Will County Board Land Use Committee Graphic.4

Will County Committee Grants Extensions for Crete, Washington Township Solar Projects

Spread the love

Will County Land Use & Development Committee Meeting | November 6, 2025

Article Summary: The Will County Land Use and Development Committee granted 180-day extensions for two commercial solar energy projects in Crete and Washington Townships, giving the developer additional time to complete the necessary permitting before their initial approvals expire.

Solar Farm Permit Extensions Key Points:

  • A first extension was approved for a TPE Development affiliated project in Crete Township (ZC-23-108), pushing its deadline to June 19, 2026.

  • A first extension was also granted for a related TPE project in Washington Township (ZC-24-020), moving its deadline to November 12, 2026.

  • The extensions were requested to allow more time to complete complex permitting and pre-construction processes.

  • Special use permits for solar facilities in Will County typically expire after two years if construction has not legally commenced.

JOLIET, IL — Two large-scale solar energy projects in eastern Will County were granted more time to get off the ground after the Will County Land Use and Development Committee on Thursday, November 6, 2025, approved their first 180-day permit extensions.

The committee unanimously approved the requests for projects in Crete and Washington townships, both associated with TPE Development, LLC. The extensions are necessary because the special use permits approved by the County Board are set to expire within the next year, and the projects have not yet completed the building permit process to legally establish the use.

The first extension was for case SEXT-25-019, concerning a commercial solar facility at the southeast corner of South Nacke Road and West Loves Lane in Crete Township. Originally approved on December 21, 2023, the permit was set to expire in December 2025. The applicant has applied for a building permit but cited needing more time to complete the process. The extension is now valid through June 19, 2026.

The second approval was for case SEXT-25-020, for a solar facility at the southeast corner of West Indiana Avenue and South Western Avenue in Washington Township, near Beecher. This project was approved on May 16, 2024, and its permit was set to expire in May 2026. According to county staff, the applicant has not yet applied for a building permit. The extension pushes the new expiration date to November 12, 2026.

Under the Will County Zoning Ordinance, a special use permit lapses after two years if the use has not been legally established. The ordinance allows the County Board to grant up to four separate 180-day extensions for “good cause.” Jordan Belknap, representing the applicant, stated they have been working with local authorities, including University Park, on necessary road improvements for the Crete project before construction can begin.

Events

No events

Leave a Comment





Latest News Stories

Screenshot 2025-10-10 at 11.52.52 AM

Will County Board Backs Effort to Rename ‘Stigmatizing’ Chicago Sanitary and Ship Canal

Will County Executive Committee Meeting October 9, 2025 Article Summary: The Will County Board has thrown its support behind a regional effort to rename the Chicago Sanitary and Ship Canal,...
Screenshot 2025-10-10 at 12.12.04 PM

Access Will County Dial-a-Ride on Track for Full County-Wide Service in 2026

Will County Public Works & Transportation Committee Meeting October 7, 2025 Article Summary: The Access Will County dial-a-ride program is set for a major expansion in 2026, with plans to...
WCO 2025-09-27 at 9.04.36 AM

Divided Will County Board Authorizes Condemnation for 143rd Street Widening

Article Summary: Following intense debate and emotional public testimony, the Will County Board narrowly approved a resolution to begin condemnation proceedings for the controversial widening of 143rd Street in Homer...
Screenshot 2025-10-10 at 11.39.44 AM

Will County Committee Approves Preliminary $161.6M Tax Levy on Split Vote Amid Heated Debate Over Spending

Will County Finance Committee Meeting October 7, 2025 Article Summary: The Will County Finance Committee on Tuesday narrowly approved a preliminary $161.6 million property tax levy for 2025, which projects...
Screenshot 2025-10-10 at 11.36.42 AM

Will County Eyes Major Overhaul to Consolidate Scattered Government Offices

Will County Capital Improvements & IT Committee Meeting October 7, 2025 Article Summary: Will County officials are formally debating a new facilities master plan to address aging buildings and dozens...
Screenshot 2025-10-10 at 11.20.27 AM

Sheriff’s Office Reports Crime Down 10%, Cites Body Cam Footage as Main Challenge of Safety Act

Will County Public Health & Safety Committee Meeting October 2, 2025 Article Summary: The Will County Sheriff's Office reported a nearly 10% overall drop in crime compared to the same...
Screenshot 2025-10-10 at 11.52.24 AM

Will County Considers Moving Land Use Public Hearings Away from Full Board Meetings

Will County Executive Committee Meeting October 9, 2025 Article Summary: A proposal to move the final public hearing for zoning and land use cases from the full Will County Board...
WCO 2025-09-27 at 9.04.36 AM

Meeting Summary and Briefs: Will County Board for September 18, 2025

The Will County Board navigated a contentious meeting on September 18, 2025, marked by narrow votes on two highly debated land use issues in Crete and Homer Glen. The board...
Meeting Briefs

Meeting Summary and Briefs: Lincoln-Way Community High School District 210 Board of Education for September 18, 2025

The Lincoln-Way Community High School District 210 Board of Education on Thursday, September 18, 2025, formally adopted a $172.7 million budget for the 2025-2026 school year. The budget includes a...
lincoln way school district 210 logo.1

Lincoln-Way 210 to Launch District Literacy Plan, Expands Community Partnerships

Article Summary: As part of its strategic plan, Lincoln-Way High School District 210 is developing a comprehensive literacy plan to embed critical thinking skills across the curriculum. The district is also...
WCO 2025-09-27 at 9.05.04 AM

County Board Abates Over $25 Million in Property Taxes for Bond Payments

Article Summary: Will County property taxpayers will be spared over $25 million in taxes for the 2026 payment year after the County Board voted to abate taxes for six separate...
Screenshot

Lincoln-Way 210 Prepares for “Retirement Wave” with Focus on Recruitment

Article Summary: Lincoln-Way High School District 210 is bracing for a significant number of retirements, with 47 teachers expected to leave over the next four years, representing nearly a quarter of...
Meeting-Briefs

Meeting Summary and Briefs: Village of New Lenox Board of Trustees for September 22, 2025

Village of New Lenox Board of Trustees Meeting | September 22, 2025 The New Lenox Village Board, meeting on September 22, 2025, with Trustee Keith Madsen presiding in the mayor's...
lincoln way school district 210 logo.2

Lincoln-Way Board Weighs Community Solar Program Promising $155,000 in Annual Savings

Article Summary: The Lincoln-Way District 210 board is considering a 20-year agreement to participate in a state-sponsored community solar program that could save the district an estimated $155,000 annually on electricity...
Meeting Briefs

Meeting Summary and Briefs: New Lenox Fire Protection District for August 2025

New Lenox Fire Protection District Meeting | August 2025 The New Lenox Fire Protection District Board of Trustees celebrated strong fiscal health and discussed project timelines at its meeting on...