Estimated power demand will outstrip supply by 2032

Estimated power demand will outstrip supply by 2032

Spread the love

(The Center Square) – The impact on electricity demand from a growing number of data centers is a recurring point of concern among energy leaders who warn that, without swift policy reform, unchecked growth could drive up costs and threaten reliability.

A recent briefing hosted by nonprofit consumer watchdog Citizens Utility Board of Illinois, or CUB, explored the issues facing the PJM region.

Panelists from CUB and the Natural Resources Defense Council, or NRDC, suggested potential solutions that would protect consumers and acknowledged an urgent need for coordinated action, they say, to contain costs and safeguard reliability.

CUB’s Jim Chillsen noted that consumers are often unaware their electric bills include capacity charges – payments that cover the power they use, but also the cost of maintaining extra generation for times of peak demand.

He highlighted that after years of flat consumption demand, PJM estimates that by 2031 data centers could add 22-30 GW of new demand, or enough electricity for more than 10 million homes, while expecting only 6-12 GW of new supply, or enough to power as many as 2.6 million homes. This imbalance, he said, has led to record-high capacity prices for which consumers will be paying for through at least May 2027 – something the panelists fear will become a “new normal.”

Without reforms, the NRDC estimates cumulative capacity costs could reach $163 billion from 2027 through 2033.

Claire Lang-Ree, NRDC clean energy advocate, stated that average utility bills have already increased by $20-$30 due to the price increase in the grid’s last auction, and it will get worse through the coming decade if nothing is done. “We’re estimating that average bills could increase by another $70 per month,” she added.

Panelists found fault with PJM’s Critical Issue Fast Path, or CIFP – an initiative launched in August to fast-track discussions and policy decisions aimed at managing rapid growth of large load customers like data centers.

The current proposal, they say, does not require data centers to reduce energy consumption during peak demand; rather, it is voluntary, which increases the risk of rolling blackouts.

They were also critical of the proposed 10-month fast track for new data center-related resources that would allow them to jump ahead in the interconnection queue, which is dominated by clean energy projects – some that have been waiting years for approval.

A better approach stressed Clara Summers, CUB’s Consumers for a Better Grid campaign manager, would require data centers to cover their own costs and bring their own capacity.

Lang-Ree added that by removing large loads out of the capacity market until they bring their own supply may bring capacity prices back down to historic levels of around $60 billion versus the $163 billion projected.

Other measures proposed include implementation of reforms such as separate tariffs, the need for accurate load forecasting, and incentives for new, fast-to-build, clean energy supply.

Stressing that accurate load forecasting is essential to controlling costs and maintaining reliability, she warned that many projects never get built, but their projected demand is used in pricing – driving up capacity pricing for everyone.

By requiring stricter standards such as financial commitments and proof of constructability from developers, consumers won’t be forced to pay for power that is never used, she said.

Summers also highlighted that battery storage is the fastest source to build. Citing analysis by Brattle, she said battery storage can be built in about 20 months or less, as opposed to a gas fired power plant which could take 44 to 50 months. She added that the batteries can store power from today’s resource mix to handle peak capacity needs and are just as reliable as a new gas plant.

Governors of PJM states are among the grid operator’s critics. They recently attended a summit convened by Gov. Josh Shapiro to discuss reforms and having a larger voice in PJM’s governance.

According to PJM, as of August, a total of 46,000 MW of new generation has signed interconnection agreements and are ready to construct, which once operational, could supply as many as 46 million homes. Many of the projects, however, are hampered by factors outside of their control – such as siting and permitting challenges, supply chain backlogs, and financial dynamics.

PJM’s stakeholders are scheduled to vote on a final proposal regarding the allocation of costs for new electric infrastructure on November 19.

Leave a Comment





Latest News Stories

New-Lenox-School-122.6

Liberty Musicians and Martino Runners Honored by School Board

New Lenox School District 122 Board Meeting | December 16, 2025 Article Summary: The Board of Education recognized student athletes and musicians for their state-level achievements in cross country and...
NL Library Graphic.2

New Lenox Library Board Approves 2026-2028 Strategic Plan, Reviews Master Building Plan

New Lenox Public Library District Meeting | Dec. 15, 2025 Article Summary: The New Lenox Public Library District Board of Trustees secured the facility's long-term direction by approving a new...
Dems fail in first try to use ‘state sovereignty’ to ‘veto’ ICE

Dems fail in first try to use ‘state sovereignty’ to ‘veto’ ICE

By Jonathan Bilyk | Legal NewslineThe Center Square As a federal judge in Chicago prepares to hear Illinois' and Chicago's lawsuit seeking to all but halt ICE and Border Patrol...
Illinois Quick Hits: McIntyre back as inspector general for DCFS

Illinois Quick Hits: McIntyre back as inspector general for DCFS

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Gov. J.B. Pritzker has reappointed Ann McIntyre to continue serving as inspector general for the Illinois Department...
Lawmakers discuss budget, spending, tax credits as Illinois Senate returns

Lawmakers discuss budget, spending, tax credits as Illinois Senate returns

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – The Illinois Senate Appropriations Committee chair says greater federal scrutiny of state government spending will not change...
IL lawmakers push discount drug legislation to prevent restricted access

IL lawmakers push discount drug legislation to prevent restricted access

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Illinois lawmakers are pushing an amendment to ban restrictions or interference with a federal discount drug program....
Chicago downtown office space vacancy rate ends year at record high levels

Chicago downtown office space vacancy rate ends year at record high levels

By Glenn Minnis | The Center Square contributorThe Center Square (The Center Square) – Wirepoints Executive Editor Mark Glennon warns Chicago’s dwindling business community could be riding into high-gear after...
Ex-Illinois candidate sides with Vance after Duckworth–Rubio clash

Ex-Illinois candidate sides with Vance after Duckworth–Rubio clash

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – U.S. Sen. Tammy Duckworth, D-Illinois, is facing fresh criticism after Vice President J.D. Vance likened her...
Illinois Quick Hits: Judge rules Cook County misspent $243M

Illinois Quick Hits: Judge rules Cook County misspent $243M

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – A circuit court judge has ruled that Cook County spent $243 million in violation of the Illinois...
Gregory A. Williams

Bolingbrook man charged after bringing loaded gun to Will County Courthouse

JOLIET – A Bolingbrook man is facing multiple felony charges after security officers discovered a loaded firearm in his possession at the Will County Courthouse last Tuesday. On the morning of...
Traffic Alert Graphic

Traffic Alert: Wolf Road water repairs rescheduled for Tuesday

MOKENA – Drivers traveling through Mokena should prepare for delays on Wolf Road tomorrow, as village officials have rescheduled planned water system repairs. The Village of Mokena announced that the infrastructure...
Planning & Zoning Graphic.3

Will County P&Z Forwards Monee and Manhattan Residential Projects

Will County P&Z Commission Meeting | Jan. 20, 2026 Article Summary: The PZC approved zoning requests facilitating residential improvements in Monee and Manhattan. The approvals allow for the construction of...
new-lenox-fire-district-stations.2

Fire District Adopts Ordinance Establishing Fees for Excessive Lift Assists

New Lenox Fire Protection District Meeting | Dec. 15, 2025 Article Summary: The Board of Trustees formally adopted a new ordinance aimed at regulating lift assist services within the district....
New Lenox Township.3

New Lenox Township Approves Tax Levies Totaling Over $5.2 Million

New Lenox Township Board Meeting | December 11, 2025 Article Summary: The Township Board approved the 2025 tax levies for both the township and the road district, alongside a bond...
Screenshot 2026-01-29 at 10.56.03 AM

Lakes Park and Spencer Meadows Subdivisions Move Forward

Village of New Lenox Meeting | January 26, 2026 Article Summary: Two residential developments, Lakes Park Phase 2 and Spencer Meadows Phase 1, passed their first reading before the New...