New Lenox D122 Explores Life Safety Bonds to Fund $8M Tyler School HVAC Project

Spread the love

New Lenox School District 122 Meeting | September 2025

Article Summary: The New Lenox School District 122 Board of Education is considering issuing life safety bonds to fund the majority of an $8 million HVAC renovation at Tyler Elementary, with a financial presentation indicating a potential property tax increase of about $30 per year for the owner of a $400,000 home for the first eight years.

Life Safety Bond Proposal Key Points:

  • The district plans to issue life safety bonds to fund the $8M+ HVAC renovation at Tyler Elementary scheduled for summer 2026.

  • The tax impact is estimated at an additional $30 per year for a home with a market value of $400,000 for the first eight years of the bond.

  • A public hearing on the bond issuance is scheduled for the board’s October 21 meeting.

  • The district’s existing large bond debt is scheduled to be fully paid off in 2033, which officials noted as a celebratory milestone.

The New Lenox School District 122 Board of Education on Tuesday, September 16, 2025, reviewed a detailed financing proposal to fund the planned $8 million HVAC and facility modernization at Tyler Elementary School. The plan involves issuing life safety bonds, a move that would have a modest impact on local property tax bills.

Elizabeth Hennessy of Raymond James presented the proposed structure and timeline for the bond issuance. She explained that funding the project with life safety bonds would result in an approximate tax increase of $30 per year for a home with a market value of $400,000. This increase would apply for the first eight years of the bond’s term.

The funds are designated for the complete overhaul of Tyler Elementary’s mechanical systems, which date back to the school’s opening in 1980. The project is slated for the summer of 2026.

According to Hennessy, the proposed timeline for the bond issuance is aggressive to ensure funds are available for the project next summer. Key dates include a public hearing and review of the bond resolution at the October 21 board meeting, with a potential bond sale on November 24 and closing on December 11, 2025.

Business Manager/CSBO Robert Groos noted that this project is the final piece of a long-term plan to modernize the district’s oldest schools, a plan that has so far been funded entirely with cash reserves. “The District has completed about $36M in projects over the past 11 years, all paid for with cash,” the minutes recorded Groos as stating. However, the scale of the Tyler project requires bond funding.

Dr. Motsch, Superintendent, framed the upcoming payoff of the district’s larger, existing bond debt in 2033 as a significant achievement for the community. The new, smaller bond for the Tyler project is structured to have a minimal long-term impact on taxpayers, especially after the older debt is retired. The board took no action, as the presentation was for discussion purposes.

Events

No events

Leave a Comment





Latest News Stories

WCO-PZ-July-15

Crete Township Wins Approval for New Digital Sign at Community Center

Crete Township received approval from the Will County Planning and Zoning Commission on Tuesday for a new digital sign at its community center, a project that required a special use...
WCO-PZ-July-15

Will County Planners OK Oversized Garage Near Naperville, Overriding Staff Recommendation

The Will County Planning and Zoning Commission on Tuesday approved variances for a new oversized accessory garage in Wheatland Township, siding with a homeowner and builder over a staff recommendation...
WCO-PZ-July-15

Green Garden Landscaping Business Gains Permit Amid Strong Neighbor Support

A small landscaping and lawn maintenance business operating on a residential property in Green Garden Township received official approval Tuesday after neighbors voiced overwhelming support for the operation. The Will...
Meeting-Briefs

Meeting Briefs: Will County Planning and Zoning Commission for July 15, 2025

Frankfort Shed Relocation Approved: A homeowner on West Harvest Drive in Frankfort Township received a variance to reduce an east side-yard setback from 10 to 4 feet. The variance, sought by...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves ‘Whisk & Flame’ Culinary Studio, Slashes Parking Requirement for Downtown Property

An experiential culinary studio named Whisk & Flame is set to open in downtown Frankfort after the Village Board approved a series of special use permits and a significant parking...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Village Board Adopts $59.4 Million Appropriation for Fiscal Year 2026

The Frankfort Village Board has formally set its maximum legal spending limit for the upcoming fiscal year, adopting a $59,366,900 appropriation ordinance for fiscal year 2026. The measure was passed...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Establishes New Zoning Rules to Attract Data Centers

The Village of Frankfort has amended its zoning ordinance to create a specific use category for data centers, a move designed to regulate and attract high-tech development. The Village Board...
Frankfort-Village-Board-Meeting-Graphic

Currie Motors Expansion Gets Approval with Site Modifications

Currie Motors on Lincoln Highway received approval from the Frankfort Village Board on Monday for a major change to its site plan, allowing for the construction of seven new parking...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves $134,531 Maintenance Contract for Wastewater Plant Filters

The Frankfort Village Board has approved a $134,531.17 agreement with Veolia Water Technologies, Inc. for critical preventative maintenance at the Regional Wastewater Treatment Plant. The contract is for the complete...
Frankfort-Village-Board-Meeting-Graphic

Meeting Briefs: Frankfort Village Board for July 14, 2025

'Whisk & Flame' Culinary Studio Approved: The board approved "Whisk & Flame," an experiential culinary studio, for 10-12 Elwood Street. The project includes four special use permits for entertainment, liquor sales,...
WCO-Exec-Cmte-July-10.1

County Approves School Resource Officer, Multi-Year Planning Requirements

Will County approved hiring an additional sheriff's deputy for a school resource officer position that will be fully funded by Summit Hill School District 161, while also passing new transparency...
WCO-Exec-Cmte-July-10.2

County Addresses Senior Tax Exemption Processing Error

A processing error that cost County Board member Julie Berkowicz $600 in senior tax exemptions has prompted discussions about improving verification systems for property tax breaks. Will County Chief Assessment...
Meeting-Briefs

Executive Committee Meeting July 10 Meeting Briefs

Liquor License Expansion: The county approved increasing Class C1 liquor licenses from eight to nine to accommodate Lockport Gas and Food LLC at 14747 W. 159th Street in Homer Glen....
frankfort-park-district

Meeting Briefs: Frankfort Park District Board for June 10, 2025

The Frankfort Park District Board of Commissioners discussed a legal dispute with the Five Oaks homeowners association over park development rules at its Tuesday meeting. Executive Director Gina Hassett reported...
Will-County-Land-Use-July-3.1

Committee Rejects Troy Township Solar Projects Amid Strong Local Opposition

The Will County Land Use and Development Committee recommended denial for two controversial commercial solar energy projects in Troy Township on Thursday, following a wave of opposition from local municipalities,...