'Consequential' day ahead for future household electricity costs

‘Consequential’ day ahead for future household electricity costs

Spread the love

(The Center Square) – PJM’s Board of Directors is preparing to make one of the most consequential decisions of this decade, says a coalition of state legislators from the grid operator’s region.

And, depending upon the choice made, it could save households and businesses as much as $70 per month on their utility bills.

On Monday, ahead of a pending Nov. 19 vote on proposals that would determine how data centers should be connected to the grid, the coalition announced it submitted a plan to ensure the 67 million Americans served by PJM will not bear an unfair share of reliability risk and cost driven by soaring data center electricity demand.

The Protecting Ratepayers Proposal came in response to PJM’s Critical Issues Fast Path, or CIFP – an initiative launched in August to fast-track discussions and policy decisions on managing rapid growth of large load customers like data centers.

The proposal builds on a resolution passed by the National Conference of State Legislators and upon elements of others submitted to PJM, including one submitted by the governors of Maryland, Virginia, New Jersey, and Pennsylvania, in partnership with the Data Center Coalition and Exelon.

It also echoes proposals from consumer advocate groups in Pennsylvania and Maryland and has gained the support of the Natural Resources Defense Council, or NRDC, whose original suggestions were included.

During a media briefing on Monday, Democratic DC Councilmember Charles Allen emphasized that the issue impacts everyone, and the coalition’s size and scope highlight what’s at stake. “It’s not very often that leaders from a broad number of states come together in a shared fight,” he added.

Sen. Katie Fry Hester, D-Md., explained that anticipated demand from new data centers is projected to reach 32 GW, with some forecasts suggesting it could grow to 60 GW in the coming years.

“That’s the equivalent of adding a major city like Philadelphia to the grid almost overnight,” she said.

On Wednesday, after reviewing between 16 and 20 proposals, PJM and its members – including utility companies, transmission operators and power generators – then vote on their recommendations to the Board of Directors.

“Data centers should power their profits, not drain the wallets of everyday Americans,” said Sen. Rachel Ventura, a Democrat from Illinois.

Her state, she said, has already started to address the challenge by passing Senate Bill 25, also known as The Clean and Reliable Grid Affordability Act, now awaiting Gov. JB Pritzker’s signature.

The bill invests in battery storage, energy efficiency, and smart grid technologies, Ventura said. It adds 3 GW of storage with no upfront cost to consumers, which can be dispatched at peak time to lower prices and improve reliability. She noted that it’s a strong first step, but Illinois alone cannot solve a regional problem.

“The cost of electricity is expected to skyrocket by over $100 billion through 2033 due to data center load growth, which could cost families and businesses in PJM territory an extra $70 per month,” said Claire Lang-Ree, advocate for the Sustainable FERC Project at NRDC.

Lang-Ree said the coalition’s proposal is one of the few that addresses the difficult question of what happens if there isn’t enough power to go around.

She explained that under their proposal, data centers can join PJM quickly, but they will be interruptible – or the first to be curtailed – unless they bring their own capacity to the grid.

Other key features of the proposal include:

Multiple fast-track options for data centers to bring their own firm power supply through new power plants, demand response, or distributed resources – while preventing them from pulling existing plants from the grid or jumping ahead of renewable projects already in the queue. Load forecasting enhancements to screen out speculative projects for transmission planning.A temporary extension of the capacity market “price collar” to curb further price spikes.

Legislators stressed that while each state faces unique energy challenges, they are united in the shared goal of ensuring ratepayers across the PJM region are not subsidizing the energy costs of new data centers being built by Fortune 500 companies like Google, Amazon, and Microsoft.

Delaware and Maryland have enacted transparency laws requiring public utilities to report how they vote in the PJM Interconnection stakeholder/committee process, according to Sen. Stephanie Hansen, a Democrat from Delaware.

Energy resources are scarce, so competition is fierce, Hansen said.

“It’s the wild wild west when it comes to where data centers will be located. There are few rules, and states are competing against each other for jobs and revenue, “knowing that the cost to feed the energy monster,” as Hansen described it, “will be socialized to other ratepayers in and out of the state.”

She said they encourage PJM to forge a responsible path going forward – and keeping renewable projects at the forefront of interconnection planning is critically important. “This is a marathon, not a sprint,” she said, “and the starting gun has already sounded.”

Events

No events

Leave a Comment





Latest News Stories

Meeting-Briefs

Meeting Summary: New Lenox School District 122 Board of Education for June 17, 2025

The New Lenox School District 122 Board of Education handled significant financial business at its June 17 meeting, approving a tentative budget for the 2025-2026 school year and renewing insurance...
Meeting-Briefs

Meeting Summary: New Lenox Board of Trustees for July 28, 2025

The New Lenox Village Board meeting on Monday was marked by ceremony and significant action on major developments. The board honored the new Pope Leo XIV and retiring Police Chief...
Meeting-Briefs

Meeting Summary and Briefs: Monee Village Board for July 23, 2025

The Monee Village Board of Trustees heard a detailed presentation for a major industrial redevelopment, approved a significant payment for its nearly-completed public works facility, and gave final clearance for...
new-lenox-fire-district-stations.2

New Lenox Fire Board Denies Variance Over Extreme Hydrant Distance, Citing Safety

NEW LENOX – The New Lenox Fire Protection District Board of Trustees unanimously denied a homeowner's variance request on Monday, citing significant public safety concerns over the property's extreme distance...
new-lenox-fire-district-stations.4

New Lenox Fire District Secures $35,000 Grant for UTV in Solar Farm Agreement

NEW LENOX – The New Lenox Fire Protection District is set to receive a $35,000 grant to purchase a new Utility Task Vehicle (UTV) as part of a community benefit...
Meeting-Briefs

Meeting Summary: New Lenox Fire Protection District for June 16, 2025

The New Lenox Fire Protection District Board of Trustees took decisive action on a residential fire code variance and discussed a new community partnership for a planned solar farm during...
Ad-Hock-July-22nd

Will County Committee Forwards Overhauled Purchasing Code Amid Debate on Local Contractor Preference

The Will County Ad-Hoc Ordinance Review Committee advanced a major overhaul of the county's purchasing code Tuesday, but only after a split vote and a pointed debate over a separate,...
Ad-Hock-July-22nd

Finance Officials Clarify How Will County Tracks Assets, From Vehicles to Desks

Will County finance officials on Tuesday detailed the policies governing how the county tracks its physical and digital assets, explaining the $5,000 threshold for items that are formally capitalized and...
Ad-Hock-July-22nd

Will County Treasurer Confirms Free Online Tax Payment Option, Warns Against High Credit Card Fees

Will County Treasurer Tim Brophy confirmed Tuesday that property owners have a free online payment option available and advised residents to avoid the high convenience fees associated with using credit...
Ad-Hock-July-22nd

Committee Highlights ‘Lack of Teeth’ in County Code Enforcement Process

While the Will County Ad-Hoc Ordinance Review Committee quickly approved minor updates to its administrative adjudication ordinance Tuesday, the action sparked a broader discussion about resident frustration over the enforcement...
Ad-Hock-July-22nd

Committee Highlights ‘Lack of Teeth’ in County Code Enforcement Process

While the Will County Ad-Hoc Ordinance Review Committee quickly approved minor updates to its administrative adjudication ordinance Tuesday, the action sparked a broader discussion about resident frustration over the enforcement...
Meeting-Briefs

Meeting Briefs: Will County Ad-Hoc Ordinance Review Committee for July 22, 2025

AI Policy Discussion Urged: Chair Jackie Triner called for the county to develop a comprehensive policy on the use of Artificial Intelligence. Citing a recent conference, Triner noted the potential benefits...
New-Lenox-Village-Board.1

New Lenox’s Crossroads Sports Complex Opens to Rave Reviews, On Time and Under Budget

NEW LENOX – The newly opened Crossroads Sports Complex is already proving to be a resounding success, according to a report delivered at the New Lenox Village Board meeting on...
New-Lenox-Village-Board.4

New Lenox Waives Over $13,000 in Permit Fees for Park District, Church Projects

NEW LENOX – The New Lenox Village Board unanimously approved waiving more than $13,000 in permit and plan review fees for two significant community projects during its meeting on Monday....
New-Lenox-Police.3

New Lenox Approves Site Plan for MBPRO Truck Repair on Moni Drive

NEW LENOX – The Village Board on Monday approved site modifications for a new truck repair business, MBPRO Services, set to open at 21660 South Moni Drive. The board unanimously...