longevity...
Inflation rises to 3.8%, driven by energy prices

Inflation rises to 3.8%, driven by energy prices

By Andrew RiceThe Center Square Inflation increased 0.6% in April, with an overall rate of 3.8% over the last 12 months, according to new data from the U.S. Bureau of...
New congressional map expected for Alabama in wake of high court ruling

New congressional map expected for Alabama in wake of high court ruling

By Alan WootenThe Center Square Alabama could soon have a congressional map in place that would offer the chance for a Republican gain of seat in the U.S. House of...
Will County Board Graphic.04

State Legislative Update: Housing Mandates, Mega Projects, and Data Centers Prompt Local Control Concerns

Will County Board Legislative Committee Meeting | May 5, 2026 Article SummaryState lobbyists from Mac Strategies briefed the Will County Board Legislative Committee on the final push of the spring...
Mastriano nominated to serve as Ambassador to Slovakia

Mastriano nominated to serve as Ambassador to Slovakia

By John ColeThe Center Square State Sen. Doug Mastriano, R-Chambersburg, has been nominated by President Donald Trump’s administration to serve as the United States Ambassador to Slovakia. “I am deeply...
Trump seeks rare suspension of the federal gas tax

Trump seeks rare suspension of the federal gas tax

By Alton WallaceThe Center Square President Donald Trump said Monday he will move to suspend the federal gasoline tax as the national average price of a gallon remains above $4.50...
Trump asks court to freeze tariff ruling amid import surge fears

Trump asks court to freeze tariff ruling amid import surge fears

By Brett RowlandThe Center Square The Trump administration asked the U.S. Court of International Trade on Monday to pause its ruling blocking the president's Section 122 tariffs, warning that even...
Data center regs proposed as $20 billion, 795-acre Joliet project advances

Data center regs proposed as $20 billion, 795-acre Joliet project advances

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Opponents of a planned $20 billion data center project in Joliet say big tech money arrived before...