New Lenox Village Board Meeting | November 10, 2025

Article Summary: The New Lenox Village Board approved several measures related to the Crossroads Sports Complex, including kitchen upgrades for its expanding restaurant and utility work to prepare for the construction of an adjacent hotel. The actions signal the facility’s evolution from a tournament-focused venue to a broader, seven-day-a-week operation.

Crossroads Sports Complex Key Points:

  • A change order was approved for a new kitchen display system to support the move to a full-service restaurant.

  • The board approved contracts to relocate utilities and construct retaining walls on the north side of the property for a new hotel.

  • A new use agreement was adopted to formalize the process for renting the facility for private events and parties.

The New Lenox Village Board on Monday, November 10, 2025, approved a series of contracts and agreements aimed at expanding operations at the Crossroads Sports Complex and preparing the site for a new hotel.

The board authorized a change order for an upgraded kitchen display system and printer for the complex’s restaurant. Scott, the facility’s manager, explained the new system is needed as the restaurant transitions from a concession-style operation to a full-service establishment with waitstaff. “This way that information could go directly to the bar and to the kitchen instead of writing it down or verbally giving that order in,” he said.

Mayor Tim Baldermann noted the plan is to “slow roll” the expansion to a seven-day-a-week restaurant to ensure it is done correctly.

In preparation for the hotel development on the north end of the property, the board approved two contracts with Northern Builders. The first is for the relocation of sanitary sewer and water lines that currently run underneath the proposed hotel footprint. The second, which required the board to waive the bid process, is for the construction of retaining walls to maximize the usable space on the narrow lot. Village officials stated the unanticipated wall construction would still fall within the original project budget.

Additionally, the board adopted a new use agreement to govern the rental of the facility for private functions like birthday parties and corporate events.

Events

No events

Leave a Comment





Latest News Stories

will-county-board.3

Leglislative Committee Meeting Briefs

Federal Grant Deadline Extended: The Surface Transportation Reauthorization deadline has been extended to May 30 for policy submissions, with both House and Senate committees actively seeking stakeholder input ahead of...
will-county-board.3

Speed Limits Reduced on Two Township Roads

The committee approved new speed zones for two township roads based on engineering studies showing current limits exceed safe driving speeds. Offner Road in Green Garden Township will have a...
will-county-board.2

Will County Finance Committee Approves Juvenile Detention Center Upgrades

Committee votes to keep facility operational, moves forward with compliance modifications Will County Finance Committee members voted unanimously Monday to recommend keeping the River Valley Detention Center operational and making...
will-county-board.2

Major Grade Separation Projects Advance with Engineering Contracts

The committee approved two significant engineering agreements for major railroad overpass projects totaling over $4 million. TranSystems Corporation received a $4,003,256 contract for construction engineering services on the Lorenzo Road...
County-Board-Room

County Authorizes Condemnation for Francis Road Project

The committee authorized the State's Attorney's Office to proceed with condemnation cases for right-of-way acquisition needed for Francis Road improvements between Gougar Road and Interstate 80. Eight property parcels are...
will-county-board

Solar Farm Access Approved for Manhattan-Arsenal Road

The committee granted access approval for a solar farm development on Manhattan-Arsenal Road approximately 1,000 feet east of Cherry Hill Road. The MCH Solar 1 project, developed by Soltage LLC,...
will-county-board.3

Will County Finance Committee Meeting Briefs

Budget Transfers Approved: The Finance Committee approved transferring $18,643 within the Supervisor of Assessments budget to move funds from software licensing to computer hardware purchases. Animal Protection Services Funding: Committee...
will-county-board.2

Public Works Committee Briefs

Major Projects Update: Construction continues on several major projects including the 80th Avenue expressway overpass, Laraway Road widening near Cedar Road, and Bell Road improvements. The Bell Road project at...
will-county-board

Capital Improvements & IT Committee Briefs

Bed donation program: Will County donated old beds from Sunny Hill Nursing Home to Joliet Junior College and Project Cure after the nursing home received all new beds for residents....
Frankfort-Village-Board-Meeting-Graphic

Frankfort Board Approves New Wendy’s on Route 30 With Numerous Modifications

A new Wendy's restaurant is set to be built at the northwest corner of U.S. Route 30 and Frankfort Square Road after the Frankfort Village Board unanimously approved the project...
Frankfort-Village-Board-Meeting-Graphic

Historic Downtown Frankfort Property Granted Deck and Patio Variances

The owners of a historic mixed-use building in downtown Frankfort have received approval for six zoning variances to construct a new paver patio and a second-floor rear deck. The Frankfort...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves $1.3 Million in Bills, Including Annual Insurance Payment

The Frankfort Village Board authorized over $1.3 million in payments at its meeting Monday, with nearly half of the total amount covering the village's annual insurance premiums. Trustees unanimously approved...
Meeting-Briefs

Meeting Briefs: Frankfort Village Board for June 2, 2025

Wendy's Project Approved with Multiple Variances: The Village Board gave final approval for a new Wendy's restaurant at U.S. Route 30 and Frankfort Square Road. The project required a major change...
frankfort-park-district.1

Frankfort Park Board Holds Closed-Door Talks on Five Oaks HOA Dispute

The Frankfort Park District Board of Commissioners entered into a closed executive session on Tuesday, May 27, to discuss pending litigation concerning the Five Oaks Park parcel, signaling a deepening...
Frankfort-Township-Logo-Graphic

Frankfort Township Approves Employee Raises, Details Major Infrastructure and Service Projects

Frankfort Township employees will receive a 2.5% cost-of-living pay increase after the Board of Trustees unanimously approved the adjustment at its Monday, May 19 meeting. The move came as Supervisor...