Will County Land Use & Development Committee Meeting | November 6, 2025

Article Summary: The Will County Land Use and Development Committee granted 180-day extensions for two commercial solar energy projects in Crete and Washington Townships, giving the developer additional time to complete the necessary permitting before their initial approvals expire.

Solar Farm Permit Extensions Key Points:

  • A first extension was approved for a TPE Development affiliated project in Crete Township (ZC-23-108), pushing its deadline to June 19, 2026.

  • A first extension was also granted for a related TPE project in Washington Township (ZC-24-020), moving its deadline to November 12, 2026.

  • The extensions were requested to allow more time to complete complex permitting and pre-construction processes.

  • Special use permits for solar facilities in Will County typically expire after two years if construction has not legally commenced.

JOLIET, IL — Two large-scale solar energy projects in eastern Will County were granted more time to get off the ground after the Will County Land Use and Development Committee on Thursday, November 6, 2025, approved their first 180-day permit extensions.

The committee unanimously approved the requests for projects in Crete and Washington townships, both associated with TPE Development, LLC. The extensions are necessary because the special use permits approved by the County Board are set to expire within the next year, and the projects have not yet completed the building permit process to legally establish the use.

The first extension was for case SEXT-25-019, concerning a commercial solar facility at the southeast corner of South Nacke Road and West Loves Lane in Crete Township. Originally approved on December 21, 2023, the permit was set to expire in December 2025. The applicant has applied for a building permit but cited needing more time to complete the process. The extension is now valid through June 19, 2026.

The second approval was for case SEXT-25-020, for a solar facility at the southeast corner of West Indiana Avenue and South Western Avenue in Washington Township, near Beecher. This project was approved on May 16, 2024, and its permit was set to expire in May 2026. According to county staff, the applicant has not yet applied for a building permit. The extension pushes the new expiration date to November 12, 2026.

Under the Will County Zoning Ordinance, a special use permit lapses after two years if the use has not been legally established. The ordinance allows the County Board to grant up to four separate 180-day extensions for “good cause.” Jordan Belknap, representing the applicant, stated they have been working with local authorities, including University Park, on necessary road improvements for the Crete project before construction can begin.

Events

No events

Leave a Comment





Latest News Stories

Screenshot 2025-11-03 at 11.39.46 AM

New Lenox Demands Over $422,000 From Developer to Complete Public Improvements

Village of New Lenox Board of Trustees Meeting | September 22, 2025 Article Summary: The Village of New Lenox is taking formal action to secure funds for unfinished public infrastructure...
new-lenox-fire-district-stations.4

New Lenox Fire District Pays Off Final Loan, Secures $75,000 State Grant

New Lenox Fire Protection District Meeting | August 2025 Article Summary: The New Lenox Fire Protection District has achieved a significant financial milestone by making the final payment on its...
New-Lenox-Sharons-Bay-Park

Damaged Drain Tiles at Bristol Park Face $107,000 Repair Bill

New Lenox Community Park District Meeting | August 2025 Article Summary: A comprehensive survey of the drainage system at Bristol Park has revealed that all of the clay tiles are...
Screenshot 2025-11-03 at 11.31.47 AM

New Lenox and Homer Glen Renew 20-Year Boundary Agreement, Defining Future Growth

Village of New Lenox Board of Trustees Meeting | September 22, 2025 Article Summary: The New Lenox Village Board has approved a new 20-year intergovernmental boundary agreement with the Village...
New-Lenox-School-122.5

New Lenox School Board Reviews $500,000 Nelson Campus Playground Proposal

Meeting Summary and Briefs: New Lenox School District 122 Meeting | August 2025 Article Summary: The New Lenox School District 122 Board of Education reviewed a proposal to partner with...
Joliet-Junior-college.-Graphic-Logo.4

JJC Board Approves Contract with Adjunct Faculty Union

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College (JJC) Board of Trustees approved a new collective bargaining agreement with the Joliet United Adjuncts...
New Lenox Park District.2

New Lenox Park District Golf Course Shatters Records with Busiest July Ever

New Lenox Community Park District Meeting | August 2025 Article Summary: The New Lenox Community Park District's golf course experienced its most successful month on record in July 2025, overcoming...
Meeting Briefs

Meeting Summary and Briefs: New Lenox Township Board of Trustees for August 14, 2025

New Lenox Township Board of Trustees Meeting | August 14, 2025 The New Lenox Township Board focused on community welfare and employee benefits at its meeting on August 14, 2025....
Illinois’ gun ban set for oral arguments in appeals court Monday

Illinois’ gun ban set for oral arguments in appeals court Monday

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – The state of Illinois will be defending its gun and magazine ban Monday in front of the...
Law professor explains why Trump could win tariff case

Law professor explains why Trump could win tariff case

By Brett RowlandThe Center Square The U.S. Supreme Court could side with the Trump administration on a multi-billion dollar case over tariffs despite two lower courts saying the power of...
New Lenox Park District

New Lenox Park District Holds Hearing on Potential $1.5 Million Bond Sale for Future Projects

New Lenox Community Park District Meeting | August 2025 Article Summary: The New Lenox Community Park District is exploring a significant capital funding measure, holding a public hearing on a...
New-Lenox-School-122.6

New Lenox School District 122 Approves $908,900 Equipment Purchase for Tyler Elementary HVAC Overhaul

Meeting Summary and Briefs: New Lenox School District 122 Meeting | August 2025 Article Summary: The New Lenox School District 122 Board of Education has authorized the pre-purchase of $908,900...
Joliet-Junior-college.-Graphic-Logo.3

JJC Board Approves Student Trustee Quorum Policy Amid Heated Debate

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College Board of Trustees passed a controversial policy change allowing the student trustee to be counted...
WATCH: Los Angeles schools superintendent renews contract

WATCH: Los Angeles schools superintendent renews contract

By Esther WickhamThe Center Square The Los Angeles Board of Education unanimously voted this week to renew its four-year contract with Los Angeles Unified School District Superintendent Alberto Carvalho, amid...
Southern California Edison works on paying Eaton Fire victims

Southern California Edison works on paying Eaton Fire victims

By Dave MasonThe Center Square Southern California Edison, which many blamed for starting the destructive Eaton Fire in the Pasadena/Altadena area, is developing a program to reimburse victims. The utility...