Will County Committee Grants Extensions for Crete, Washington Township Solar Projects

Spread the love

Will County Land Use & Development Committee Meeting | November 6, 2025

Article Summary: The Will County Land Use and Development Committee granted 180-day extensions for two commercial solar energy projects in Crete and Washington Townships, giving the developer additional time to complete the necessary permitting before their initial approvals expire.

Solar Farm Permit Extensions Key Points:

  • A first extension was approved for a TPE Development affiliated project in Crete Township (ZC-23-108), pushing its deadline to June 19, 2026.

  • A first extension was also granted for a related TPE project in Washington Township (ZC-24-020), moving its deadline to November 12, 2026.

  • The extensions were requested to allow more time to complete complex permitting and pre-construction processes.

  • Special use permits for solar facilities in Will County typically expire after two years if construction has not legally commenced.

JOLIET, IL — Two large-scale solar energy projects in eastern Will County were granted more time to get off the ground after the Will County Land Use and Development Committee on Thursday, November 6, 2025, approved their first 180-day permit extensions.

The committee unanimously approved the requests for projects in Crete and Washington townships, both associated with TPE Development, LLC. The extensions are necessary because the special use permits approved by the County Board are set to expire within the next year, and the projects have not yet completed the building permit process to legally establish the use.

The first extension was for case SEXT-25-019, concerning a commercial solar facility at the southeast corner of South Nacke Road and West Loves Lane in Crete Township. Originally approved on December 21, 2023, the permit was set to expire in December 2025. The applicant has applied for a building permit but cited needing more time to complete the process. The extension is now valid through June 19, 2026.

The second approval was for case SEXT-25-020, for a solar facility at the southeast corner of West Indiana Avenue and South Western Avenue in Washington Township, near Beecher. This project was approved on May 16, 2024, and its permit was set to expire in May 2026. According to county staff, the applicant has not yet applied for a building permit. The extension pushes the new expiration date to November 12, 2026.

Under the Will County Zoning Ordinance, a special use permit lapses after two years if the use has not been legally established. The ordinance allows the County Board to grant up to four separate 180-day extensions for “good cause.” Jordan Belknap, representing the applicant, stated they have been working with local authorities, including University Park, on necessary road improvements for the Crete project before construction can begin.

Events

No events

Leave a Comment





Latest News Stories

Meeting-Briefs

Meeting Summary: New Lenox Board of Trustees for July 28, 2025

The New Lenox Village Board meeting on Monday was marked by ceremony and significant action on major developments. The board honored the new Pope Leo XIV and retiring Police Chief...
Meeting-Briefs

Meeting Summary and Briefs: Monee Village Board for July 23, 2025

The Monee Village Board of Trustees heard a detailed presentation for a major industrial redevelopment, approved a significant payment for its nearly-completed public works facility, and gave final clearance for...
new-lenox-fire-district-stations.2

New Lenox Fire Board Denies Variance Over Extreme Hydrant Distance, Citing Safety

NEW LENOX – The New Lenox Fire Protection District Board of Trustees unanimously denied a homeowner's variance request on Monday, citing significant public safety concerns over the property's extreme distance...
new-lenox-fire-district-stations.4

New Lenox Fire District Secures $35,000 Grant for UTV in Solar Farm Agreement

NEW LENOX – The New Lenox Fire Protection District is set to receive a $35,000 grant to purchase a new Utility Task Vehicle (UTV) as part of a community benefit...
Meeting-Briefs

Meeting Summary: New Lenox Fire Protection District for June 16, 2025

The New Lenox Fire Protection District Board of Trustees took decisive action on a residential fire code variance and discussed a new community partnership for a planned solar farm during...
Ad-Hock-July-22nd

Will County Committee Forwards Overhauled Purchasing Code Amid Debate on Local Contractor Preference

The Will County Ad-Hoc Ordinance Review Committee advanced a major overhaul of the county's purchasing code Tuesday, but only after a split vote and a pointed debate over a separate,...
Ad-Hock-July-22nd

Finance Officials Clarify How Will County Tracks Assets, From Vehicles to Desks

Will County finance officials on Tuesday detailed the policies governing how the county tracks its physical and digital assets, explaining the $5,000 threshold for items that are formally capitalized and...
Ad-Hock-July-22nd

Will County Treasurer Confirms Free Online Tax Payment Option, Warns Against High Credit Card Fees

Will County Treasurer Tim Brophy confirmed Tuesday that property owners have a free online payment option available and advised residents to avoid the high convenience fees associated with using credit...
Ad-Hock-July-22nd

Committee Highlights ‘Lack of Teeth’ in County Code Enforcement Process

While the Will County Ad-Hoc Ordinance Review Committee quickly approved minor updates to its administrative adjudication ordinance Tuesday, the action sparked a broader discussion about resident frustration over the enforcement...
Ad-Hock-July-22nd

Committee Highlights ‘Lack of Teeth’ in County Code Enforcement Process

While the Will County Ad-Hoc Ordinance Review Committee quickly approved minor updates to its administrative adjudication ordinance Tuesday, the action sparked a broader discussion about resident frustration over the enforcement...
Meeting-Briefs

Meeting Briefs: Will County Ad-Hoc Ordinance Review Committee for July 22, 2025

AI Policy Discussion Urged: Chair Jackie Triner called for the county to develop a comprehensive policy on the use of Artificial Intelligence. Citing a recent conference, Triner noted the potential benefits...
New-Lenox-Village-Board.1

New Lenox’s Crossroads Sports Complex Opens to Rave Reviews, On Time and Under Budget

NEW LENOX – The newly opened Crossroads Sports Complex is already proving to be a resounding success, according to a report delivered at the New Lenox Village Board meeting on...
New-Lenox-Village-Board.4

New Lenox Waives Over $13,000 in Permit Fees for Park District, Church Projects

NEW LENOX – The New Lenox Village Board unanimously approved waiving more than $13,000 in permit and plan review fees for two significant community projects during its meeting on Monday....
New-Lenox-Police.3

New Lenox Approves Site Plan for MBPRO Truck Repair on Moni Drive

NEW LENOX – The Village Board on Monday approved site modifications for a new truck repair business, MBPRO Services, set to open at 21660 South Moni Drive. The board unanimously...
Meeting-Briefs

Meeting Summary: New Lenox Board of Trustees for July 14, 2025

The New Lenox Village Board of Trustees met Monday to approve site plans for a new business, waive fees for community projects, and hear a glowing report on the new...