Station 62 Remodel Advances as Fire District Seeks to Waive Permit Fees
New Lenox Fire Protection District Meeting | September 2025
Article Summary: The planned remodel of New Lenox Fire Station 62 is moving into its next phase, with officials having completed soil boring at the site and planning to apply for building permits in October. To manage costs for the multi-million dollar project, the district has formally asked the Village of New Lenox to waive its permit fees.
Station 62 Remodel Update Key Points:
-
District officials, including Trustee Keith Popp, met with construction manager Northern Builders.
-
Soil boring tests were recently completed at the station site.
-
The district plans to formally apply for building permits for the project in October.
-
A request has been submitted to the Village of New Lenox to waive the permit fees.
Progress on the New Lenox Fire Protection District’s remodel of Station 62 continues, with key preliminary steps now complete, the Board of Trustees learned on Monday, September 22, 2025.
According to a project update, Trustee Keith Popp and district attorney John Motylinski met with representatives from the project’s construction manager, Northern Builders, on the preceding Friday. On that same day, crucial soil boring tests were conducted at the station site to ensure the ground is suitable for the planned addition.
With the initial site work done, the district is preparing to submit its official application for building permits to the Village of New Lenox in October. In an effort to control costs for the extensive project, which was previously estimated at around $4 million, the district has asked the village to waive its permit fees.
Trustees expressed optimism about the project’s direction. “Looking forward to a relationship with Northern Builders,” Trustee Levey commented. Trustee Popp added, “Working with Northern Builders on St. 2 is going well.”
Latest News Stories
Pursuit following railroad theft ends in New Lenox; one suspect at large
Waste Management Commits to Expanded Litter Patrols Around Landfill
County Approves $22 Million in Road Projects for Lorenzo Road and Mills Road
Landfill Committee Advances Plan to Purchase Fourth Compressor for RNG Plant
Will County Commits $15M to Transfer Sanitary District Operations to City of Joliet
Attorneys review Chicago Teachers Union audits following congressional request
DHS: ICE agent shoots, kills armed Minneapolis man; protests erupt
‘They deserve their story’: Bill aims to open foster care files
Under Trump, Big Bend CBP Sector in Texas making history
Meeting Summary and Briefs: Lincoln-Way 210 Board of Education for Jan. 15, 2026