Will County Board Land Use Committee Graphic.4

Will County Committee Grants Extensions for Crete, Washington Township Solar Projects

Spread the love

Will County Land Use & Development Committee Meeting | November 6, 2025

Article Summary: The Will County Land Use and Development Committee granted 180-day extensions for two commercial solar energy projects in Crete and Washington Townships, giving the developer additional time to complete the necessary permitting before their initial approvals expire.

Solar Farm Permit Extensions Key Points:

  • A first extension was approved for a TPE Development affiliated project in Crete Township (ZC-23-108), pushing its deadline to June 19, 2026.

  • A first extension was also granted for a related TPE project in Washington Township (ZC-24-020), moving its deadline to November 12, 2026.

  • The extensions were requested to allow more time to complete complex permitting and pre-construction processes.

  • Special use permits for solar facilities in Will County typically expire after two years if construction has not legally commenced.

JOLIET, IL — Two large-scale solar energy projects in eastern Will County were granted more time to get off the ground after the Will County Land Use and Development Committee on Thursday, November 6, 2025, approved their first 180-day permit extensions.

The committee unanimously approved the requests for projects in Crete and Washington townships, both associated with TPE Development, LLC. The extensions are necessary because the special use permits approved by the County Board are set to expire within the next year, and the projects have not yet completed the building permit process to legally establish the use.

The first extension was for case SEXT-25-019, concerning a commercial solar facility at the southeast corner of South Nacke Road and West Loves Lane in Crete Township. Originally approved on December 21, 2023, the permit was set to expire in December 2025. The applicant has applied for a building permit but cited needing more time to complete the process. The extension is now valid through June 19, 2026.

The second approval was for case SEXT-25-020, for a solar facility at the southeast corner of West Indiana Avenue and South Western Avenue in Washington Township, near Beecher. This project was approved on May 16, 2024, and its permit was set to expire in May 2026. According to county staff, the applicant has not yet applied for a building permit. The extension pushes the new expiration date to November 12, 2026.

Under the Will County Zoning Ordinance, a special use permit lapses after two years if the use has not been legally established. The ordinance allows the County Board to grant up to four separate 180-day extensions for “good cause.” Jordan Belknap, representing the applicant, stated they have been working with local authorities, including University Park, on necessary road improvements for the Crete project before construction can begin.

Today Jun 11
Sunny
80° 61°

Sunny

💨 10 to 15 mph 💧 0%

Leave a Comment





Latest News Stories

solar panels photovoltaics in solar farm

Will County Grants Extensions for Seven Solar and Commercial Projects Amid Permitting Delays

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: The Will County Land Use and Development Committee approved a slate of extensions for seven previously authorized...
Screenshot 2026-05-10 at 4.08.39 PM

Meeting Summary and Briefs: New Lenox Village Board of Trustees for March 9, 2026

New Lenox Village Board of Trustees Meeting | March 9, 2026 The New Lenox Village Board of Trustees advanced several capital projects and administrative measures during its regular meeting on...
Will County Board Graphic.03

Will County Committee Postpones Liquor, Ad-Hoc Committee: Gaming, and Tobacco Ordinance Updates Amid Extensive Revisions

Will County Board Ad-Hoc Ordinance Review Committee Meeting | March 10, 2026 Article Summary: A Will County Board committee paused the advancement of major updates to the county's liquor, video...
Screenshot 2026-05-10 at 4.08.39 PM

Joliet Resident Appeals to New Lenox Board Over Massive Data Center Proposal

New Lenox Village Board of Trustees Meeting | March 9, 2026 Article Summary: A Joliet resident utilized the New Lenox Village Board's public comment period to raise alarms about an...
solar panels photovoltaics in solar farm

Land Use Committee Approves 4.98-Megawatt Solar Facility on Eagle Lake Road Near Peotone

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: Reversing a deadlocked Planning and Zoning Commission, the Will County Land Use and Development Committee unanimously approved...
Will County Board Graphic.04

Will County Advances Nearly $1.5 Million in Right-of-Way and Improvement Agreements for Weber, Gougar, and Laraway Roads

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Public Works and Transportation Committee authorized a slate of professional services and construction agreements Tuesday to...
Will County Public Works Committee

Public Works Committee: Approves $1.59 Million Contract for Scheer Road Bridge Replacement in Green Garden Township

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Will County Public Works and Transportation Committee on Tuesday advanced a nearly $1.6 million contract to...
will county Committee-Legislative.Graphic

Will County Board Backs $10 Million State Public Health Grant Increase Amid Funding Cuts

Legislative Committee Meeting | March 2026 Article Summary: The Will County Legislative Committee unanimously approved a resolution supporting a state legislative push to increase the Local Health Protection Grant by $10...
Monee Fire

Barn Fire on Whispering Hills Lane Claims Livestock, Draws Extensive Mutual Aid Response

Article Summary: A massive late-night structure fire completely destroyed a 60-by-60-foot wood frame barn on Whispering Hills Lane, resulting in the loss of 15 animals but no human injuries. Firefighters from...
Will County Board Graphic.01

Will County Public Works Committee Shelves License Plate Reader Agreement Amid Bipartisan Privacy Concerns

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Will County Public Works and Transportation Committee abruptly removed an agreement with the Illinois State Police...
Will County P&Z Logo Planning Zoning.2

Will County Planning and Zoning Commission Overrides Staff to Approve New Lenox Accessory Building Variance

Will County Planning and Zoning Commission Meeting | March 3, 2026 Article Summary: The Will County Planning and Zoning Commission voted to override a staff recommendation of denial, approving a...
sheriff dog

Will County Sheriff’s Office Welcomes Remi, First Electronic Scent Detection Dog

Article Summary: The Will County Sheriff’s Office announced the addition of Remi, a Labrador serving as the department's first Electronic Scent Detection dog. The newly trained K9 will assist investigators...
Will County Public Works Committee

Will County Transportation Department Announces Open House for Manhattan-Monee Road Expansion

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Will County Division of Transportation is inviting residents to a public open house on March 19...
Screenshot 2026-05-10 at 4.08.39 PM

Village Board Grants Rare Building Code Exemption for Residential Deck Railing

New Lenox Village Board of Trustees Meeting | March 9, 2026 Article Summary: Following a permitting error by the Village's previous building inspector, the New Lenox Board granted a waiver...
Will County Board Graphic.04

Will County Community Mental Health Board Faces $5 Million Shortfall in 2026 Grant Requests

Will County Executive Committee Meeting | March 12, 2026 Article Summary: The Will County Community Mental Health Board has received over $9 million in funding requests for its 2026 grant cycle,...