Commission Grants Green Garden Solar Farm Project Variance Extension

Spread the love

Will County Planning and Zoning Commission Meeting | November 4, 2025

Article Summary: The Will County Planning and Zoning Commission granted a 180-day extension for two variances related to a commercial solar energy facility in Green Garden Township, allowing the developer to wait for optimal planting conditions in Spring 2026 before proceeding. The variances, originally approved in March, concern the mowing schedule and plant height for the native pollinator habitat required for the project.

Green Garden Solar Farm Key Points:

  • The first-time extension was granted for variances associated with a 35-acre solar project on LaGrange Road near West Manhattan-Monee Road.

  • The variances reduce the required number of mowings from five to one per year and increase the maximum allowed ground cover height from 13 to 36 inches.

  • The developer requested the extension to allow time to prepare the site for planting a native pollinator seed mix in favorable spring conditions.

A commercial solar energy facility planned for Green Garden Township received a procedural timeline extension from the Will County Planning and Zoning Commission on Tuesday, November 4, 2025.

The commission approved a 180-day extension for two variances previously granted to applicant TPE IL WI258, LLC, an affiliate of TPE Development, LLC, for a 35-acre solar farm. The project is located on vacant property at the northeast corner of LaGrange Road and West Manhattan-Monee Road in Monee.

The variances, originally approved by the commission on March 4, 2025, are key to the project’s use of native plantings and agrivoltaics—the simultaneous use of land for agriculture and solar power generation. One variance reduces the required number of mowings from five times per year to just one, while the other increases the maximum allowable plant height from 13 inches to 36 inches. These changes are necessary to establish and maintain a healthy native pollinator habitat on the site, which is a requirement of the state’s community solar program.

According to a memo from county staff, the developer has not yet applied for a building permit because “favorable planting conditions for the site are not expected until after the variances expire on March 4, 2026.” The extension was requested to allow the developer time to prepare the site for planting in the spring of 2026.

The commission, which is authorized to grant up to two 180-day extensions for good cause, approved the request. The variances will now expire on August 31, 2026.

Leave a Comment





Latest News Stories

Screenshot 2025-11-27 at 7.18.58 PM

New Lenox Approves 24/7 Cybersecurity Monitoring

Village of New Lenox Meeting | Nov. 24, 2025 Article Summary: The New Lenox Village Board approved a new contract for around-the-clock cybersecurity detection and response to protect village financial...
Weather-Winter

New Lenox Buried Under 12.3 Inches of Snow; Sub-Zero Cold Snap Approaching Friday

Article Summary: New Lenox residents are digging out from a major winter storm that dropped more than a foot of snow over the weekend. The active weather pattern is forecast...
Will County Board Graphic.01

Frankfort Turns to County for Wildlife & Dangerous Animal Control

Will County Board Meeting | November 2025 Article Summary: The Village of Frankfort has entered into a two-year agreement with Will County Animal Protection Services to handle calls regarding bats...
joliet junior college foundation

JJC Foundation Director Kristin Mulvey to Retire After 25 Years of Transformative Leadership

Joliet Junior College Meeting | November 12, 2025 Article Summary:Kristin Mulvey, the longtime Executive Director of Institutional Advancement and the JJC Foundation, was honored by the Board of Trustees as...
nl-food-pantry-horizontal___22114454354

New Lenox Township Hires Full-Time Maintenance Position Amid Surging Food Pantry Demand

New Lenox Township Meeting | October 2025 Article Summary: The New Lenox Township Board of Trustees unanimously approved the creation of a new full-time maintenance position to help manage the...
under armor logo

Lincoln-Way 210 Switches to Under Armour for Athletic Apparel

Lincoln-Way Community High School District 210 Meeting | November 20, 2025 Article Summary: The Lincoln-Way District 210 Board of Education has approved a new 3.5-year agreement with BSN and Under Armour...
Screenshot 2025-11-27 at 7.18.21 PM

Baldermann Defends Investment Strategy, Blasts Social Media Critics

Village of New Lenox Meeting | Nov. 24, 2025 Article Summary: New Lenox Mayor Tim Baldermann issued a fiery defense of the Village Board's decision to suspend the property tax...
Will County Logo Graphic

Crete “Group Care” Home Approved for Senior Living

Will County Board Meeting | November 2025 Article Summary: The Will County Board unanimously approved a special use permit for a senior group care home in Crete Township. The facility...
Meeting Briefs

Meeting Summary and Briefs: New Lenox School District 122 for October 21, 2025

New Lenox School District 122 Meeting | October 21, 2025 The New Lenox School District 122 Board of Education held a public hearing and subsequently approved the issuance of up...
About Us Website Header - 1

New Lenox Library Reviews Strategic Plan Draft Following Robust Community Feedback

New Lenox Public Library District Meeting | October 20, 2025 Article Summary: The New Lenox Public Library District Board of Trustees is reviewing a draft of its 2026-2028 Strategic Plan,...
Meeting Briefs

Meeting Summary and Briefs: New Lenox Community Park District for October 15, 2025

New Lenox Community Park District Meeting | October 15, 2025 The New Lenox Community Park District Board of Commissioners on Wednesday, October 15, 2025, discussed plans for a future indoor...
will county board graphic

New Bar Approved in Frankfort Despite Board Opposition

Will County Board Meeting | November 2025 Article Summary: The Will County Board narrowly approved a special use permit for a new bar in Frankfort Township, paving the way for...
joliet junior college logo

JJC Board Approves Grundy County Land Purchase Amid Heated Debate

Joliet Junior College Meeting | November 12, 2025 Article Summary:The Joliet Junior College Board of Trustees voted 6-2 to approve a real estate contract for a new campus in Grundy...
Screenshot 2025-11-21 at 10.20.03 AM

Support Staff Urge Lincoln-Way 210 Board for ‘Fair Contract’ During Public Comment

Lincoln-Way Community High School District 210 Meeting | November 20, 2025 Article Summary: Three members of Lincoln-Way District 210's support staff addressed the Board of Education, voicing frustrations over working without...
New-Lenox-School-122.6

New Lenox SD 122 Approves Community Solar Agreement, Anticipates $62K in Annual Savings

New Lenox School District 122 Meeting | October 21, 2025 Article Summary: New Lenox School District 122 will join a community solar program after the Board of Education approved a...