Will County Committee Grants Extensions for Crete, Washington Township Solar Projects

Spread the love

Will County Land Use & Development Committee Meeting | November 6, 2025

Article Summary: The Will County Land Use and Development Committee granted 180-day extensions for two commercial solar energy projects in Crete and Washington Townships, giving the developer additional time to complete the necessary permitting before their initial approvals expire.

Solar Farm Permit Extensions Key Points:

  • A first extension was approved for a TPE Development affiliated project in Crete Township (ZC-23-108), pushing its deadline to June 19, 2026.

  • A first extension was also granted for a related TPE project in Washington Township (ZC-24-020), moving its deadline to November 12, 2026.

  • The extensions were requested to allow more time to complete complex permitting and pre-construction processes.

  • Special use permits for solar facilities in Will County typically expire after two years if construction has not legally commenced.

JOLIET, IL — Two large-scale solar energy projects in eastern Will County were granted more time to get off the ground after the Will County Land Use and Development Committee on Thursday, November 6, 2025, approved their first 180-day permit extensions.

The committee unanimously approved the requests for projects in Crete and Washington townships, both associated with TPE Development, LLC. The extensions are necessary because the special use permits approved by the County Board are set to expire within the next year, and the projects have not yet completed the building permit process to legally establish the use.

The first extension was for case SEXT-25-019, concerning a commercial solar facility at the southeast corner of South Nacke Road and West Loves Lane in Crete Township. Originally approved on December 21, 2023, the permit was set to expire in December 2025. The applicant has applied for a building permit but cited needing more time to complete the process. The extension is now valid through June 19, 2026.

The second approval was for case SEXT-25-020, for a solar facility at the southeast corner of West Indiana Avenue and South Western Avenue in Washington Township, near Beecher. This project was approved on May 16, 2024, and its permit was set to expire in May 2026. According to county staff, the applicant has not yet applied for a building permit. The extension pushes the new expiration date to November 12, 2026.

Under the Will County Zoning Ordinance, a special use permit lapses after two years if the use has not been legally established. The ordinance allows the County Board to grant up to four separate 180-day extensions for “good cause.” Jordan Belknap, representing the applicant, stated they have been working with local authorities, including University Park, on necessary road improvements for the Crete project before construction can begin.

Events

No events

Leave a Comment





Latest News Stories

new-lenox-park-district.6

New Lenox Park District Board Approves 2025-2026 Budget

NEW LENOX – The New Lenox Community Park District Board of Commissioners unanimously approved the budget and appropriation ordinance for the 2025-2026 fiscal year during its regular meeting on June...
New-Lenox-School-122.6

Staffing Shortage Leads D122 to Renew Contract for School Psychologist

Facing a persistent staffing shortage for a critical role, the New Lenox School District 122 Board of Education has renewed its contract with an outside agency to provide a school...
Meeting-Briefs

Meeting Summary: New Lenox Township for June 12, 2025

At its June 12 meeting, the New Lenox Township Board of Trustees heard reports on rising demand for community services, discussed ongoing maintenance projects, and assigned responsibilities to its newly...
New-Lenox-Village-Board.4

New Lenox Approves Major Residential Subdivision, Paves Way for Route 6 Commercial Growth

NEW LENOX – The Village Board took decisive action on two major developments Monday, giving final approval to a 55-lot residential subdivision for "empty nesters" and clearing a key hurdle...
New-Lenox-Sharons-Bay-Park

Contractor Selected for Sharon’s Bay Park Redevelopment

NEW LENOX – The New Lenox Community Park District is moving forward with plans to redevelop Sharon's Bay Park, having approved a contractor for the project at its Wednesday meeting....
New-Lenox-Sharons-Bay-Park

Contractor Selected for Sharon’s Bay Park Redevelopment

NEW LENOX – The New Lenox Community Park District is moving forward with plans to redevelop Sharon's Bay Park, having approved a contractor for the project at its Wednesday meeting....
New-Lenox-School-122.5

Handbook Changes at D122 Include Swapping PSAT for PreACT

Students in New Lenox School District 122 will see several changes in the upcoming school year, as the Board of Education approved updates to the 2025-2026 Parent/Student Handbook that affect...
New-Lenox-Police.3

New Dining Options Coming as Village Approves Hot Dog Stand, Restaurant Patio

NEW LENOX – The local dining scene is set for a boost after the Village Board on Monday approved plans for a new hot dog stand and an outdoor patio...
Meeting-Briefs

Meeting Summary: New Lenox Park District for June 18, 2025

The New Lenox Community Park District Board of Commissioners met on June 18, 2025, to approve its annual budget, advance key park projects, and hear updates on a wide range...
Screenshot-2025-08-13-at-2.11.44-PM

Monee Board Sets Spending Plan with 2025-2026 Appropriations Ordinance

Article Summary: The Monee Village Board has approved its annual appropriations ordinance, which acts as the village's legal spending authority for the fiscal year that began May 1, 2025. The...
New-Lenox-School-122.3

New Lenox School District 122 Honors State Track and Field Athletes

New Lenox School District 122 took time during its June 17 board meeting to celebrate the outstanding achievements of its junior high athletes at the 2025 IESA State Track and...

Fiber Optic Internet Competition Coming to New Lenox

NEW LENOX – Residents may soon have a new choice for high-speed internet, as Champaign-based Pavlov Media announced its intention to build out a fiber optic network across the village....
Screenshot-2025-08-13-at-2.15.28-PM

Monee Officials Issue Pool Safety Alert Amid Summer Heat

Article Summary: Following an increase in new pool installations, Monee's Building Services department is reminding residents of mandatory permit and safety requirements. Officials are emphasizing life-safety measures to prevent drownings,...
New-Lenox-Village-Board

Village Board Approves Millions in Spending on Roads, Parks, and Museum

NEW LENOX – The New Lenox Village Board authorized millions of dollars in spending on Monday for its annual road program and for continued investment in its newest community amenities,...
Meeting-Briefs

Meeting Summary: New Lenox School District 122 Board of Education for June 17, 2025

The New Lenox School District 122 Board of Education handled significant financial business at its June 17 meeting, approving a tentative budget for the 2025-2026 school year and renewing insurance...